Angus Website Updated New Questions28 Nov 2021 20:30
When will the full remap images of Saltfleetby be available, and would you buy/lease further equipment to enhance production from other areas of the licence. Thankyou.
Asked on 8 November 2021
40 %
Can you clarify how things stand in relation to Balcombe, please.
In your RNS of 02/08/21, you wrote that Angus will be making its appeal to the Planning Inspectorate and is presently preparing its statement of case.
But hasn’t the delay for submitting this appeal now expired?
Thank you.
Asked on 25 November 2021
20 %
What is the latest estimated schedule for drilling the sidetrack? Thank you.
Asked on 25 November 2021
13 %
Civil Works
We havent seen any evidence of civil works starting at SFB. Concrete foundations will be required for the equipment and ISBL pipe work.
Equipment power generator & switchgear was planned to arrive in October, Separators storage tanks & ground flare was planned to arrive this month November, Gas compressor also in November – see 11 August 2021 RNS No. 34411.
Having all the necessary foundation completed will save time. Can you please clarify as to whether the civil works have started? If not, why not? Thank you.
Asked on 25 November 2021
13 %
Will Angus be updating the Saltfleeby build and delivery schedule due in November?
Asked on 25 November 2021
13 %