RE: Site Visit Takeaway Point No.715 Sep 2022 16:04
OK, now the dust has settled, did anything concrete come out of the site visit? ie Timelines etc like on the 29th Feb we start clearing the site for the helical incline or the "Jumbos" will be delivered on the 31st of November, its great having ideas, plans and ambitions, but I really want to get back in soon when we have a "Copper bottom" guarantee of some real progress, we have seen the core samples, we have seen the upturned hull model, we have seen the refining plant area, with the plans for the associated tunnel under the B5111, we have seen the Morris shaft, The winding gear, the head frame we have talked endlessly about shipping out to refiners by road, sea and rail, we have seen the plans for the Helical incline and which zones will be targeted 1st, I guess we have all looked at QME mining website, but what we appear to be missing is a timeframe, some accountable milestone dates