Notes from Vox interview for continued high-grade iron ore results at Han**** - 04 Feb 20224 Feb 2022 14:21
Interview: https://audioboom.com/posts/8025391-bill-brodie-good-of-alien-metals-discusses-the-continued-high-grade-iron-ore-results-at-the-hanco
RNS: http://www.rns-pdf.londonstockexchange.com/rns/6709A_1-2022-2-3.pdf
Download: https://www.mediafire.com/file/b164ob1sxgmzs2v/Notes_from_Vox_interview_for_continued_high-grade_iron_ore_results_at_Han****_-_04_Feb_2022.pdf/file
* Overview of current projects?
- 3 main projects:
1/ Iron Ore in Pilbara, WA
2/ along with EH/Munni Munni also in Pilbara for Silver, Copper, Nickel and PGE’s also gaining momentum
3/ and Silver/Copper projects in Mexico hopefully advancing very soon.
* Update on latest HG (high grade) iron ore results in Han****?
- Phase 3 drilling in progress undertaking more resource drilling to increase resource from Inferred to Indicated
- Tested some new targets, 10.5Mt already defined as HG at plus 60%, but only scratched surface in terms of potential
- Had a couple of machines on site as part of the scope of work so decided to take a bulk sample to advance mining development aspect of the project, took a bulk 2.4 ton sample from a pit from one of the drill platforms from the middle of Ridge C resource
- Took 9 piles of dirt from each level as they went down into pit with machine and gathered representative samples and quickly had them assayed at the lab to ensure consistency of grade
- Fantastic results, 8 out of 9 averaged 62.2% and the top result was at surface where we expected a lower grade but still came back in at 59.8%, very exciting and now have a good sized bulk sample at labs for metallurgical testing to improve knowledge of mining processes, product yields and also generate customer samples for potential offtake partners (with several in talks already) for due diligence testing.
* Timeline of news and events and expectations for the next year?
- This time next year Lloyd would like to be at a ‘shovel ready’ production status at Han**** with all permitting in place with necessary infrastructure, not much required as essentially a haul road
- Everything else is to be supplied by contractors such as mining equipment, processing of screening and crushing (crushing unlikely though) and haulage to Port Hedland
- In meantime have another big drilling plan ready for after the wet season but currently doing metallurgical testing, analysing results, planning and securing appropriately more nimble and agile drilling machines that can roar around on new ridges for quick holes while background team getting on with permitting and the Mining Plus team work on mine development
- This is just for Han****, by mid 2022 plan to get some holes into Brockman and bring that project up to speed and feel it has as much, if not more potential than Han****.
Contd....