RE: Coal Resource High time to utilise cheaper Energy 5 Apr 2024 08:57
(Q) Mollah Amjad: Barapukuria was supposed to produce about 64 mill tons over 32 years at $34 a ton, but Barapukuria coal is now dearer than imported coal at $176. Should new mines be through a Public Ltd Co or a Private Co?
(A) Kamruzzaman (Bara): Barapukuria still generates affordable electricity, even at $176. However, it may not be possible to conduct coal extraction through a government company. That’s true. It’s not possible to follow government procurement rules. A foreign company can do it in a joint venture with a local company. This way, technology transfer can happen.