2nd Q was from Charlie Sharp at Canaccord
Yes. Good morning. Thanks for taking my question. Just two small questions, if I may. Firstly, on the water handling, what’s the critical path item or items that we should be sort of on the lookout for in terms of the timing to have that work completed? And then secondly, on the field development plan, are there any sticking points? It seems as though in the past, you have been quite close to getting approval, I just wonder if there are any sort of particular outstanding issues?
A from Jon Harris
Okay. The first one on critical path for water handling, we are kind of pursuing two routes with that. One is, we are looking at getting an existing unit that was basically produced for somebody else who then decided they didn’t want it. So, that’s an existing piece of equipment. However, that’s only one part of kind of processing train. So, we also have to look at water heaters to heat the oil, so that we can affect separation. And also there is a whole bunch of utilities that go with that. So, I would say in that particular path, the critical path is through the water heater, and the utilities and not actual critical piece of equipment. The second path we are going for is we have gone out to tender for new build items, a new build water handling package…and that critical path is through the tendering and construction probe process once we selected somebody. So, hopefully that answered that question. Your second question was around, are there any particular sticking points within the FDP, I don’t actually think so. I think we are just working towards kind of an agreed level of activity with the state. And essentially, it’s like it’s a refinement point, so, I wouldn’t say that we don’t think we can close out on the agreed scope for the next – the first 1st phase of the field development plan. So, I don’t think there is any particular sticking points, I think we will get there.