Kosmos Energy Ghana update from May 11th6 Jun 2020 08:16
Relevant....as TLW the operator, obv.
1 - "the new Ntomme-09 producer well is undergoing completion operations ahead of start-up later in the current quarter".
2 - gas offtake ....problem resolved as national gas co. buying up TLW's gas...
DALLAS – Kosmos Energy says its production offshore Ghana has not been severely disrupted by COVID-19.
The deepwater Jubilee gas enhancement project was completed in February with subsequent rates of around 90,000 b/d achieved. Currently operator Tullow Oil is raising water injection capacity from two pumps, which should provide necessary pressure support for the reservoir; a third pump is also available.
In addition, gas offtake from the Ghana National Gas Co. has been consistent at around 90,000-100,000 MMcf/d, which should help sustain higher oil rates in future.
Production from the TEN field is currently above 50,000 b/d and the new Ntomme-09 producer well is undergoing completion operations ahead of start-up later in the current quarter.