RE: Dundas2 Feb 2023 18:01
Dundas has been undergoing optimisation since June 2019; quite a long time (see the rns dated 27th June).
$7m was raised in March last year to complete the optimisation and feasibility study (see the rns dated 24th March 2022). In that rns it was stated: 'The Company will commence works at Dundas this forthcoming field-season to complete the necessary engineering, geo-technical and planning activities, including evaluation of an optimised mine schedule for production.'
Since then there was a brief and vague update in the interims in September when it was also stated: 'We expect to provide a further and fuller update in Q4 2022'.
They may have expected it, but personally I didn't. For transparency, I am a former investor here who lost money, so call me bitter and twisted if you like, but imo the record of non delivery here has been truly remarkable.