RE: Morocco aims to become the world’s premier fertiliser producer17 Nov 2022 14:38
Work done / ongoing. According to the update in July. All C&P form the article posted recently.
1, further drilling of deep holes was supplemented by directional drilling and four additional ERT surveys. The deeper drill holes had the dual purpose of further understanding the lithography around the declines to assist in finalising the precise siting for key infrastructure to take advantage of the most competent ground conditions.
2, The new portal location was approved as the go-forward case for more detailed engineering, the company said.
3, “Engineering is well under way on each of the key infrastructure areas. Civil and structural work has now commenced following the decisions made with regard to mine site and portal locations,”
4, In conjunction with Reminex, an improved solution for process plant water supply was investigated in detail and approved as the go-forward case for further design work.
5, Meanwhile, the power strategy for the mine was more clearly defined during the quarter, with the main feed onto site, backup feed and substation now confirmed. Emmerson said engagement with State-owned utility ONEE would now move forward to develop key design criteria.
6, In terms of other infrastructure, Emmerson engaged with a specialist consultant to assist in the design of the highway connection, after which a baseline study was completed to understand local transport characteristics such as travel directions and distances, traffic, air pollution or quality of roads, as well as to assess the impact of the future mine.
7, finance, This work was ongoing, the company said, with options for the location of the road junction already identified and under discussion with the relevant government bodies to achieve the best outcome.