ESIA16 May 2023 18:57
No holder enjoys days like these when the SP tanks but we really are in the hands of the Moroccan authorities.
Graham Clarke was brought in to build & run a mine. He has years of experience doing this & is a perfect fit.
So why are we not building the mine?
A couple of reasons combined has held this back,
1, The Moroccan mining licencing rules changed in 2020 meaning the ESIA was far more important than it was before. EML are on the 4th application, we have an experienced approvals manager brought in especially to get the ESIA passed (Hajar Alaoui), was brought in April 2022).
2, Morocco is currently in the worst drought for 40yrs, currently reservoir levels are below 25% & this is after the rainy season. Of course they have to be careful conserving water & making sure there is zero contamination from the mining tailings. EML have offered solutions, hopefully they are enough to get the permit granted.
If you read the last RNS, it sounds like (or at least to me), that GC was hoping to be in position to announce the permit, meaning he believes it could land anytime.
The good news is while EML have been waiting pre construction work has been continuing. This work was always going to be needed to be done so time wise it will not have too much of a detriment to the actual mine construction.
While it is frustrating, I am happy to wait, GC has always said Morocco is fully supportive of the project & mining licences have been granted. Everyone involved in EML has been frustrated by the wait, but I cannot see what more they can do other than wait & answer any queries the Moroccan gov have swiftly which I am sure they are doing.
GLA