RE: Piled into GCAT: low AISC, production up, royalty financing more than mcap + JV coming. Soon 2 producing projects. £100mil mcap target10 Aug 2023 17:13
BaniJuhina,
I was referring specifically to the RNS results for Q2 2023, this is the official results the company itself has published and any discrepancies with the numbers is down to the company itself.
This is a recorded past event, therefore any corrections must be through an issue of another RNS and definitely not through any interview or the like.
Mining
· The underground mine remained on care and maintenance,
· A total of 38,011 high-grade tonnes were mined from the open pit @ 2,51 g/t,
· A total of 18,394 low-grade tonnes were mined from the open pit @ 1,55 g/t,
They mined a combined total of (38,011 + 18,394) 56,405t
April May June
Mined 15,000 + 18,660 + 19,970 53,630t
Treated 16,819 + 17,210 + 16,691 50,720t
Smelted 640 + 526 + 479 1,645oz
Processing
· The milling plant processed a total of 38,543t at an average grade of 2.23g/t,
· The heap leach plant processed a total of 12,177t at an average grade of 1.26g/t
The mined tonnage has lost 2,775 t from grades to the monthly table.
With the above information I am able to show a loss of 49.52% ( which is an approximate) between the processing and smelting operations.
Using the same data, I'd like you to show the 75% you talk of or just show where I've got it wrong please.