RE: Investment Report: Newmont's Asset Divestiture and the Havieron Project5 Aug 2024 08:21
From the PFS
For 2mt pa operation
A$529m (US$389m) total cost:-
A$146m (US$112m) for the Box cut, Exploration Decline, surface infrastructure, initial road service corridor, 3 ponds.
A$383m :-
Plant modifications, road, utilities, underground mine infrastructure down to 750m below the cover, Paste plant and paste fill.
As it’s a top down operation, the initial revenues pay for ongoing works and is a low cost effective process. It’s not A$383m to paid all at once it’s a gradual draw down.
(Ggp not liable for the plant modifications or the latest tailings dam lift. These are included in the total cost.)
What isn’t in the total cost sum is the increase to 3mt, which is additional decline infrastructure, drilling outside of the PFS 2mt operation, associated underground infrastructure and additional paste fill ( all from revenues ongoing).