Drill results31 Dec 2021 07:14
When you look back at the years drill results the shear numbers of drills has been quite staggering .
Dec 2020
Total of 128,559m from 134 drill holes
65,000m planned till June
Jan 2021
Total of 138,504m from 153 drill holes
Jun 2021
Total of 164,420m from 190 drill holes
Dec 2021
Total of 219,561m from 266 drill holes
Plus around 10,000m 10 holes completed assays pending.
90,000m planned till June
That’s around 100,000m completed drilling.
35,000m more than planned.
Nearly 2/3rds more than planned.
First tranche of the NCM loan $20m was to cover this drilling and construction.
It’s no wonder they needed another $10m.