Cobus Loots, CEO of Pan African Resources, on delivering sector-leading returns for shareholders. Watch the video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAmur Minerals Share News (AMC)

  • This share is currently suspended. It was suspended at a price of 0.09

Share Price Information for Amur Minerals (AMC)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 0.09
Bid: 0.00
Ask: 0.00
Change: 0.00 (0.00%)
Spread: 0.00 (0.00%)
Open: 0.00
High: 0.00
Low: 0.00
Prev. Close: 0.09
AMC Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Amur Minerals outlines plan for Kun-Manie feasibility study

Wed, 24th Jun 2020 11:17

(Sharecast News) - Nickel-copper sulphide exploration and development company Amur Minerals Corporation updated shareholders on its strategy for the compilation of the bankable feasibility study on its Kun-Manie nickel-copper sulphide project in Russia's far east, which it noted was adjacent to the largest nickel consuming nations of China, Korea and Japan.
The AIM-traded firm said that, as it made "good progress" on its permanent conditions TEO and received key resource, mining and processing information from the work programme, it was looking beyond the completion of the TEO - Russia's mandatory feasibility study - to the compilation of the bankable feasibility study.

It said the purpose of a bankable feasibility study was to provide the technical, environmental and economic detail of the project to give institutional investors the confidence to proceed with the project financing, necessary to advance Kun-Manie through construction and into production.

The study strategy covered three areas, being finalising the detailed plan, costing and technical parameters for the bankable feasibility study, attaining binding offtake agreements, initiating the funding for the study.

It released its pre-feasibility Study in February 2019, ahead of the start of the TEO, with the board saying on Wednesday that the bankable feasibility study objectives were "broadly the same" as the pre-feasibility study, but had a "far greater level of detail and accuracy".

In addition to the data being provided by the TEO on the Kun-Manie mine site, the bankable feasibility study would also cover the detailed engineering and costing for the access road, the proposed rail siding and logistics.

The company said it was currently in the process of finalising the detailed plan and costing of the study, and would begin engaging with potential partners who will assist in the compilation of it.

Amur announced on 11 June that it had received non-binding indicative offtake terms for both the nickel and copper concentrates, which was a TEO requirement for establishing that a marketable product could be generated.

The firm said it would continue to engage with the wider metals commodities market, with the objective of obtaining binding offtake agreements.

It said the attainment of binding agreements would be an important step in attracting the funding for the bankable feasibility study.

Amur said its primary funding objective was to position the company so that it can finance the bankable feasibility study.

It was envisaged that the funding would be primarily through debt, with a further component funded through equity, or a supporting investment from an offtake partner.

In addition, the firm said it was actively seeking to invest in mining opportunities in the near future that were either near cash flow, or were already in production in established mining jurisdictions.

The objective for the strategy was to provide revenue streams to fund the company's corporate activities through the bankable feasibility study and beyond.

"Significant progress has been achieved on the TEO, and we are on track to complete this for December," said chief executive officer Robin Young.

"Beyond this, our next major milestone is the bankable feasibility study, which is a substantive body of work."

Young said that as the Company started planning for the study, it was equally important that it planned for the future funding requirements.

"The addition of Adam Habib to the team has added to our capability to market the Kun-Manie project to a wider pool of financing sources, which have an interest funding projects through to completion of a bankable feasibility study."

At 1109 BST, shares in Amur Minerals were down 12.73% at 1.2p.
More News
4 May 2020 18:27

Amur Minerals Repays Initial Advance Of Plena Global Loan Note

Amur Minerals Repays Initial Advance Of Plena Global Loan Note

Read more
17 Apr 2020 06:03

Amur Minerals Raises GBP750,000 Through Share Placing

Amur Minerals Raises GBP750,000 Through Share Placing

Read more
12 Mar 2020 15:49

Amur Minerals Gets GBP1.5 Million Loan For Kun-Manie Feasibility Study

Amur Minerals Gets GBP1.5 Million Loan For Kun-Manie Feasibility Study

Read more
17 Feb 2020 09:42

Testing For Saleable Copper Begins At Amur Minerals's Kun-Manie

Testing For Saleable Copper Begins At Amur Minerals's Kun-Manie

Read more
28 Jan 2020 14:11

Amur Minerals Completes Rock Mechanics Study At Kun-Manie

Amur Minerals Completes Rock Mechanics Study At Kun-Manie

Read more
15 Jan 2020 15:52

Amur Minerals submits environmental assessment for Kun-Manie

(Sharecast News) - Russia-focussed nickel-copper sulphide exploration and development company Amur Minerals Corporation announced on Wednesday that the baseline environmental assessment (BLEA) for its Kun-Manie nickel copper sulphide project was now complete, and had been filed and approved by the necessary Russian Federation agencies.

Read more
15 Jan 2020 11:09

Amur Minerals Completes Environmental Survey At Kun-Manie, Russia

Amur Minerals Completes Environmental Survey At Kun-Manie, Russia

Read more
6 Dec 2019 16:00

UK Shareholder Meetings Calendar - Next 7 Days

UK Shareholder Meetings Calendar - Next 7 Days

Read more
18 Nov 2019 14:15

Amur Minerals Shares Surge As It Repays Convertible Loan In Full

Amur Minerals Shares Surge As It Repays Convertible Loan In Full

Read more
12 Nov 2019 15:52

Amur Minerals identified water sources for Kun-Manie development

(Sharecast News) - Eastern Russia-focussed nickel-copper sulphide exploration and development company Amur Minerals Corporation announced on Tuesday that the hydrological assessment - a component of the permanent conditions 'TEO', a Russian equivalent to a feasibility study - for its Kun-Manie nickel copper sulphide project was now complete, and had been approved by the necessary Russian agencies.

Read more
12 Nov 2019 11:40

Amur Minerals Completes Hydrological Assessment For Kun-Manie Project

Amur Minerals Completes Hydrological Assessment For Kun-Manie Project

Read more
4 Nov 2019 10:39

UK WINNERS & LOSERS SUMMARY: Egdon Resources Hit By UK Fracking Ban

UK WINNERS & LOSERS SUMMARY: Egdon Resources Hit By UK Fracking Ban

Read more
4 Nov 2019 10:21

Amur Minerals Raises GBP1.2 Million Through Share Subscription

Amur Minerals Raises GBP1.2 Million Through Share Subscription

Read more
1 Oct 2019 14:56

Amur Minerals Half-Year Loss Narrows As Progresses Kun-Manie Work

Amur Minerals Half-Year Loss Narrows As Progresses Kun-Manie Work

Read more
23 Sep 2019 14:37

Amur Minerals TEO And Definitive Feasibility Study Making Progress

Amur Minerals TEO And Definitive Feasibility Study Making Progress