110.5 MWp in Solar Development Projects

17 Nov 2025 11:19

RNS Number : 8228H
Zenith Energy Ltd
17 November 2025
 

November 17, 2025

 

ZENITH ENERGY LTD.

("Zenith" or the "Company")

110.5 MWp in Solar Development Projects

Zenith Energy Ltd. ("Zenith" or the "Company") (LSE: ZEN; OSE: ZENA; XSAT: ZENA SDR), the listed international energy production and development company, is pleased to announce the signing of a new agreement to acquire a solar energy development project located in the Puglia region of Italy (the "Puglia Acquisition") by its wholly-owned Italian subsidiary created to manage its solar energy portfolio, WESOLAR S.R.L. ("WESOLAR").

Overview of the Acquisitions

· The Puglia Acquisition is located in Italy's Puglia region and comprises approximately 12 MWp of ground-mounted PV capacity across roughly 15 hectares of flat, well-levelled land, resulting in minimal earth-moving requirements.

· In addition, the Company has secured sufficient land to accommodate an integrated 3 MW Battery Energy Storage System ("BESS") to optimise energy dispatch and support the local grid.

· A BESS is designed to store electricity generated during low-price periods and discharge it during higher-priced fasce orarie (time-of-use tariff periods), thereby maximising revenue. In Italy, electricity prices fluctuate throughout the day-with peak hours (fasce orarie di punta) commanding materially higher prices-allowing strategic storage and release to enhance project returns.

· The Puglia Acquisition is currently classified as being in the 'Development' stage.

· Puglia is among Italy's most favourable regions for solar power generation, benefiting from high solar irradiation levels that support superior economic performance for photovoltaic projects.

· The Puglia Acquisition strengthens the Company's presence in the region and complements its existing development pipeline in Piedmont and Lazio. Together, these three clusters form a strategically significant solar development portfolio across some of Italy's most attractive and highly sought-after renewable-energy generation areas.

· Italy continues to rank among the global leaders in photovoltaic technology, deployment, and installed capacity.

· The Company expects the project to reach Ready-to-Build status within 12-16 months.

· The total consideration for the Puglia Acquisition is EUR 1,050,000, including the associated land. Payment will be made upon securing all required permits and achieving Ready-to-Build status at the conclusion of the development process.

 

Strategy Overview

In the solar energy industry, a "pipeline" refers to the aggregate portfolio of development projects being actively advanced toward construction. Zenith's pipeline is composed of projects progressing daily through design, permitting, and grid-connection milestones, moving step by step toward Ready-to-Build ("RtB") status. This expanding portfolio already carries tangible market value, which increases as projects mature and de-risk through successive development stages. Owing to Zenith's optimised site selection and high-quality development standards, portions of the portfolio could already be monetised with professional counterparties, reflecting its strong commercial quality and competitiveness.

Zenith plans to sell only a portion of its development portfolio. This strategic divestment will generate immediate profit and strengthen both profitability and liquidity, while allowing the Company to continue expanding its project base and initiate construction of selected solar assets.

To ensure full transparency and effective communication with shareholders, Zenith is commissioning an independent valuation of its development portfolio, illustrating the progress achieved since the Company's strategic shift in early 2025 toward solar energy development and production.

With the original 100 MWp development target now substantially met, Zenith will define a new capacity objective and broaden its strategy to support continued growth in electricity production.

The Company has also initiated development activities in BESS segment, a highly attractive and complementary market that enhances grid stability and long-term value creation.

As previously announced, funding for these next phases will be secured through financing from specialised renewable-energy lenders and through the sale of selected portions of the existing development portfolio to interested professional counterparties.

Transition to Production: Creating Tangible and Recurring Revenue

As part of its long-term growth strategy, Zenith intends not only to develop and sell projects, but also to select certain RtB assets and construct them, enabling the Company to generate direct, tangible revenue from electricity production.

While development-stage asset sales generate strong near-term profitability, owning and operating selected plants provides stable, predictable, and recurring cash flows supported by Italy's favourable solar-generation economics. Production assets benefit from long operating lives, low operating costs, and exposure to steady market demand for clean electricity. This dual-track model strengthens Zenith's financial profile by combining short-term value creation from development sales with long-term revenue generation from energy production.

By constructing and operating a portion of its RtB pipeline, Zenith enhances its revenue base, builds tangible asset value on the balance sheet, and demonstrates its capability as a fully integrated renewable-energy operator.

Overview of Zenith Energy's Solar Portfolio (as of November 17, 2025)

Project / Stage

Capacity (MWp)

Status

Notes

Liguria Solar Asset

0.5

Production Upgrade

Currently producing 0.2 MWp, upgrade to 0.5 MWp planned.

Lazio Agrivoltaic Project 1

10.0

Development

First Lazio acquisition (10 MWp) announced Aug 6, 2025.

Lazio Agrivoltaic Project 2

7.0

Development

First announced on August 27, 2025, installed capacity has been increased to7 MWp from 5 MWp.

Piedmont Agrivoltaic Development Projects

30.0

Development

Acquisition comprising of various agrivoltaics projects announced onAugust 11, 2025.

Piedmont PV Development Project

10.0

Development

Originally an Agrivoltaic project, subsequently reclassified to conventional solar energy as announcedon August 22, 2025.

Piedmont Agrivoltaic Development Project

18.0

Development

Acquisition signed and announced on October 19, 2025.

Puglia Solar Asset

3.0

Ready-to-Build

All permits obtained, grid connection ready, announced on July 30, 2025.

Puglia Development Asset

6.0

Development

Acquisition signed and announced on September 16, 2025.

Puglia Solar Development (PV + BESS)

10.0

Development

Acquisition signed on October 9, 2025, of development project of approx. 10 MWp and a BESS project with a capacityof up to approx. 10 MW.

Puglia PV Development

4.0

Development

Acquisition signed and announced on October 19, 2025. Includes a BESS project with a capacity of up to approx. 2 MW.

Puglia PV Development

12.0

Development

Acquisition signed and announced on November 17, 2025. Includes a BESS project with a capacity of up to approx. 3 MW.

Total Portfolio

110.5

 

 

 

Andrea Cattaneo, Chief Executive Officer of Zenith Energy, commented:

"We are pleased to expand our presence in Puglia, further strengthening Zenith's strategic cluster in one of Italy's most attractive solar regions. With this latest addition, our development portfolio now surpasses the 100 MWp milestone, reflecting consistent progress and strong execution.

The Puglia acquisition also reinforces our commitment to Battery Energy Storage Systems, a core element of our strategy to enhance flexibility, resilience, and long-term project value.

With a solid development base in place, our next priority is to bring selected Ready-to-Build assets into construction, supported by specialised lenders. This will provide tangible production revenue and further demonstrate the quality and bankability of Zenith's portfolio.

As outlined, we will divest a portion of our pipeline to realise immediate value while continuing to expand and advance our project base. This balanced model positions Zenith for sustained profitability and long-term growth across both solar and storage."

Further Information:

Zenith Energy Ltd

Andrea Cattaneo, Chief Executive Officer

 

 

 

Tel: +1 (587) 315 1279

E: info@zenithenergy.ca

 

Notes to Editors:

Zenith Energy Ltd. is a revenue generating, independent energy company with energy production, exploration and development assets in North Africa, the US and Europe. The Company is listed on the London Stock Exchange Main Market (LSE: ZEN), the Euronext Growth of the Oslo Stock Exchange (OSE: ZENA) and on the Spotlight Stock Market in Sweden (XSAT: ZENA SDR).

Zenith's strategic focus is on pursuing development opportunities through the development of proven revenue generating energy production assets, as well as low-risk exploration activities in assets with existing production.

For more information, please visit: www.zenithenergy.ca

Twitter: @zenithenergyltd

LinkedIn: https://bit.ly/3A5PRJb

 

Market Abuse Regulation (MAR) Disclosure

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 as it forms part of UK domestic law by virtue of the European Union (Withdrawal) Act 2018 ("MAR"). Upon the publication of this announcement via a Regulatory Information Service ("RIS"), this inside information is now considered to be in the public domain.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
ACQBBBDBRBBDGUR
Date   Source Headline
18th Sep 202410:00 amRNSPayment of Outstanding Notes of 2024 Bond - Update
20th Aug 20244:00 pmRNSPayment of Outstanding Notes of 2024 Bond
12th Aug 20248:15 amRNSUpdate on Tunisian production portfolio
31st Jul 20245:30 pmRNSPublication of 2024 FY annual audited report
23rd Jul 20246:10 pmRNSSuccessful Conclusion of Bond Exchange Offer
7th Jun 20242:05 pmRNSAdmission to trading of Common Shares
6th Jun 202412:30 pmRNSPayment of 2026 multi-currency bond coupon
4th Jun 20249:15 amRNSUpdate on Arbitrations against Republic of Tunisia
7th May 20247:00 amRNSUpdate on ICC Arbitration proceedings against ETAP
22nd Apr 20241:25 pmRNSNew Bond Exchange Offer
17th Apr 20246:20 pmRNSUpdated TCFD Disclosures in Annual Report
11th Apr 202411:45 amRNSSuccessful Conclusion of Bond Exchange Offer
2nd Apr 20247:00 amRNSTotal Voting Rights
20th Mar 20248:30 amRNSUpdate on Arbitrations against Republic of Tunisia
12th Mar 20245:50 pmRNSUpdate on Italian Energy Production Portfolio
11th Mar 20241:00 pmRNSPositive support for Bond Exchange Offer
1st Mar 20241:01 pmRNSUpdate on Bond Exchange Offer
22nd Feb 20242:15 pmRNSAdmission to trading of UK Financing Common Shares
13th Feb 20245:15 pmRNSCompletion of financing with institutional support
25th Jan 20247:30 amRNSBond exchange offer to investors
18th Jan 20241:40 pmRNSUpdate on United States portfolio
29th Dec 202312:02 pmRNSPublication of Half-Year Results
20th Dec 202311:50 amRNSAcquisition of Devonian Petroleum Limited
6th Dec 202311:00 amRNSICC Arbitration for SLK against Tunisia
30th Nov 202312:30 pmRNSNew Kazakhstan subsidiary and pre-contract terms
29th Nov 20239:40 amRNSICC Arbitral Tribunal awards costs
28th Nov 20237:00 amRNSMoU – South Sudan
9th Nov 202312:15 pmRNSPayment of 2026 multi-currency bond coupon
1st Nov 20239:15 amRNSICC Arbitration proceedings against ETAP
25th Oct 20232:30 pmRNSCommencement of Trading on OTCQB Venture Market
18th Oct 202311:01 amRNSSeizure on SMP's bank account
10th Oct 202311:45 amRNSAssignment of new Debt Issuer Credit Rating
4th Oct 20232:00 pmRNSAdmission to trading of Common Shares
29th Sep 202311:05 amRNSConfirmation of Debt Issuer Credit Rating
25th Sep 20236:30 pmRNSImplementation of Share Consolidation
22nd Sep 20236:30 pmRNSShare Consolidation
20th Sep 20233:50 pmRNSShare Consolidation
19th Sep 20239:45 amRNSThird MOU for oil production asset in Kazakhstan
15th Sep 20239:30 amRNSSecond MOU for oil production assets in Kazakhstan
4th Sep 202310:40 amRNSMOU and Exclusivity for asset in Kazakhstan
4th Sep 20237:00 amRNSTermination of SPA for acquisition of OMV Yemen
29th Aug 20237:00 amRNSAcquisition of US listed company
4th Aug 20235:20 pmRNSUpdate on Benin PSC
3rd Aug 202310:06 amRNSThird Acquisition in USA
2nd Aug 202312:00 pmRNSPayment of 2024 multi-currency bond coupon
31st Jul 202311:36 amRNSPublication of 2023 FY annual audited report
10th Jul 20238:15 amRNSConservative seizure of ETAP bank account
5th Jul 202311:35 amRNSSecond acquisition in USA
3rd Jul 202311:10 amRNSCourt rejects SMP’s request and awards damages
23rd Jun 20237:00 amRNSMOU with Ministry of Petroleum – South Sudan

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.