Operations Update

17 Sep 2018 07:10

RNS Number : 9283A
Tlou Energy Ltd
17 September 2018
 

17 September 2018

 

Tlou Energy Limited

 

("Tlou" or "the Company")

 

Operations Update

 

 

Tlou Energy Limited, the ASX, AIM and BSE listed company focused on developing gas-to-power projects in southern Africa using coal bed methane ("CBM") natural gas from its gas field in Botswana, is pleased to provide an update on field operations at its Lesedi CBM project.

 

Key Points:

· Pilot production well locations have been agreed, scouted and inspected;

· Site preparation work has commenced for the first pilot production well;

· The Company is currently waiting on the final pieces of equipment to arrive onsite prior to spudding the first well in October.

 

Pilot well drilling program

Tlou Energy Limited is set to commence drilling of pilot production wells at its gas field in Botswana. If successful, these wells will form part of the Company's initial gas-to-power project which will include installation of transmission lines and grid connection. Further details on the proposed initial project are outlined below.

 

Preparations are currently underway with pre-mobilisation activities to ensure adequate site clearing and construction of well-site facilities, as well as ensuring a nearby core-hole that has been drilled is adequately plugged and abandoned prior to spudding of the first well. To maximise efficiencies, the vertical production wells and top-hole sections of lateral wells will initially be drilled, once the last of the long lead items for this stage of the program are onsite which is scheduled for early October. Up to three production pods (comprising three wells per pod) are currently planned.

 

The pilot well drilling program is being conducted in accordance with health and safety requirements and are consistent with the Company's approved environmental impact statement. There are various stages to the program including:

 

· Selection of well locations, site clearing and preparation;

· Mobilisation of equipment and ordering of long lead items;

· Engagement of relevant contractors (drilling supervisors, directional drilling staff, engineers);

· Field camp preparation;

· Drilling of top-hole (vertical) section of wells;

· Lateral well directional drilling and intersection with production well;

· Completion of wells including installation of well-head equipment;

· Pressure testing, dewatering; and

· Gas production, analysis and testing.

 

The wells will be drilled as 'dual lateral pods', comprising of a single vertical production well, intersected by two lateral wells. The lateral wells will be drilled through the gassy coal seam with gas extracted from this coal produced through the vertical production well where it can be gathered and used for power generation.

 

Initial gas-to-power project

Tlou is planning a gas-to-power project whereby gas from the Company's Lesedi CBM project will be used for power generation, and this power sold into the power market within Botswana and/or across the Southern African Power Pool (SAPP).

 

An initial development of up to 10 MW is planned. This will start with the first 2 MW of power which can then be expanded thereafter as further drilling is conducted and additional gas becomes available. With significant gas reserves already in place, the Company can readily expand upon successful implementation of the initial project.

 

The dual lateral pods will be located in the area where the initial gas-to power project will be situated, subject to success.

 

The Lesedi CBM project will require connection to the local power grid. This connection is planned to be made at the town of Serowe, which is located approximately 100 Km from the Lesedi CBM project. A draft transmission line route has been determined with negotiations ongoing with the regional and local land boards and the environmental impact assessment approval process continuing.

 

The Company plans to sell power to potential customers, either on the "spot market" or through Power Purchase Agreements (PPA) with one or more customers. Sale of power is planned to be through the Botswana power grid which facilitates the sale of power within Botswana and regionally via the SAPP. Other options available to the Company to sell gas include potential Compressed Natural Gas (CNG) or small scale Liquified Natural Gas (LNG) projects that have been proposed to the Company by third parties including the use of natural gas as feedstock for manufacturing.

 

The information contained within this announcement is deemed to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014. Upon the publication of this announcement, this inside information is now considered to be in the public domain.

 

For further information regarding this announcement please contact:

 

Tlou Energy Limited

+61 7 3012 9793

Tony Gilby, Managing Director

Solomon Rowland, General Manager

Grant Thornton (Nominated Adviser)

+44 (0)20 7383 5100

Samantha Harrison, Colin Aaronson, Harrison Clarke

Shore Capital (Broker)

+44 (0) 207 408 4090

Jerry Keen, Toby Gibbs, Mark Percy

FlowComms Limited (Investor Relations)

+44 (0) 7891 677 441

Sasha Sethi

 

Company Information

Tlou Energy is focused on delivering Gas-to-Power solutions in Botswana and southern Africa to alleviate some of the chronic power shortage in the region. Tlou is developing projects using coal bed methane ("CBM") natural gas. Botswana has a significant energy shortage and generally relies on expensive imported power and diesel generation to fulfil its power requirements. As 100% owner of the most advanced gas project in the country, the Lesedi CBM Project, Tlou Energy provides investors with access to a compelling opportunity using domestic gas to produce power and displace expensive diesel and imported power.

 

The Company is listed on the Australian Securities Exchange, London's AIM market and the Botswana Stock Exchange and is led by an experienced Board, management and advisory team including individuals with successful track records in the CBM industry.

 

Since establishment, the Company has significantly de-risked the project in consideration of its goal to become a significant gas-to-power producer. The Company flared its first gas in 2014, holds a Mining Licence and nine Prospecting Licences, covering an area of ~8,300Km2 in total, and the Lesedi Project already benefits from significant independently certified Contingent Gas Resources of ~3.2 trillion cubic feet (3C) and independently certified Gas Reserves of ~261 billion cubic feet (3P).

 

The Company is planning an initial scalable gas-to-power project. Following successful implementation of this first scalable project, the Company looks forward to evaluating longer-term prospects for the delivery of electricity generated from CBM in Botswana to neighbouring countries.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDFKADDDBKBBCD
Date   Source Headline
20th Nov 20178:05 amRNSTlou secures new Botswana cornerstone investor
10th Nov 20174:40 pmRNSSecond Price Monitoring Extn
10th Nov 20174:35 pmRNSPrice Monitoring Extension
9th Nov 20178:11 amRNSAppendix 4G
7th Nov 20177:00 amRNSCore-hole Drilling and Seismic Survey Update
25th Oct 20177:51 amRNSResults of Annual General Meeting
24th Oct 20177:00 amRNSSeismic Survey Update
23rd Oct 201712:12 pmRNSOPERATIONAL REPORT - QUARTER ENDING 30 SEPTEMBER
16th Oct 201711:02 amRNSReplacement: Exercise of Options
16th Oct 20179:18 amRNSExercise of Options
9th Oct 20177:28 amRNSSeismic Survey
25th Sep 20177:56 amRNSNotice of Annual General Meeting and Annual Report
20th Sep 201711:30 amRNSResponse to Government Request for Proposal Submit
11th Sep 20177:00 amRNSFinal Results
31st Aug 20177:00 amRNSMining Licence Terms
24th Aug 20177:00 amRNSRequest for Proposal Submission Date Extended
21st Aug 20177:00 amRNSMining Licence Awarded
20th Jul 20173:06 pmRNSCorporate Presentation
19th Jul 20177:00 amRNSOPERATIONAL REPORT - QUARTER ENDING 30 JUNE 2017
13th Jul 20173:07 pmRNSTender Submission Closing Date confirmed
12th Jul 20177:00 amRNSDirector Appointment
3rd Jul 20177:00 amRNSMining licence application and RFP submission
22nd Jun 20177:00 amRNSDirector Appointment
20th Jun 20177:00 amRNSFirst gas to power generation
31st May 20177:00 amRNSUpdate on seismic survey
10th May 20177:00 amRNSNew Corporate Presentation
28th Apr 20177:00 amRNSOperational report quarter ending 31 March 2017
27th Apr 20177:01 amRNSChange of director interests
26th Apr 20177:00 amRNSFinal SPP and additional placement announcement
18th Apr 20177:00 amRNSShare Purchase Plan Offer Booklet
12th Apr 20172:17 pmRNSIPC Partnership with African Investment Management
11th Apr 20177:00 amRNSExtension to SPP announcement
4th Apr 20177:00 amRNSUpdate on earthquake in Botswana
3rd Apr 20177:00 amRNSLicence renewal
30th Mar 20172:50 pmRNSINTERVIEW WITH CEO OF IPC
29th Mar 20177:00 amRNSNew Corporate Presentation
24th Mar 20177:00 amRNSEquity Placement and Share Purchase Plan
9th Mar 20177:00 amRNSResults of SRK report
2nd Mar 201711:24 amRNSAppointment of Shore Capital as Joint Broker
27th Feb 201712:12 pmRNSDevelopment partner for CBM to Power Project
20th Feb 20177:00 amRNSInterim Results
15th Feb 20177:00 amRNSReserves Upgrade
10th Feb 20177:00 amRNSPerformance Rights Update
31st Jan 20177:00 amRNSOPERATIONAL REPORT QUARTER ENDING 31 DECEMBER 2016
10th Jan 20177:00 amRNSRequest for Proposal received
22nd Dec 20167:00 amRNSBOARD OF DIRECTORS UPDATE
5th Dec 20167:00 amRNSCORPORATE PRESENTATION
1st Dec 20167:00 amRNSProject Update
28th Nov 20167:00 amRNSCO-OPERATION AGREEMENT EXTENDED
10th Nov 20167:00 amRNSResults of Annual General Meeting

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.