Roundtable Discussion; The Future of Mineral Sands. Watch the video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksTlou Energy Regulatory News (TLOU)

Share Price Information for Tlou Energy (TLOU)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 2.05
Bid: 2.00
Ask: 2.10
Change: 0.00 (0.00%)
Spread: 0.10 (5.00%)
Open: 2.05
High: 2.05
Low: 2.05
Prev. Close: 2.05
TLOU Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Project Update

1 Dec 2016 07:00

RNS Number : 6367Q
Tlou Energy Ltd
01 December 2016
 

1 December 2016

 

Tlou Energy Limited

 

('Tlou' or 'the Company')

 

LESEDI PROJECT UPDATE AND FIELD DEVELOPMENT PROGRAM

 

 

Tlou Energy Limited, the AIM and ASX listed company focused on delivering power in Botswana and southern Africa through the development of coal bed methane ('CBM'), is pleased to provide an update on progress at the Lesedi CBM Project ('Lesedi' or 'the Project') located in prospecting licence PL002/2004 in Botswana.

 

Highlights:

 

· First gas monetisation planned - gas produced by the Company will power the Project following completion of upgrades leading to ongoing cost savings

 

· Actively planning forthcoming field development program:

o SRK Consulting engaged to assist in recommendation of target development areas for the Project and further exploration.

o Flow testing at the Selemo wells is progressing well; providing vital data ahead of full field development and will be incorporated into Lesedi's Feasibility Study

 

· Detailed activities being advanced relating to the phased development of a CBM to power project (10MW ramping up to 50MW), to commence following field development:

o Working with specialist engineers on a Field Development Plan. - Initial project plan is expected to be completed by the end of the year. This will also provide data ahead of a future mining licence application

o Advancing a study of power grid integration points and transmission line options (midstream development)

o Downstream development relating to the planning, design, and development of the power generation units is progressing alongside specialist partners

o Terms to be discussed with the Government of Botswana in relation to an off-take agreement for the approved 50MW power project

o Assessing various funding options, having been contacted by a range of parties, for the development of the Project

 

Executive Director Gabaake Gabaake said, "This is an extremely exciting time for the Company. The Board and management are very busy as the Company focuses on getting the initial 10-50MW project up and running. As investors can see, there are a considerable number of parts to bring together to develop the project as we aim to get our first power to market and start generating revenue. In the near term we will be providing an update on our field development program, and our studies for the development of our scalable CBM to power plant, which are being advanced alongside specialist partners. In addition, we will keep the market up to date on progress of other items including the offtake agreement, conversion of the field operations to run on CBM and a future mining licence application.

 

"We are incredibly grateful to our shareholders, many of whom have been with us since 2009, for their strong support. We also benefit from the backing of the Government of Botswana and, as highlighted today, a range of potential funding partners. Our objective is to bring the Project to fruition as soon as possible to unlock the best possible value for our shareholders."

 

Gas Flows

The Company has been producing gas at the Selemo wells located in the Lesedi project during the year. This led to the Company becoming the first in Botswana to book independently certified gas reserves in October 2016. Since this time, flow testing has continued at the Selemo wells and is planned to do so for the foreseeable future. The data from this testing provides vital input into full field development and is incorporated into the project's feasibility study.

 

Conversion of field generation from diesel to gas

Power required to run pumps and metering at the Selemo wells is currently supplied by diesel generators. The Company's operations team are planning to replace these with gas fired generators, which can then run on the gas being produced from our wells. Once implemented, this will be a significant milestone and in effect be proof of concept or 'first gas monetisation' by providing a cost saving to the Company with a much-reduced diesel requirement.

 

Regional geological data

Tlou has an extensive geological database across much of its licence area particularly over the Lesedi project. As the Company progresses towards field development and further exploration, a key task is to assess the most prospective areas to base future projects. In this regard, the Company has engaged SRK Consulting ('SRK') to assist with this process due to their expertise in this area along with their in-depth knowledge of the project, having been involved in the booking of initial gas reserves recently as well as contingent resources prior to that. SRK will review the Company's geological model and make recommendations in relation to future work. This will incorporate potential field, seismic and drilling data, develop optimum production layouts including updating well performance simulation and help define what work would best facilitate the addition of further reserves. This is likely to be completed in late 2016 or early 2017.

 

Further field exploration

The Company is considering expansion of its exploration work in the field. The potential remains for exploration in both the Lesedi and Mamba project areas held by the Company. The report from SRK as mentioned above will provide valuable data in relation to this process.

 

50MW CBM to power project

As previously announced, Tlou has been approved by the Government of Botswana to develop a 50MW CBM to power project. The 50MW project is planned to be delivered on a staged basis and can be divided into three distinct parts, upstream, midstream and downstream development, with excellent progress being made in each of these areas.

 

Upstream development

This is essentially the field development part of the project which includes items such as the drilling of wells and gas gathering and compression. The Company is working with specialist engineers to develop this part of the project further. This work is aimed at:

· developing the process flow and high level operating philosophy for the initial 10MW phase of the project;

· determine capital, operating and maintenance costs; and

· provide a project execution plan to ensure the Company's objectives for the Lesedi CBM Project can be achieved in the desired timeframes.

 

This work is likely to be completed in late 2016. This process will also provide engineering, operating and maintenance input into a future mining licence application.

 

Midstream development

This process relates to the construction of the transmission lines or gas pipeline. The Company has been in discussion with Botswana Power Corporation ('BPC'), owners of the power network infrastructure in Botswana. Following these discussions, the Company is working on a study of options available for midstream development including:

· determining the lowest cost and most effective integration point in the BPC network for up to 100MW of power generation located at the Company's Lesedi project starting with an initial 10MW within two years and ramping up to 50MW;

· determining the most feasible route and cost of a transmission line for a 10MW, 50MW and 100MW project;

· Assessing upgrades required in the BPC network at the integration point, if any, and the related costs.

 

This process is expected to take approximately three months to complete.

 

Downstream development

Downstream development relates to the planning, design, and development of the power generation units. This is well underway and the Company is being assisted by our co-operation partners GE, a world-leader in the design, construction, operation, and maintenance of power generation facilities. GE has identified suitable generation equipment for the initial project along with capex and opex calculations. These costs as well as the various specifications of the power generation equipment are key items that will be used for the project's feasibility planning.

 

Offtake agreement

Discussions are continuing with the Government of Botswana in relation to the terms of the power purchase agreement for the approved 50MW power project. This process involves various elements within Government and Botswana's Public Procurement and Asset Disposal Board so is likely to be an evolving process. The terms of the proposal, including power price and length of the agreement, are key items that will be incorporated into the offtake agreement.

 

Project Funding

Since the recent reserves announcement, the Company has been contacted by different parties interested in discussing the Company's proposed power project and potential future investment. The Company owns 100% of the Lesedi CBM project and as no firm funding agreement has been put in place, various options remain available to the Company. These may involve development of projects through special purpose vehicles, joint ventures, infrastructure funds, equity and debt financing.

 

**ENDS**

 

For further information regarding this announcement please contact:

 

Tlou Energy Limited

+61 7 3012 9793

Gabaake Gabaake, Executive Director

Solomon Rowland, Company Secretary

Grant Thornton (Nominated Adviser)

+44 (0)20 7383 5100

Samantha Harrison, Colin Aaronson, Harrison Clarke

Brandon Hill Capital (Financial Adviser and Joint broker)

+44 (0)20 3463 5016

Jonathan Evans, Alex Walker

Optiva Securities Limited (Joint broker)

+44 (0)20 3137 1904

Jeremy King, Christian Dennis

St Brides Partners Limited (Public Relations)

+44 (0) 20 7236 1177

Elisabeth Cowell, Lottie Brocklehurst

FlowComms Limited (Investor Relations)

+44 (0) 7891 677 441

Sasha Sethi

 

Company Information

 

Tlou Energy is an AIM and ASX listed company focused on delivering power in Botswana through the development of coal bed methane ('CBM') projects. Botswana has a severe energy shortage and is currently relying on expensive imported power and diesel generation to deliver its requirements. However, as the 100% owners of the most advanced gas project in the country, the Lesedi CBM Project ('Lesedi'), Tlou Energy provides investors with access to an immediate and longer term opportunity using domestic gas to produce power at lower costs than the current arrangements.

 

The Company is led by an experienced Board, management and advisory team including individuals with successful track records in the Australian CBM industry.

 

Since establishment in 2009 the Company has significantly de-risked the project in pursuit of its goal to become a significant gas to power producer and the Company has the most advanced CBM project in Botswana. It holds 10 prospecting licences covering an area of ~8,300Km2 and the Lesedi project already benefits from significant, independently certified contingent gas resources of ~3.3 trillion cubic feet (TCF) (3C) as well as an initial independent gas reserve certification.

 

The first planned gas-to-power solution is expected to be delivered through a scalable project with the Botswana Government. Following successful implementation of this project the Company plans larger projects to provide further power to Botswana and the southern African region.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLEAFAFELDKFEF
Date   Source Headline
29th Apr 20247:00 amRNSFurther Placement of Entitlement Offer Shortfall
26th Apr 20247:00 amRNSQuarterly Activities Report q/e 31 March 2024
26th Mar 20247:00 amRNSPlacement of Entitlement Offer Shortfall
8th Mar 20247:00 amRNSInterim Results
23rd Feb 20247:00 amRNSLesedi Project Update
5th Feb 20247:00 amRNSResults of Entitlement Offer
24th Jan 20247:00 amRNSQuarterly Activities Report q/e 31 December 2023
8th Jan 20247:00 amRNSNon-Renounceable Entitlement Offer Extension
22nd Dec 202311:18 amRNSResult of General Meeting
15th Dec 20237:00 amRNSNon-Renounceable Entitlement Offer
27th Nov 20237:00 amRNSFirst Gas Flow from Lesedi 6 Production Pod
24th Nov 20239:00 amRNSNotice of General Meeting
6th Nov 20237:00 amRNSA$3m Loan Agreement
31st Oct 20237:00 amRNSResults of AGM and Chairman's Address
27th Oct 20237:00 amRNSQuarterly Activities Report q/e 30 September 2023
6th Oct 20237:00 amRNSCompletion of Private Placement
29th Sep 20238:31 amRNSFinal Results
29th Sep 20237:00 amRNSNotice of AGM
11th Sep 20239:19 amRNSDate of 2023 Annual General Meeting
11th Sep 20237:00 amRNSLesedi Drilling and Project Update
25th Jul 20237:00 amRNSQuarterly Activities Report q/e 30 June 2023
22nd Jun 20233:22 pmRNSUpdate - Results of Entitlement Offer
20th Jun 20237:22 amRNSResults of Entitlement Offer
14th Jun 20237:00 amRNSDrilling and Operational Update
12th Jun 20234:23 pmRNSPublication of Supplementary Prospectus
5th Jun 20237:38 amRNSEntitlement Offer – Extension of Closing Date
23rd May 20239:43 amRNSDespatch of Prospectus to Eligible Shareholders
12th May 20237:00 amRNSPartially Underwritten Entitlement Offer
2nd May 20237:00 amRNSA$2m Loan Agreement Signed
28th Apr 20237:00 amRNSQuarterly Activities Report
13th Apr 20237:09 amRNSLesedi 6 Production Well Drilling
27th Mar 20237:13 amRNSA$200k placement
15th Mar 20237:00 amRNSGas Production Well and Core-hole Drilling
9th Mar 20237:00 amRNSInterim Results
23rd Feb 20232:25 pmRNSInterview with Proactive Investors
27th Jan 20237:00 amRNSOperational Report Quarter ended 31 December 2022
25th Jan 202311:42 amRNSIssue of Shares and Total Voting Rights
19th Jan 20235:16 pmRNSChange of Adviser
18th Jan 20238:14 amRNSResults of General Meeting
19th Dec 20227:00 amRNSNotice of General Meeting
15th Dec 20227:00 amRNSA$3 million placement
17th Nov 202212:16 pmRNSHolding(s) in Company
17th Nov 202212:16 pmRNSHolding(s) in Company
15th Nov 20222:05 pmRNSSecond Price Monitoring Extn
15th Nov 20222:00 pmRNSPrice Monitoring Extension
11th Nov 20222:05 pmRNSSecond Price Monitoring Extn
11th Nov 20222:00 pmRNSPrice Monitoring Extension
11th Nov 20227:00 amRNSA$3 million placement
9th Nov 202212:09 pmEQSTlou Energy raises A$2mln to get Lesedi into development by end 2023
4th Nov 20227:28 amRNSA$2 million placement

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.