Pin to quick picksTharisa Regulatory News (THS)

Share Price Information for Tharisa (THS)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 69.00
Bid: 68.00
Ask: 70.00
Change: 0.00 (0.00%)
Spread: 2.00 (2.941%)
Open: 0.00
High: 0.00
Low: 0.00
Prev. Close: 69.00
THS Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Production Report Q1 FY2021

12 Jan 2021 07:00

RNS Number : 2826L
Tharisa PLC
12 January 2021
 

 

Tharisa plc

(Incorporated in the Republic of Cyprus with limited liability)

(Registration number HE223412)

JSE share code: THA

LSE share code: THS

A2X share code: THA

ISIN: CY0103562118

LEI: 213800WW4YWMVVZIJM90

('Tharisa' or the 'Company')

PRODUCTION REPORT FOR THE FIRST QUARTER FY2021[1] ENDED 31 DECEMBER 2020

 

Consistent production performance, in line with guidance, feeding into a strong PGM market

 

 

Tharisa, the leading integrated platinum and chrome producer with operations in South Africa, announces another strong quarter of production ended 31 December 2020. The consistent operational performance underpins the Company maintaining its annual guidance of platinum group metals (PGMs) and chrome concentrate production for FY2021.

 

 

Health & Safety

‒ Strong safety record maintained with an LTIFR of 0.08 per 200 000 man hours worked

‒ Globally economies have been placed at various levels of lockdown to limit the impact of the coronavirus, with South Africa being placed on a level 3 risk adjusted lockdown, however, operations at the Tharisa Mine continued throughout the period. The Company acknowledges the rapid rise in infections globally, and of concern is the increase in infections in South Africa, with 35 active cases at the Tharisa Mine at the time of reporting

‒ It is with great sadness that we report that a second employee has succumbed to COVID-19 and we pass our deepest condolences to his family, colleagues and friends

 

 

Key Operating Highlights

 

 

Quarter ended 31 Dec 2020 

Quarter ended 30 Sep 2020 

Quarter on quarter movement % 

Quarter ended 31 Dec 2019 

Year on year movement %

Reef mined

kt

1 234.3

1 405.7

(12.2)

1 143.0

8.0

6E PGMs produced

koz

39.3

40.5

(3.0)

34.4

14.2

Chrome concentrates produced (excluding third party)

kt

372.3

370.8

0.4 

342.5

8.7

Average PGM contained metal basket price

US$/oz

2 399

1 951

22.9

1 406

70.6

Average metallurgical grade chrome concentrate contract price

US$/t

136

142

(4.2)

145

(6.2)

 

 

Metal Pricing

‒ Average PGM basket price for the year increased to US$2 399/oz (ZAR37 410/oz) in Q1 FY2021 vs Q1 FY2020 and up 22.9% vs Q4 FY2020

‒ The current spot price basket price for Tharisa's prill split is US$2 995/oz with spot prices for the major PGMs as follows

o Platinum US$1 108

o Palladium US$2 421

o Rhodium US$18 840

‒ Average metallurgical grade chrome price for Q1 FY2021 of US$136/t (ZAR2 114/t), vs Q1 FY2020 of US$145/t (ZAR 2 120/t) and Q4 FY2020 of US$142/t (ZAR2 376/t). The current market price is US$145/t to US$150/t

Operational Overview

‒ PGM production is up 14.2% year on year ('YoY') on a 6E basis to 39.3koz vs 34.4koz in Q1 FY2020 and in line with 40.5koz in Q4 FY2020

‒ Chrome concentrate production (excluding third party) is up 8.7% YoY to 372.3kt vs 342.5kt in Q1 FY2020 and marginally stronger versus 370.8kt in Q4 FY2020

‒ Speciality grade chrome production is up 15% YoY to 93.8kt vs 81.5kt in Q1 FY2020 and flat versus 93.2kt in Q4 FY2020 (25.2% of total chrome production vs 23.8% in Q1 FY2020 and 25.1% in Q4 FY 2020)

‒ The Company concluded a four-year Collective Wage Agreement with the main unions represented at the Tharisa Mine, effective from July 2020 until 30 June 2024

Guidance for FY2021

‒ The Company remains on track for FY2021 production guidance of 155 koz to 165 koz PGMs (6E basis) and 1.45 Mt to 1.55 Mt of chrome concentrates

‒ COVID-19 remains a risk to the Company and our forecasts and guidance are premised on the current level of economic activity being permitted by government regulations

 

Phoevos Pouroulis, CEO of Tharisa, commented:

 

"The first quarter provided a solid platform for Tharisa to meet its production guidance for the current financial year with all key metrics delivering strong growth versus the same period in FY2020. The consistent performance has been delivered in a strong spot market for PGMs in particular and stable chrome prices.

 

Construction of the Vulcan processing plant remains on schedule and on budget for commissioning at the end of this financial year, which will further boost Tharisa's chrome concentrate production from FY2022 onwards.

 

The significant progress made in optimising our mining operations during the course of 2019, and 2020 has been demonstrated by the consistent performance and availability of our operations over the last several quarters. We continue to invest in our assets and in our market leading research and development, which will contribute to further production growth from our long life Tharisa Mine.

 

The headwinds from the global COVID-19 pandemic continue to challenge the industry worldwide."

 

Investor relations contacts:

Ilja Graulich (Head of Investor Relations and Communications)

+27 11 996 3500

+27 83 604 0820

igraulich@tharisa.com

 

Financial PR contacts:

Bobby Morse / Augustine Chipungu / James Husband

+44 207 466 5000

tharisa@buchanan.uk.com 

Broker contacts:

Peel Hunt LLP (UK Joint Broker)

Ross Allister / David McKeown / Alexander Allen

+44 207 7418 8900

BMO Capital Markets Limited (UK Joint Broker)

Thomas Rider / Pascal Lussier Duquette / Nick Macann

+44 207 236 1010

Berenberg (UK Joint Broker)

Matthew Armitt / Jennifer Wyllie / Detlir Elezi

+44 203 207 7800

Nedbank Limited (acting through its Corporate and Investment Banking division) (RSA Broker)

Shabbir Norath

+27 11 295 6575

About Tharisa

 

Tharisa is an integrated resource group incorporating mining, processing, exploration and the beneficiation, marketing, sales and logistics of PGMs and chrome concentrates. Its principle asset is the Tharisa Mine located in the South-Western Limb of the Bushveld complex, South Africa. The open pit, mechanised mine has a 14-year open pit life of mine (LOM) and the ability to extend operations underground by at least 40 years. Tharisa is listed on the Johannesburg Stock Exchange (JSE: THA) and the Main Market of the London Stock Exchange (LSE: THS).

 

 

 

 

Detailed production report

Safety

Safety is a core value, and Tharisa continues to strive for zero harm at its operations. An LTIFR of 0.08 per 200 000 man hours worked was recorded.

The Company has a continuous education campaign to prevent complacency around the COVID-19 pandemic. For full details on all the preventative measures Tharisa has implemented, please go to https://www.tharisa.com/pdf/covid-19/covid-19-presentation-of-compliance.pdf

 

 

 

Quarter ended 31 Dec 2020 

Quarter ended 30 Sep 2020 

Quarter on quarter movement % 

Quarter ended 31 Dec 2019 

Year ended 30 Sep 2020 

Reef mined

kt

1 234.3

1 405.7

(12.2)

1 143.0

4 971.1

Stripping ratio

m3: m3

11.3

13.0

(13.1)

10.9

12.1

Reef milled

kt

1 413.7

1 401.8

0.8 

1 247.1

5 036.1

PGM flotation feed

kt

1 080.3

1 062.5

1.7 

921.0

3 765.9

PGM rougher feed grade

g/t

1.43

1.54

(7.1)

1.41

1.46

PGM recovery

%

78.9

77.1

2.3 

82.2

80.1

6E PGMs produced

koz

39.3

40.5

(3.0)

34.4

142.1

Platinum produced

koz

21.5

22.7

(5.3)

19.1

78.7

Palladium produced

koz

6.8

6.1

11.5 

5.6

23.0

Rhodium produced

koz

3.7

3.9

(5.1)

3.2

13.5

Average PGM contained metal basket price

US$/oz

2 399

1 951

23.0 

1 406

1 704

Platinum price

US$/oz

946

901

5.0 

909

876

Palladium price

US$/oz

2 349

2 283

2.9 

1 744

2 147

Rhodium price

US$/oz

14 621

10 482

39.5 

5 711

8 348

Average PGM contained metal basket price

ZAR/oz

37 410

32 978

13.4 

20 745

27 691

Cr2O3 ROM grade

%

17.7

18.0

(1.7)

18.3

18.2

Chrome recovery

%

62.8

62.3

0.8 

63.1

62.1

Chrome yield

%

26.3

26.4

(0.4)

27.5

26.7

Chrome concentrates produced (excluding third party)

kt

372.3

370.8

0.4 

342.5

1 344.8

Metallurgical grade

kt

278.5

277.6

0.3

261.0

1 023.2

Specialty grades

kt

93.8

93.2

0.6 

81.5

321.6

Third party chrome production

kt

62.9

52.8

19.1 

62.3

169.8

Metallurgical grade chrome concentrate contract price

US$/t CIF China

136

142

(4.2)

145

140

Metallurgical grade chrome concentrate contract price

ZAR/t CIF China

2 114

2 376

(11.0)

2 120

2 231

Average exchange rate

ZAR:US$

15.6

16.9

(7.7)

14.7

16.2

Market update and metal production

PGM prices, in particular platinum and rhodium, continued their strong performance for the quarter under review. With Tharisa's prill split favouring rhodium at 9.5%, the Company continues to enjoy a healthy revenue stream from this metal in particular. With platinum now consistently above US$1 000/oz, the overall basket price was favourably set at US$2 399/oz for the quarter, and even with a strengthening currency against the US$, the ZAR prices received per PGM ounce increased to ZAR37 410/oz. Spot PGM basket prices are trading at US$2 996/oz and ZAR46 150/oz.

While flat quarter on quarter, the chrome market continues to be an important revenue and margin generator for Tharisa. Stainless steel production in China in 2020 was approximately 29.5Mt, an increase of almost 1Mt over 2019. Production is forecast to increase at a rate of 5% to 10% in 2021, with ferrochrome an essential ingredient for the production of stainless steel, demand should increase accordingly. Fortunately for Tharisa, chrome ore demand (and in particular chrome ore concentrates owing to the fact that the Chinese government is phasing out furnaces of 25MvA and less in favour of more efficient and environmentally friendly smelters). Offtake for the quarter under review was positive with the majority of production sold. Notwithstanding the imminent Chinese New Year, orders remain strong, noting that the current chrome price is trading at US$145/t to US$150/t at the time of reporting, with the ZAR having weakened to spot levels of ZAR15.40/US$.

Operations update

Operations continued to perform well despite the ongoing headwinds of the COVID-19 pandemic.

 

Mining

While mining rates were seasonally lower compared to the previous quarter, the volumes mined and the associated strip ratio are in line with guidance and ahead of the life of mine strip requirements. The overall performance remains in line with expectations.

 

Processing

Recoveries for both PGM and chrome saw slight improvements quarter on quarter and are in line with the planned increases in overall recovery as highlighted in previous announcements. PGM rougher feed grade remains below expectations. This will be addressed as the mine continues with more selective mining on the back of the volume and operational flexibility, which the mine has been developing over the past 18 months.

Construction of the Vulcan plant remains on track.

Labour relations

 

The Company announced in December 2020 that it had concluded a market related four-year Collective Agreement on Substantive Terms and Conditions of Employment with the main unions represented at the Tharisa Mine, namely the Association of Mineworkers and Construction Union (AMCU), the National Union of Mineworkers (NUM) and Solidarity. This agreement, in line with the South African inflation rate, provides further stability for the Company moving forward and allows Tharisa to focus on growing the business for the benefit of all stakeholders.

 

Cash Balance and Debt Position

Tharisa had a cash balance of US$49.8 million at the end of the quarter and a total debt of US$45.0 million, of which US$5.5 million is trade finance facilities, resulting in a positive net cash position of USD4.8 million.

Outlook

Tharisa maintains its FY2021 production guidance of between 155 koz to 165 koz PGMs (6E basis) and 1.45 Mt to 1.55 Mt of chrome concentrates. The increase in COVID-19 infections remains a risk to the Company and our forecasts and guidance are premised on the current level of economic activity being permitted by government regulations.

The above information has not been reported on or reviewed by Tharisa's auditors.

 

Paphos, Cyprus

12 January 2021

 

 

[1] Tharisa's financial year begins 01 October each year, and finishes on 30 September.

 

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
DRLEALFFFEFFEFA
Date   Source Headline
15th Apr 20241:30 pmRNSTransaction in Own Shares
10th Apr 20247:00 amRNSQ2 FY2024 Production Results
4th Apr 20247:08 amRNSTransaction in Own Shares
26th Mar 20247:00 amRNSUS$5 Million General Share Repurchase
22nd Feb 20247:00 amRNSResults of AGM and dividend conversion rates
23rd Jan 20247:00 amRNSChange of independent auditors - FY2024
11th Jan 20247:00 amRNSTharisa Q1 FY2024 production report
22nd Dec 20237:00 amRNSDistribution of Annual Report and Notice of AGM
21st Dec 20239:15 amRNSRetirement and appointment of INED
14th Dec 20237:00 amRNSAnnual Financial Report
13th Dec 20237:00 amRNSRelease date of Annual Results FY2023
6th Dec 20237:00 amRNSTrading Statement
17th Oct 20237:00 amRNSTharisa Q4 FY2023 Production Report
3rd Oct 20239:30 amRNSKaro Mining Holdings VFEX update 30 June 2023
28th Sep 20237:00 amRNSDirectorate Change
1st Aug 20232:15 pmRNSTransfer of treasury shares/Total voting rights
21st Jul 20232:00 pmRNSDealings by director of major subsidiary
12th Jul 20237:00 amRNS3rd Quarter Production Results
7th Jul 20232:10 pmRNSDealing in securities by directors
29th Jun 202311:00 amRNSDealings by directors and company secretary
19th May 20237:00 amRNSH1 FY2023 Results and dividend timetable
18th May 20237:00 amRNSTharisa H1FY2023 Results and Investor Presentation
16th May 20233:00 pmRNSTharisa Trading Statement H1 FY2023
13th Apr 20237:00 amRNSTharisa Production Report Q2 FY2023
11th Apr 20232:55 pmRNSDirector/PDMR Shareholding
3rd Apr 20237:00 amRNSTotal Voting Rights
27th Mar 20237:00 amRNSTHARISA SECURES $130 MILLION OFFTAKE-BASED FINANCE
23rd Feb 20238:00 amRNSResults of the AGM and dividend conversion rates
20th Feb 20237:00 amRNSDirector/PDMR Shareholding
2nd Feb 202312:00 pmRNSDirector/PDMR Shareholding
1st Feb 20232:15 pmRNSTotal Voting Rights
31st Jan 20238:00 amRNSDirector/PDMR Shareholding
11th Jan 20237:00 amRNSTharisa Production Report Q1 FY2023
22nd Dec 20227:00 amRNSNotice of AGM and no change statement
15th Dec 20229:43 amEQSTharisa ends the year in a 'net cash positive position'
12th Dec 20221:00 pmRNSKaro Project Result of private placement & listing
7th Dec 202212:00 pmRNSCONSTRUCTION COMMENCEMENT CEREMONY KARO PLATINUM
5th Dec 20227:00 amRNSAnnual Financial Report
5th Dec 20227:00 amRNSAnnual Financial Report - Results in ZAR
2nd Dec 202211:00 amRNSRelease of FY2022 results
30th Nov 20222:07 pmRNSKARO $50 million Bond issue Extension Closing date
29th Nov 20227:00 amRNSTrading FY2022
28th Oct 202211:00 amRNSKARO PLATINUM PROJECT - US$50 MILLION BOND ISSUE
24th Oct 202212:00 pmRNSLoss of life incident at Tharisa Mine
11th Oct 202212:00 pmRNSInvestorMeet - Tharisa production and Karo update
11th Oct 20227:00 amRNSProduction report Q4 FY2022
3rd Oct 20227:00 amRNSTotal Voting Rights
8th Sep 20222:00 pmRNSDealings by director of a major subsidiary
6th Sep 20223:00 pmRNSDealing in securities by Executive Chairman & CEO
12th Jul 20227:00 amRNSProduction report for Q3 FY2022

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.