Trinidad Development and Exploration Update

13 May 2015 07:00

RNS Number : 9797M
Range Resources Limited
13 May 2015
 



Trinidad Development and Exploration Update

Range is pleased to provide a Trinidad update with the following highlights:

· Average production in Trinidad in May reached 650 barrels of oil per day (bopd) from an average of 617 bopd in the previous month;

 

· The work programme on the first 13 development and exploration wells to be drilled this year has been finalised;

 

· Range and LandOcean are also finalising 9 additional development and exploration wells to be drilled as part of the 2015 / 2016 work programme;

 

· Funding for these wells is available under the extended 12 month credit facility with LandOcean which has enabled Range to commence its exploration and development programmes. In addition, Range is in discussions with Sinosure and LandOcean to finalise the previously announced US$50 million trade financing package;

 

· All necessary approvals have been received on the first three wells, including an exploration well on the Guayaguayare licence (the Canari North well) and preparations are underway to spud these wells during the current quarter;

 

· During the current quarter to date, the Company has:

o Initiated testing operations on the QU 454ST development well located in the South Quarry field. This well was drilled to a target depth of 2,000 ft. in the previous quarter. The well encountered potential oil bearing sands in three zones and is currently being tested from the lowest zone;

o Brought into production the QU 455 development well, located in the South Quarry field. This well was drilled to a target depth of 890 ft. in the previous quarter. The well is scheduled for optimisation in the short term; and

o Waiting to perforate the QU 456 development well, located in the South Quarry field, subject to relevant government approvals. This well was drilled to 2,002 ft. in the previous quarter.

Upcoming development and exploration work programme

Range and its strategic partner LandOcean Energy Services Co., Ltd (LandOcean) have completed geological and geophysical studies aimed at improving operational efficiency, and sub-surface evaluation, in order to reduce risk and improve well economics by drilling the best possible targets and increasing production potential. These studies have prioritised the first 13 development and exploration wells to be drilled this year (please refer to the table below for further information on these wells). In addition, Range and LandOcean are finalising 9 additional development and exploration wells to be drilled as part of the 2015 / 2016 work programme, the details of which the Company expects to announce shortly.

Funding for these wells is available under the extended 12 month credit facility with LandOcean as announced on 1 May 2015, which enables Range to commence its planned exploration and development programmes in Trinidad immediately. In addition, further to the announcement on 11 December 2014 in relation to the second purchase order under the Integrated Master Services Agreement for US$50 million of services from LandOcean, the Company is currently in the process of amending the purchase order to include provision of drilling services of the developments wells, as well as waterflooding work.

The drilling services will be provided by LandOcean on a turnkey basis and priced in line with market rates in Trinidad, to be reviewed periodically by both parties.

Well

Location

Depth (ft.)

Target Horizon

Development / Exploration

Proposed Spud Date

1. QUN 158

Morne Diablo

2,000

Lower Forest and Upper Cruse

Development

May

2. Canari North

Guayaguayare (Shallow)

5,000

Lower Gros Morne

Exploration

June

3. MD 249

Morne Diablo

3,000

Upper Cruse and Middle Cruse

Development

June

4. QUN 16R

Morne Diablo

2,000

Upper Cruse

Development

Q3 2015*

5. QUN 15 Outstep

Morne Diablo

2,000

Upper Cruse

Development

Q3 2015*

6. QUN 16 Outstep

Morne Diablo

2,000

Upper Cruse

Development

Q3 2015*

7. GGY Deep Commitment

Guayaguayare (Deep)

8,500

Upper Cretaceous

Exploration

Q3 2015*

8. GY 218SE

Beach Marcelle

3,000

Upper Gros Morne

Development

Q3 2015*

9. GY 2R

Beach Marcelle

2,000

Upper Gros Morne

Development

Q4 2015*

10. GY 161S

Beach Marcelle

3,000

Upper Gros Morne

Development

Q3 2015*

11. GY 180SE

Beach Marcelle

4,000

Lower Gros Morne

Development

Q4 2015*

12. GY 68W

Beach Marcelle

1,800

Middle Gros Morne

Development

Q4 2015*

13.GY 300/298W

Beach Marcelle

3,000

Middle Gros Morne

Development

Q4 2015*

*Subject to government and regulatory approvals

Planned work programme on the first 13 wells

The first two development wells QUN 158 and MD 249 are located on the north flank of the Southern Range anticline.

The QUN 158 is a step-out well to be drilled to a total depth of 2,000 feet. The well will be targeting the relatively under-explored Lower Forest 3 sands, which flowed at a stabilised production rate of 120 bopd in the recently drilled QUN 157 well, located 200 feet to the South East. The QUN 158 well will also be testing a less-explored Upper Cruse formation, which is well-developed in nearby QUN 120 and QUN 128 wells.

The MD 249 is an infill well which will be drilled to a total depth of 3,000 ft. to test the prolific Upper Cruse channel sand complex and the extent of the underlying Middle Cruse sand trend, also productive in the immediate area.

The Company will provide a separate announcement during May on the progress of the ongoing drilling preparations on the Canari North exploration well on the Guayaguayare licence, ahead of anticipated well spudding in June 2015.

The Company has received all necessary approvals to proceed with the first three wells (the QUN 158, MD 249, and Canari North wells) and is currently in the process of preparing and submitting the final documents for drilling approvals on the other 10 wells.

In order to improve forward planning and reduce approval-related delays as much as possible, the Company has implemented a new tracking system which has resulted in the submission processes becoming more consistent. Range is in the process of establishing a production planning department to manage the drill locations and planning in advance, including permitting of all drilling locations.

In addition, Range along with other operator companies in Trinidad, has been working with relevant authorities to define better guidelines, which have led to improved submission and approval timelines.

Electromagnetic Surveying (Stratagem)

The Company has also received regulatory approvals to conduct Electromagnetic Surveying in the Morne Diablo and South Quarry fields. This new technology will be used to image shallow resistive bodies and identify possible oil reservoirs at 1,000 feet or less, thus reducing exploration and development risks at a relatively low cost with minimal environmental impact. Based on the potentially high impact these surveys could have, they will be given priority status in all undrilled acreage where shallow hydrocarbon potential may be present.

Range looks forward to providing further operational updates in due course. A full year production forecast will be provided later in Q2 2015.

 

 

 

 Further comment and information

 

Range Resources Limited

Evgenia Bezruchko (Investor Relations)

e. admin@rangeresources.co.uk

t. +44 (0)20 7025 7040

 

Cantor Fitzgerald Europe (Nominated Advisor and Broker)

David Porter / Sarah Wharry (Corporate Finance)

Richard Redmayne (Corporate Broking)

t. +44 (0)20 7894 7000

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLPKBDNABKDBPD
Date   Source Headline
3rd Jun 20137:00 amPRNAtzam #4 Update - Significant Initial Oil Production
30th May 20137:35 amPRNGuatemala Update
23rd May 20137:32 amPRNNotice of General Meeting
16th May 20133:25 pmPRNGuatemala Update
16th May 20132:30 pmPRNTrinidad Update
9th May 20134:35 pmRNSPrice Monitoring Extension
3rd May 201310:25 amPRNPresentation on the Proposed Merger with IOP
1st May 20138:21 amPRNQuarterly Activities Report and Appendix 5B
26th Apr 20133:16 pmPRNQ&A on the Proposed Merger with International Petroleum
26th Apr 201310:05 amPRNQuarterly Activities and Cashflow Report
24th Apr 20137:30 amRNSRestoration - Range Resources Limited
24th Apr 20137:30 amPRNRange Proposes to Undertake Strategic Merger
15th Apr 20137:42 amPRNPrecautionary Suspension
15th Apr 20137:40 amRNSSuspension - Range Resources Limited
15th Mar 20138:57 amPRNHalf Yearly Report
11th Mar 20139:19 amPRNTexas Sale Agreement Reached
8th Mar 20137:51 amPRNDebt Financing and Trinidad License Extensions
20th Feb 20138:48 amPRNGuatemala Update
18th Feb 20139:27 amPRNJoint Venture Agreement On Georgian CBM Project
13th Feb 20139:03 amPRNGuatemala Update
11th Feb 201311:11 amPRNTrinidad Update
1st Feb 201312:13 pmPRNWebcast Interview
1st Feb 20137:03 amPRNQuarterly Activities Report and Appendix 5B
25th Jan 20137:00 amPRNStrategic Stake in Citation Resources
24th Jan 20137:12 amPRNTrinidad Update
18th Dec 20127:57 amPRNCompany Update
14th Dec 20121:11 pmPRNStatement re Share Trading
29th Nov 201210:14 amPRNResults of AGM and Company Presentation
15th Nov 20121:33 pmPRNGeorgia, Puntland and Financing Update
1st Nov 20127:00 amPRNMiscellaneous
31st Oct 20127:00 amPRNAnnual Report and Notice of Annual General Meeting
22nd Oct 20127:00 amPRNInvestor Q&A available on website
11th Oct 20127:08 amPRNTrinidad Reserves Upgrade and Financing Package
14th Sep 20125:33 pmPRNInvestor Q&A available on website
10th Sep 20127:20 amPRNTrinidad Update
30th Aug 20127:03 amPRNTrinidad Update â€" Rig 8 Spud
28th Aug 20127:00 amPRNPuntland Drilling Update
21st Aug 20129:25 amPRNJV Partner Trading Halt & Suspension
1st Aug 20127:01 amPRNQuarterly Activities Report and Appendix 5B
30th Jul 20127:46 amPRNInvestor Q and A
27th Jul 20127:50 amPRNPuntland Drilling Update
25th Jul 20127:06 amPRNTrinidad Production Milestone â€" 1,000 Bopd
23rd Jul 20127:11 amPRNPuntland Drilling Update
18th Jul 20124:36 pmPRNShabeel North Drilling Update
17th Jul 20127:41 amPRNInvestor Q&A
26th Jun 20128:12 amPRNTrinidad Operations Update
22nd Jun 20127:26 amPRNPuntland Drilling Update
12th Jun 20128:23 amPRNColombia Farm-In Finalised & New Joint Broker Appointed
8th Jun 20128:02 amPRNTexas Reserves Upgrade
6th Jun 20127:06 amPRNPuntland Update - Shabeel North Spuds

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.