Trinidad Development and Exploration Update

13 May 2015 07:00

RNS Number : 9797M
Range Resources Limited
13 May 2015
 



Trinidad Development and Exploration Update

Range is pleased to provide a Trinidad update with the following highlights:

· Average production in Trinidad in May reached 650 barrels of oil per day (bopd) from an average of 617 bopd in the previous month;

 

· The work programme on the first 13 development and exploration wells to be drilled this year has been finalised;

 

· Range and LandOcean are also finalising 9 additional development and exploration wells to be drilled as part of the 2015 / 2016 work programme;

 

· Funding for these wells is available under the extended 12 month credit facility with LandOcean which has enabled Range to commence its exploration and development programmes. In addition, Range is in discussions with Sinosure and LandOcean to finalise the previously announced US$50 million trade financing package;

 

· All necessary approvals have been received on the first three wells, including an exploration well on the Guayaguayare licence (the Canari North well) and preparations are underway to spud these wells during the current quarter;

 

· During the current quarter to date, the Company has:

o Initiated testing operations on the QU 454ST development well located in the South Quarry field. This well was drilled to a target depth of 2,000 ft. in the previous quarter. The well encountered potential oil bearing sands in three zones and is currently being tested from the lowest zone;

o Brought into production the QU 455 development well, located in the South Quarry field. This well was drilled to a target depth of 890 ft. in the previous quarter. The well is scheduled for optimisation in the short term; and

o Waiting to perforate the QU 456 development well, located in the South Quarry field, subject to relevant government approvals. This well was drilled to 2,002 ft. in the previous quarter.

Upcoming development and exploration work programme

Range and its strategic partner LandOcean Energy Services Co., Ltd (LandOcean) have completed geological and geophysical studies aimed at improving operational efficiency, and sub-surface evaluation, in order to reduce risk and improve well economics by drilling the best possible targets and increasing production potential. These studies have prioritised the first 13 development and exploration wells to be drilled this year (please refer to the table below for further information on these wells). In addition, Range and LandOcean are finalising 9 additional development and exploration wells to be drilled as part of the 2015 / 2016 work programme, the details of which the Company expects to announce shortly.

Funding for these wells is available under the extended 12 month credit facility with LandOcean as announced on 1 May 2015, which enables Range to commence its planned exploration and development programmes in Trinidad immediately. In addition, further to the announcement on 11 December 2014 in relation to the second purchase order under the Integrated Master Services Agreement for US$50 million of services from LandOcean, the Company is currently in the process of amending the purchase order to include provision of drilling services of the developments wells, as well as waterflooding work.

The drilling services will be provided by LandOcean on a turnkey basis and priced in line with market rates in Trinidad, to be reviewed periodically by both parties.

Well

Location

Depth (ft.)

Target Horizon

Development / Exploration

Proposed Spud Date

1. QUN 158

Morne Diablo

2,000

Lower Forest and Upper Cruse

Development

May

2. Canari North

Guayaguayare (Shallow)

5,000

Lower Gros Morne

Exploration

June

3. MD 249

Morne Diablo

3,000

Upper Cruse and Middle Cruse

Development

June

4. QUN 16R

Morne Diablo

2,000

Upper Cruse

Development

Q3 2015*

5. QUN 15 Outstep

Morne Diablo

2,000

Upper Cruse

Development

Q3 2015*

6. QUN 16 Outstep

Morne Diablo

2,000

Upper Cruse

Development

Q3 2015*

7. GGY Deep Commitment

Guayaguayare (Deep)

8,500

Upper Cretaceous

Exploration

Q3 2015*

8. GY 218SE

Beach Marcelle

3,000

Upper Gros Morne

Development

Q3 2015*

9. GY 2R

Beach Marcelle

2,000

Upper Gros Morne

Development

Q4 2015*

10. GY 161S

Beach Marcelle

3,000

Upper Gros Morne

Development

Q3 2015*

11. GY 180SE

Beach Marcelle

4,000

Lower Gros Morne

Development

Q4 2015*

12. GY 68W

Beach Marcelle

1,800

Middle Gros Morne

Development

Q4 2015*

13.GY 300/298W

Beach Marcelle

3,000

Middle Gros Morne

Development

Q4 2015*

*Subject to government and regulatory approvals

Planned work programme on the first 13 wells

The first two development wells QUN 158 and MD 249 are located on the north flank of the Southern Range anticline.

The QUN 158 is a step-out well to be drilled to a total depth of 2,000 feet. The well will be targeting the relatively under-explored Lower Forest 3 sands, which flowed at a stabilised production rate of 120 bopd in the recently drilled QUN 157 well, located 200 feet to the South East. The QUN 158 well will also be testing a less-explored Upper Cruse formation, which is well-developed in nearby QUN 120 and QUN 128 wells.

The MD 249 is an infill well which will be drilled to a total depth of 3,000 ft. to test the prolific Upper Cruse channel sand complex and the extent of the underlying Middle Cruse sand trend, also productive in the immediate area.

The Company will provide a separate announcement during May on the progress of the ongoing drilling preparations on the Canari North exploration well on the Guayaguayare licence, ahead of anticipated well spudding in June 2015.

The Company has received all necessary approvals to proceed with the first three wells (the QUN 158, MD 249, and Canari North wells) and is currently in the process of preparing and submitting the final documents for drilling approvals on the other 10 wells.

In order to improve forward planning and reduce approval-related delays as much as possible, the Company has implemented a new tracking system which has resulted in the submission processes becoming more consistent. Range is in the process of establishing a production planning department to manage the drill locations and planning in advance, including permitting of all drilling locations.

In addition, Range along with other operator companies in Trinidad, has been working with relevant authorities to define better guidelines, which have led to improved submission and approval timelines.

Electromagnetic Surveying (Stratagem)

The Company has also received regulatory approvals to conduct Electromagnetic Surveying in the Morne Diablo and South Quarry fields. This new technology will be used to image shallow resistive bodies and identify possible oil reservoirs at 1,000 feet or less, thus reducing exploration and development risks at a relatively low cost with minimal environmental impact. Based on the potentially high impact these surveys could have, they will be given priority status in all undrilled acreage where shallow hydrocarbon potential may be present.

Range looks forward to providing further operational updates in due course. A full year production forecast will be provided later in Q2 2015.

 

 

 

 Further comment and information

 

Range Resources Limited

Evgenia Bezruchko (Investor Relations)

e. admin@rangeresources.co.uk

t. +44 (0)20 7025 7040

 

Cantor Fitzgerald Europe (Nominated Advisor and Broker)

David Porter / Sarah Wharry (Corporate Finance)

Richard Redmayne (Corporate Broking)

t. +44 (0)20 7894 7000

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLPKBDNABKDBPD
Date   Source Headline
28th May 20128:10 amPRNChange of Director’s Interest Notice
22nd May 201210:49 amPRNCompany Presentation
22nd May 20129:21 amPRNChange of Director's Interest Notices - Appendix 3Y
18th May 20127:50 amPRNLodgement of Open Briefing Puntland
17th May 20121:20 pmPRNPuntland Drilling Update
17th May 20121:07 pmPRNPuntland Update
16th May 20128:55 amPRNTexas and Trinidad Update
14th May 20127:08 amPRNPuntland Update
9th May 20127:29 amPRNGeorgia Update
1st May 20127:15 amPRNQuarterly Activities Report and Appendix 5B
19th Apr 20127:00 amRNSOffer Update
18th Apr 201210:35 amPRNMarket Update
12th Apr 20128:27 amPRNTrinidad Update
12th Apr 20127:44 amPRNPuntland Drilling Update
12th Apr 20127:43 amPRNPuntland Drilling Update
11th Apr 20127:16 amPRNNominated Adviser to Change Name
5th Apr 201212:35 pmRNSCancellation of Admission to AIM
3rd Apr 20127:01 amRNSDirectorate Change
3rd Apr 20127:00 amRNSOffer Update
29th Mar 201211:16 amRNSResult of EGM
26th Mar 20122:18 pmRNSForm 8.3 - Stagecoach Theatre Arts PLC
23rd Mar 201211:27 amRNSForm 8.3 - Stagecoach Theatre Arts
22nd Mar 201210:10 amRNSForm 8.3 - Stagecoach Theatre
20th Mar 20129:29 amPRNPuntland Offshore
16th Mar 20127:58 amPRNHalf Yearly Accounts
13th Mar 20127:00 amRNSForm 8 (OPD) Stagecoach Theatre Arts plc
13th Mar 20127:00 amRNSSupplementary Form (OP) Lifeskills Education
13th Mar 20127:00 amRNSForm 8 (OPD) Lifeskills Education Limited
12th Mar 201212:51 pmRNSRule 2.10 Announcement
12th Mar 201212:07 pmRNSForm 8.3 - Stagecoach Theatre Arts PLC
12th Mar 20127:00 amRNSOffer by Lifeskills Education Limited
9th Mar 20127:47 amPRNNorth Chapman Ranch Update
7th Mar 20122:06 pmPRNPuntland Drilling Update
6th Mar 20127:00 amPRNRange obtains quotation on OTCQX International
28th Feb 20127:00 amRNSHalf Yearly Report
23rd Feb 20127:09 amPRNOperations Update
1st Feb 20128:44 amPRNQuarterly Activities Report for December 2011
31st Jan 201212:47 pmPRNQuarterly Activities and Cashflow Report
27th Jan 20127:00 amPRNTrinidad & Texas Update
25th Jan 201212:34 pmPRNTrinidad - Partnership with Leni Gas & Oil Plc
25th Jan 201212:07 pmPRNTrinidad - Partnership with Leni Gas & Oil Plc
23rd Jan 20127:08 amPRNGeorgia Update â€" Site Construction Underway
17th Jan 20127:00 amPRNSpudding of Historical Puntland Exploration Well
6th Jan 20127:43 amPRNTexas and Corporate Update
30th Dec 20117:17 amPRNTrinidad & Texas Update
23rd Dec 201111:13 amPRNTrinidad & Texas Reserves & Valuation Report
23rd Dec 20117:34 amPRNTexas Update
9th Dec 201112:29 pmPRNOperational Update
6th Dec 20119:07 amPRNCompany Presentation
1st Dec 20117:00 amPRNLetter to Option holders

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.