Singida Project Update

13 Feb 2023 07:00

RNS Number : 6489P
Shanta Gold Limited
13 February 2023
 

13 February 2023

 

Shanta Gold Limited

 

("Shanta Gold" or the "Company")

 

Singida Project Update

 

Shanta Gold (AIM: SHG), the East Africa-focused gold producer, developer and explorer, is pleased to provide investors with a positive update on the construction progress at the Singida Gold Project ("Singida") in Central Tanzania. Please find enclosed a link to the presentation outlining the full details below:

 

https://shantagold.com/investors/presentations/

 

 

Eric Zurrin, Chief Executive Officer, commented:

 

"We are delighted with the great progress being made at Singida, with construction on schedule for first production next month. The completion of this mine will transform Shanta Gold into a 100,000 oz/pa producer with a diversified resource base, de-risking the balance sheet and providing the business with further financial flexibility."

 

 

Singida Project Update Highlights (31 Jan 2023):

 

· Overall construction activity at the Project is 93% complete;

 

· All essential equipment for operation of the gold mine is now delivered to site;

 

· The stockpile of crushed ore has now reached 32,300 tonnes equal to over one month of supply, significantly de-risking the ramp-up period of operations;

 

· The Run of Mine stockpile at the Singida process plant is currently 127,000 tonnes at an average grade of 3.34 g/t containing 13,581 oz of gold equal to approximately 4 months of processing;

 

· The installation of Tailings Storage Facility ("TSF") HDPE liner for partial deposition is on track for completion in March 2023;

 

· Hot commissioning of the NCP-manufactured Milling circuit planned for the second half of February 2023;

 

· Hot commissioning of the COMO engineering elution and electrowinning circuit underway (https://www.comoeng.com.au/singida-gold-project-shipped-to-site/);

 

· Hot commissioning of the full process plant is planned for March 2023; and

 

· Shanta welcomed back George Kondela, new General Manager of Singida, in January 2023 to lead the Singida Gold Mine. George is a Tanzanian national with 24 years of mining experience having worked with Barrick, Randgold, Mineral Deposits, Placer Dome and Pan Australian Resources. George is well known to the Shanta team over the last 20 years and previously worked with Shanta in 2019/20 before being recruited to Barrick. George is a trained geologist and will also focus on reserve life expansion at Singida, where the existing resource base is hugely underexplored and ripe for geological upside across the existing various greenstone deposits.

 

Notes:

1. Excluding 41 kt of gravels mined on surface.

 

 

Enquiries:

 

Shanta Gold Limited

 

Eric Zurrin (CEO)

 +44 (0) 14 8173 2153

Luke Leslie (CFO)

 

 

 

Nominated Adviser and Joint Broker

 

Liberum Capital Limited

 

Scott Mathieson / Ed Thomas / Nikhil Varghese / Lucas Bamber

 +44 (0) 20 3100 2000

 

 

Joint Broker

 

Tamesis Partners LLP

 

Charlie Bendon / Richard Greenfield

 +44 (0) 20 3882 2868

 

 

Public Relations

 

FTI Consulting

 

Sara Powell / Nick Hennis

+44 (0) 20 3727 1426

 

 

 

About Shanta Gold

 

Shanta Gold is an East Africa-focused responsible gold producer, developer, and explorer. The company has an established operational track record, with defined ore resources on the New Luika and Singida projects in Tanzania, with reserves of 645 koz grading 3.0 g/t, and exploration licences covering approximately 800 km2 in the country. Alongside New Luika and Singida, Shanta also owns the high-grade West Kenya Project in Kenya and licences with resources of 1.7 million ounces including 722 koz in the Indicated category grading 11.45 g/t. With a strong balance sheet, a growing diversified portfolio and a maiden dividend paid in 2021, Shanta offers a resilient investment opportunity for the near and long-term. Shanta is quoted on London's AIM market (AIM: SHG) and has approximately 1,051 million shares in issue.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDUURRROBUUAUR
Date   Source Headline
18th Aug 20177:00 amRNSInterim results
18th Aug 20177:00 amRNSTermination of Arrangement Agreement
3rd Aug 20177:00 amRNSChief Executive and Director Change
31st Jul 201711:44 amRNSChange of Registered Office
19th Jul 20177:00 amRNSQ2 2017 Production And Operational Update
5th Jul 201710:03 amRNSUpdate on Tanzanian Legislative Changes
3rd Jul 201712:20 pmRNSResult of Annual General Meeting
30th Jun 20177:00 amRNSProposed Tanzanian Legislative Changes
26th Jun 20171:07 pmRNSHolding(s) in Company
20th Jun 20176:24 pmRNSDirector/PDMR Shareholding
20th Jun 20176:23 pmRNSBlocklisting Six Monthly Return
20th Jun 20175:09 pmRNSResults of Fundraising
20th Jun 20177:02 amRNSProposed Fundraising to raise approximately US$14m
20th Jun 20177:01 amRNSDebt Restructuring
20th Jun 20177:00 amRNSArrangement Agreement To Acquire Helio Resource
13th Jun 20177:01 amRNSFinal Results
13th Jun 20177:00 amRNSAppointment of Non-Executive Director
23rd May 20177:00 amRNSFirst underground ore produced from the NLGM
22nd May 20177:00 amRNSPower Station equipment financing
18th May 20177:00 amRNSEUR2.1 m underground equipment financing
3rd May 20177:00 amRNSNkuluwisi Exploration Update
20th Apr 20177:00 amRNSQ1 2017 Production And Operational Update
23rd Mar 20177:00 amRNSNLGM Revised Mine Plan and Reserves Update
8th Mar 20177:00 amRNSExploration Update, Nkuluwisi, Lupa Goldfields
3rd Mar 20173:13 pmRNSResponse to the Ministry of Energy & Minerals
19th Jan 20177:00 amRNSQ4 2016 Production and Operational Update
20th Dec 201610:52 amRNSReplacement - Director Dealing
20th Dec 20167:00 amRNSDirector Dealing
19th Dec 20167:00 amRNSBlocklisting Six Monthly Return
16th Dec 20167:00 amRNSNLGM Intersects First Underground Ore
23rd Nov 20167:00 amRNSAnalyst site visit
17th Nov 20167:00 amRNS$5.25m silver streaming advanced payment received
2nd Nov 20167:00 amRNSZurich Precious Metals Summit
18th Oct 20167:00 amRNSQ3 2016 Production and Operational Update
3rd Oct 20167:00 amRNSHigh grade intercepts at Singida
7th Sep 20167:00 amRNSIlunga Resource Upgrade
17th Aug 20167:00 amRNSInterim Results
19th Jul 20167:00 amRNSQ2 2016 Production and Operational Update
15th Jul 20167:00 amRNSPilot-scale production to commence at Singida
7th Jul 201611:12 amRNSPassing of Non-Executive Director
6th Jul 20167:00 amRNSNew Luika Gold Mine, Ilunga Exploration Update
27th Jun 20167:00 amRNSNew Luika underground project update
20th Jun 20164:40 pmRNSBlocklisting Six Monthly Return
17th Jun 20167:00 amRNSDirector Dealing in Convertible Loan Notes
14th Jun 20161:04 pmRNSDirector Dealing
8th Jun 20167:00 amRNSCompletion of Convertible Loan Note Restructuring
6th Jun 20163:49 pmRNSResult of Open Offer
2nd Jun 20163:51 pmRNSResult of Annual General Meeting
25th May 20164:17 pmRNSDirectors Dealings
20th May 20167:00 amRNSPosting of Circular and Details of Open Offer

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.