Update on Processing Plant - Lemphane Kimberlite Lesotho

25 Nov 2014 07:00

PARAGON DIAMONDS LTD - Update on Processing Plant - Lemphane Kimberlite Lesotho

PARAGON DIAMONDS LTD - Update on Processing Plant - Lemphane Kimberlite Lesotho

PR Newswire

London, November 24

Paragon Diamonds Limited / Index: AIM / Epic: PRG / Sector: Resources 25 November 2014 Paragon Diamonds Limited ("Paragon"or the "Company") Update onProcessing Plant for Lemphane Kimberlite Project, Lesotho Paragon Diamonds Limited, the AIM quoted vertically integrated diamonddevelopment company in Lesotho, Africa, is pleased to announce the finalisationof the design and order plans for a state of the art processing plant for its80% owned Meso Diamonds' Lemphane kimberlite mine (`the Project'), which islocated among a cluster of kimberlites known for producing large, high valuediamonds. The plant's modular design and use of the latest X-Ray Transmission(XRT) diamond recovery technology will reduce both capital and operating costsat Lemphane, improve diamond recovery, and as a result significantly enhancethe Project's economics. This update is in line with the Company's objective tocommence Stage I production at Lemphane in Q1 2015, which will involve theextraction of 1 million tonnes of kimberlite over a two year period and,according to an independent report, is expected to lead to the recovery of over100 diamonds larger than 9 carats, including stones over 100 carats in size. * Finalisation of design and order plans for US$6 million 75tonne per hour (0.5Mt/yr) processing plant follows a comprehensive analysis of various plant options and evaluation of technologies successfully used by other key industry players previously * Lemphane Project's economics significantly enhanced as a result of the state of the art plant: + Lower operating costs - the plant will incorporate the latest advances in XRT diamond recovery technology which is proven to significantly reduce costs, maximise the recovery of large high value stones and minimise breakages. + Capital costs of Stage II production expected to be significantly reduced from the initial scoping study as a result of the new technology when applied to a full-scale 3Mt/yr plant - it is expected that the overall size and footprint of the plant will reduce along with the associated operating costs + Improved diamond recoveries - XRT technology has been shown to significantly improve diamond recoveries compared to other conventional diamond recovery technology * An upgraded pre-feasibility study, based on the revised 48Mt of kimberlite amenable to open-pit mining and incorporating the latest improvements in both operating and capital costs, including the planned national grid electrification of the region due mid-2015 will be undertaken in due course to verify management's assertions * Titanium Capital Investments Ltd (`Titanium Capital'), a private equity investment company managed by Paragon's Chairman Philip Falzon Sant Manduca, is acting as assuror (for nil consideration) for the pre-ordering costs of the plant supporting Paragon's efforts to prepare for the plant's construction as soon as Stage I production funding negotiations have been successfully concluded - the acquisition of the plant is conditional upon Paragon securing the required funding. The assurance given by Titanium Capital constitutes a Related Party Transaction under AIM Rule 13. The directors, excluding Philip Falzon Sant Manduca consider, having consulted Northland Capital Partners Limited (the Company's Nominated Adviser) that the terms of the assurance are fair and reasonable insofar as the Company's shareholders are concerned. * Board is highly focused on prioritising debt financing over equity as a means of structuring the funding, thereby rewarding existing shareholders by generating maximum value added * Plant is on course to be commissioned in time for commencement of Stage I production in Q1 2015 Paragon's Chairman, Philip Falzon Sant Manduca said, "The construction of this`state of the art' processing plant is a major milestone for Paragon as we homein on our Q1 2015 target for the commencement of Stage I production. AsLemphane is the last, known undeveloped large diamondiferous kimberlite pipe inLesotho, Paragon benefits from last mover advantage, whereby we get to see inpractice the advantages and disadvantages of the various techniques andtechnologies employed on other kimberlites to date, as well as enjoying accessto the latest equipment. We have therefore cherry-picked the best-in-classX-Ray technology for our plant, which not only lowers our forecast operatingcosts but also maximises the recovery rates of large high value stones atLemphane, reduces the potential for breakages, and enhances on-site security. "From the outset, Lemphane's company-making credentials have always been clearto me. By potentially providing a source of large, high value diamonds,Lemphane delivers a strong platform from which we can build Paragon into avertically integrated diamond house, with material interests in upstream anddownstream activities to capture as much value as possible for ourshareholders. Thanks to the plant's modular design its capacity can be easilyscaled up to accommodate Stage II's higher volumes, which along with thecurrent technology to be adopted will translate into a significant reduction inStage II's CAPEX requirement. When measured against a static quantum ofresource, this increases the potential magnitude for future revenues andtherefore substantially improves Lemphane's potentially attractive economics.This lies behind a further increase in Titanium's commitment to Paragon in theform of assurance towards the design and pre-ordering costs of the plant to therelevant contractors, so that we have a greater potential to meet our timetableof production commencing in Q1 2015. I look forward to providing furtherupdates in the near term." Further Information The processing plant will have a name-plate capacity of 75 tonnes per hour, andat a planned utilisation (90%) and availability (92.5%) of approximately 20hours per day, an annual throughput of 0.5Mt/yr is expected. The primaryhead-feed size will be +50-85mm. A 50mm x 25mm x 20mm diamond would typicallyweigh at least 300ct, thus the potential for diamond breakage during primarycrushing operations is reduced. "Tomra®" XRT technology will be used to recover all +15mm diamonds,corresponding to circa 7.5ct for an oblate shape, typical of type IIa diamonds.Furthermore, all XRT feed will be sorted to recover diamonds prior to anysubsequent crushing, and secondary crushing will be at a maximum closed-sizesetting of 35mm, corresponding to circa 100ct for an oblate shape. As such, thevast majority of the one hundred and nineteen +9ct diamonds, including a +100ctdiamond, four 50-100ct and twenty two 20-50ct diamonds predicted from the SizeFrequency Model for the initial 1Mt of mining, will be recovered by the XRTcircuit, without further exposure to a secondary crushing circuit. After coarse diamond recovery, all material will be progressively reduced to-15mm before further processing by traditional Dense Media Separation (DMS) andfluorescent X-ray "FlowSort®" recovery to extract the smaller (
Date   Source Headline
8th Jul 201412:15 pmPRNResult of AGM
8th Jul 20147:00 amPRNAGM Statement
30th Jun 20144:02 pmPRNTotal Voting Rights
9th Jun 20147:00 amPRNIssue of Equity
5th Jun 20147:00 amPRNPositive Modelling Report - Lemphane Diamond Lesotho
3rd Jun 20144:40 pmRNSSecond Price Monitoring Extn
3rd Jun 20144:35 pmRNSPrice Monitoring Extension
23rd May 20149:34 amPRNNotice of AGM and Posting of Annual Accounts
23rd May 20147:00 amPRNAudited Final Results
19th May 20144:40 pmRNSSecond Price Monitoring Extn
19th May 20144:35 pmRNSPrice Monitoring Extension
12th May 20147:00 amPRNUpdate on Lemphane Kimberlite Project, Lesotho
7th Apr 20144:35 pmRNSPrice Monitoring Extension
3rd Apr 201410:15 amPRNUK Investor Show, London, 5 April 2014
26th Mar 20144:40 pmRNSSecond Price Monitoring Extn
26th Mar 20144:35 pmRNSPrice Monitoring Extension
24th Feb 20147:00 amPRNMining Lease finalised for Lemphane Kimberlite
19th Feb 201411:59 amPRNHolding(s) in Company
31st Jan 20143:04 pmPRNTotal Voting Rights
29th Jan 20147:00 amPRNDirectors' Shareholdings
13th Jan 20149:15 amPRNHolding(s) in Company
8th Jan 201411:34 amPRNResult of General Meeting
17th Dec 20137:27 amPRNAcquisition(s)
11th Dec 20137:00 amPRNOperational Update
10th Dec 20137:00 amRNSLemphane Kimberlite Tonnage Estimate Update
29th Nov 20132:18 pmPRNNotice of General Meeting
29th Nov 20137:00 amPRNTotal Voting Rights
25th Nov 20137:00 amPRNDirector Subscription
20th Nov 20137:00 amPRNHolding(s) in Company
15th Nov 20132:55 pmPRNSubscription
4th Nov 20137:00 amPRNNew Licence Award
21st Oct 20131:39 pmPRNHolding(s) in Company
16th Oct 20137:00 amPRNValuation of Diamonds
14th Oct 20137:00 amPRNAward of Mining Licence
19th Sep 20137:00 amPRNInterim Results
31st Jul 201312:09 pmPRNTotal Voting Rights
18th Jul 201311:35 amPRNIssue of Equity
18th Jul 201311:20 amPRNResult of AGM
17th Jul 20137:04 amPRNOperational Update
8th Jul 201312:01 pmPRNIssue of Options
21st Jun 20137:00 amPRNHolding(s) in Company
14th Jun 20137:25 amPRNNotice of Results and AGM
11th Jun 20134:08 pmPRNHolding(s) in Company
7th Jun 20132:52 pmPRNHolding(s) in Company
29th May 20137:02 amPRNSubscription to raise £1.55 million
29th May 20137:01 amPRNPreliminary Results
29th May 20137:00 amPRNAppointment of Nomad & Broker
29th Apr 20137:00 amRNSLemphane Bulk Sampling Program Update
22nd Apr 20133:40 pmRNSAppointment of joint broker
22nd Apr 20137:00 amRNSLemphane Scoping Study Released

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.