Longonjo Update

3 Jan 2024 07:00

Pensana Plc - Longonjo Update

Pensana Plc - Longonjo Update

PR Newswire

LONDON, United Kingdom, January 03

 

 

THIS ANNOUNCEMENT CONTAINS INSIDE INFORMATION

 

Pensana Plc

("Pensana" or the "Company")

 

UPDATE ON CONSTRUCTION ACTIVITIES AT LONGONJO

 

Pensana is pleased to provide the following update on activities at the Longonjo minesite ahead of main construction.

 

As previously announced the early-stage development activities are being funded by a US$15 million bridging loan provided by FSDEA (the Angolan Sovereign Wealth Fund) ahead of the main finance. 

 

The significant activities have been the civil works for the camp, the rehabilitation of the access road to the Longonjo railway station and the agricultural demonstration plots under the Livelihood Restoration Programme.

 

The 4.5 kilometre road linking the site to the Benguela railway line has been upgraded. The enhanced road features include an improved roadbed substructure, a redefined road profile and rapid drainage systems.

 

Serving as the primary route for inbound materials during construction and later for reagent import and the export of Mixed Rare Earth Carbonate in containers, the road connects the mine to the Longonjo station for rail access to the port of Lobito for shipping.

 

The Benguela railway line is part of the Lobito corridor undergoing a US$550 million investment from the US Government. The investment aims to secure critical minerals across central Africa to be exported via the port of Lobito and is anticipated to become one of Africa's most important rail transport systems.

 

 Several kilometres of overhead powerlines, together with an underground water supply and effluent disposal system have been installed ahead of the arrival of the 350-person modular camp, which has been assembled at Johannesburg and is being relocated to site. The camp will be the primary operations base for the construction team.

 

 Agricultural demonstration plots have been established by South African agriculture consultants, Vuna Agri, as part of the Livelihood Restoration Programme. The demonstration plots have an area of nine hectares and have now successfully completed their first full season.  The Livelihood Restoration Programme was established to provide replacement land for any displaced farmers and additionally to provide a training base for those persons affected by the project to develop their agricultural skill sets. 

 

 

The objective is to help local growers and farmers create healthy and sustainable agro-ecosystems, boosting household income in nearby communities, whilst enhancing overall food security. This ongoing programme is being conducted in collaboration with local universities with a view to continually improving farming practices.

 

Tim George CEO commented: "We now have over 50 engineering contractors and Longonjo staff working on site in preparation for the commencement of main construction. There has been a very positive reaction to the activities on site amongst the local community, in particular with the creation of well-paid jobs and the successful implementation of the first phase of the livelihood restoration programme.

 

We have a strong team supporting the main construction which is being manged by MCC a leading project management team with a track record of delivering projects across Africa, including Angola. ADP, the main contractor is an African minerals specialist in the detailed design, construction and commissioning of modular mineral processing plants with extensive development experience in Angola."

 

About Longonjo

 

The electrification of motive power through EVs and Wind Turbines is the biggest energy transition in history and is forecast to generate a demand growth for magnet metal NdPr of 7.5% CAGR over the next decade.

 

Pensana owns one of the world's largest undeveloped rare earth mines, and one of only three with a JORC Reserve >100,000 tonnes of NdPr.

 

At full production Longonjo will produce ~5% of world production of NdPr in the form of an exported mixed rare earth carbonate.

 

The upfront capital cost of US$200 million for the fully permitted mine and processing facilities is amongst the lowest amongst its peers making Pensana highly competitive.

 

Pensana also has a fully permitted US$250 million downstream separation facility at the Saltend Chemicals Park in the Humber Freeport.

 

Financing for each of the Longonjo and Saltend projects is currently underway.

 

The information contained within this announcement is considered by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No.596/2014. Upon the publication of this announcement via a Regulatory Information Service, this inside information will be considered to be in the public domain. The person responsible for arranging for the release of this announcement on behalf of the Company is Paul Atherley, Chairman.

 

- ENDS -

 

 

For further information, please contact:

 

Shareholder/analyst enquiries:

Pensana Plc 

Paul Atherley, Chairman IR@pensana.co.uk

Tim George, Chief Executive Officer

Rob Kaplan, Chief Financial Officer



Date   Source Headline
28th Apr 20264:59 pmPRNHolding(s) in Company
17th Apr 20267:00 amPRNUS$165 million Strategic Investment to support U.S. Mine to Magnet strategy
9th Mar 202611:20 amPRNAdjournment of General Meeting and Corporate Presentation
4th Mar 20267:28 amPRNIncreased US$165 million Strategic Investment to support U.S. Mine to Magnet strategy - Proposed adjournment of General Meeting
3rd Mar 20267:00 amPRNConstruction on track for 2027 first production
10th Feb 20263:10 pmPRNUS$ 160 million Strategic Equity Investment
4th Feb 20267:00 amPRNUpdate on US$25 million Longonjo mine finance
21st Jan 202612:28 pmPRNIssue of Equity
21st Jan 20267:04 amPRNUpdate on Longonjo infill and resource expansion drill programme
14th Jan 202612:28 pmPRNDirectors Dealings
14th Jan 20267:00 amPRNLongonjo Main Construction well underway
23rd Dec 20252:09 pmRNSHolding(s) in Company
23rd Dec 20252:09 pmPRNHolding(s) in Company
19th Dec 202511:08 amRNSIssue of Equity - Updated Admission Date and number of shares to be issued
19th Dec 202511:08 amPRNIssue of Equity - Updated Admission Date and number of shares to be issued
18th Dec 20251:46 pmRNSIssue of Equity
18th Dec 20251:46 pmPRNIssue of Equity
18th Dec 20251:01 pmRNSIssue of Equity
18th Dec 20251:01 pmPRNIssue of Equity
18th Dec 20257:00 amPRNMajor shareholder support for US Strategy
16th Dec 202510:00 amPRNIssue of Equity
15th Dec 20253:15 pmPRNIssue of Equity/Total Voting Rights
9th Dec 20257:00 amPRNUS$100 million Strategic Equity Investment
3rd Dec 202512:08 pmPRNAnnual General Meeting - Chairman's Presentation
3rd Dec 202511:57 amPRNResult of AGM
27th Nov 20257:00 amPRNLongonjo study lifts HREE production fivefold
17th Nov 20257:00 amPRNMajor drill programme to increase Longonjo resource to over one billion tonnes
10th Nov 20257:00 amPRNNotice of Annual General Meeting and Form of Proxy
31st Oct 20258:43 amPRNNew Corporate Presentation
28th Oct 20257:00 amPRNU.S. EXIM debt funding to accelerate U.S. mine-to-magnet supply chain
22nd Oct 20257:00 amPRNPartnership with Vacuumschmelze GmbH to establish mine-to-magnet supply chain in the US
15th Oct 20259:00 amPRNPublication of Annual Report 2025 and Notice of Annual General Meeting
9th Oct 20251:21 pmPRNIssue of Equity
30th Sep 20257:00 amPRNDate of Annual General Meeting and proposed share consolidation
26th Sep 20254:34 pmPRNHolding(s) in Company
25th Sep 20259:15 amPRNNew Corporate Presentation
9th Sep 20257:00 amPRNAppointment of Chief Operating Officer
5th Sep 202511:04 amPRNIssue of Equity
3rd Sep 20254:57 pmPRNHolding(s) in Company
11th Aug 20257:00 amPRNAppointment of US advisor Stonegate Capital Partners
28th Jul 20257:00 amPRNLongonjo construction budget on track and Coola carbonatite drilling
23rd Jun 20257:00 amPRNMOU with ReElement Technologies to develop a sustainable rare earth supply chain
18th Jun 202511:22 amPRNIssue of Equity
18th Jun 20259:17 amPRNHolding(s) in Company
16th Jun 20257:00 amPRNMOU with Toyota Tsusho Corporation for Rare Earth Offtake
13th Jun 20259:59 amPRNHolding(s) in Company
10th Jun 202512:21 pmPRNGrant of Share Awards
10th Jun 202512:19 pmPRNIssue of Equity/Total Voting Rights
5th Jun 202511:10 amPRNIssue of Equity
30th May 20257:00 amPRNGBP 2 million Placement to major institutional shareholders

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.