PROGRESS REPORT

26 Jan 2011 07:00

RNS Number : 0752A
Patagonia Gold PLC
26 January 2011
 



PATAGONIA GOLD PLC

 

Trading Symbol PGD.L

 

  26th January 2011

 

PROGRESS REPORT

CAP-OESTE, COSEGOLD-SILVER PROJECTS

LOMADA GOLD PROJECT

SANTA CRUZ PROVINCE, ARGENTINA

 

Highlights:

 

·; Final drilling results from the recently completed drilling campaign on the COSE project continue to report exceptionally high grade gold and silver, including drill hole CSE-O65-D intersecting 1.00 metre @ 346.60g/t gold and 16,519g/t silver.

 

·; A potential new mineralised vein has been discovered at Cap-Oeste with drill-hole CO-166-D intersecting 1.10 metres @ 435.40g/t gold and 1,006g/t silver within the Esperanza fault zone

 

·; Construction of the 50,000 tonne Heap Leach project at Lomada de Leiva remains on schedule, with the commissioning of the processing facility and commencement of irrigation anticipated for early March 2011.

 

The second stage extension and infill drilling campaign at COSE, comprising 23 diamond HQ core drill-holes for 6,582 metres, was completed in Q4 2010.

 

Results not previously reported include:

Hole No.

From

Interval

Grade

Grade

metres

metres

Au g/t

Ag g/t

CSE-055-D

223.50

4.70

17.88

282

CSE-057-D

208.02

4.09

121.82

2,404

CSE-059-D

230.16

8.14

8.18

466

and

252.00

1.40

24.90

55

CSE-062-D

196.00

4.40

11.53

1,058

CSE-063-D

287.20

6.80

38.66

587

including

287.20

1.80

131.02

1,469

CSE-065-D

200.50

3.50

31.92

66

and

232.40

1.00

346.60

16,519

including

233.15

0.25

1,371.60

60,141

 

Note: PGSA estimates that the reported intervals represent 75 to 80% of the true width of the mineralised structure.

 

El Tranquilo Property Block:

 

The El Tranquilo property block, covering over 60 square kilometres, contains the COSE project, the Cap-Oeste gold and silver project, the Pampa prospect and the Vetas Norte and Breccia Valentina structural trends. The property is located approximately 120km to the south east of the Lomada de Leiva gold project where development of a heap leach operation is currently in progress. 

 

COSE project:

The COSE project contains an advanced exploration target associated with the larger Cap-Oeste gold-silver deposit located 2 kilometres to the north west.

 

The central mineralised breccia zone of COSE, containing the exceptionally high grade gold and silver, has been delineated within an area 120 metres down dip by 35 metres along strike with a true width of 3.5 to 4.5 metres. The second stage drilling campaign, designed to define the limits of the mineralisation for a maiden resource, has shown the deposit to be larger than initially indicated.

The mineralisation remains open in all directions.

 

PGSA has retained Mining Engineers, Chlumsky, Armbrust and Meyer, LLC. (CAM) of Lakewood, Colorado, to independently define and describe a gold and silver Resource at COSE, which complies with Canadian National Instrument 43-101 (NI 43-101). The report, together with a preliminary economic assessment, is scheduled for completion in Q1 2011

 

NCL Ingenieria Y Construccion SA, Chile, has prepared a preliminary cost analysis to evaluate the potential CAPEX and OPEX costs involved in the development of a decline access and an underground mine, using sub-level stoping, for the extraction of the known mineralisation at COSE.

NCL's report will be incorporated into CAM's NI43-101 report.

 

Cap-Oeste project:

The Cap-Oeste project contains the Cap-Oeste Main shoot gold and silver deposit on which an NI43-101 compliant resource of 655,932 ounces of gold equivalent, 88% in the indicated category, has been delineated so far. The mineralisation at Cap-Oeste remains open in all directions.

 

A drilling campaign commenced in Q4 2010 to extend the main shoot down dip and to test the 4 other shoots (B to E) already discovered on the 1,200 metres strike length of the Bonanza fault structure. The drill campaign is ongoing.

 

Drill-hole CO-166-D, designed to test for down dip extension on E shoot, located 200 metres to the west of the Main shoot on the Bonanza fault structure, intersected a potential new mineralised vein reporting 435.40g/t gold and 1,006g/t silver over 1.1 metres within the Esperanza fault zone. The current drill campaign will be amended to further explore this exciting new discovery.

 

The Esperanza fault zone runs east-west sub-parallel on surface to the north-west trending Cap-Oeste Bonanza fault. The two fault zones have opposite dips indicating that they will intersect below the current known mineralisation providing a significant exploration target.

 

A total of 28,500 metres of drilling has been programmed in 2011 for the El Tranquilo property block of which 26,000 metres is allocated to increase the resource base on Patagonia Gold's Flagship Cap-Oeste project.

 

All drill-core was photographed prior to being cut for assaying. Samples were analysed by Alex Stewart (Assayers) Argentina SA. Check assays, standards and laboratory duplicates were performed on a systematic basis at Alex Stewart (Assayers) Argentina SA. The exceptionally high grade results have been analysed by both fire assay and gravimetric gold analysis. Gravimetric analysis is more accurate for extremely high grade gold and silver values and there has been a very good correlation of the gold fire assays values and gravimetric results with overall variation less than 5%.

 

Lomada de Leiva project:

The Lomada de Leiva gold-heap leach project (Lomada project) is located on the La Paloma property block approximately 40km to the south of the town of Perito Moreno and currently contains a Canadian National Instrument 43-101 (NI 43-101) compliant resource of 161,346 ounces of gold in the measured and indicated categories with a further inferred 73,725 ounces of gold.

 

The first stage of the Lomada project consists of constructing a 50,000 tonne trial heap leach pad and processing facility, which based on 70% recovery, is estimated to yield approximately 2,200 ounces of gold for the first 6 metre loading.

 

Construction of the heap leach pad commenced in late September 2010. The heap leach pad's 100m x 100m base area, pregnant and barren solution ponds, plant site and emergency containment dam, mining and placement of approximately 50,000 tonnes of ore on the heap leach pad, have all been completed.

 

The processing facility and irrigation system are both currently being manufactured and are both on schedule for completion and commissioning in March 2011.

 

Subject to successful leaching and additional permitting, further loading and production from the first stage heap leach will continue until the main 5 million tonne heap leach project is fully operational, scheduled for Q4 2011.

 

The features of the main heap leach project are:

 

·; Low pre-production capital of $8.5 million

·; Production of 21,000 oz. of gold/year, for a mine life of 7 years, at a cash cost of $299/oz.

·; Project cash flow before tax, of $63.6 million, based on a cash price of $850/oz. gold.

 

Marc Sale, (BSC. Geology, Fellow AusIMM, member AIG) a Director and consultant to Patagonia Gold Plc and a qualified person as defined in National Instrument 43-101, has reviewed and verified all scientific or technical mining disclosure contained in this press release.

 

ENDS

 

For more information, please contact:

Bill Humphries / Richard Prickett

Patagonia Gold Plc

Tel: +44(0)20 7409 7444

 

Simon Raggett / Angela Peace

Strand Hanson Ltd

Tel: +44(0)20 7409 3494

David Bick / Mark Longson

Square 1 Consulting

Tel : +44(0)20 7929 5599

 

Robin Henshall / Tim Graham

Matrix Corporate Capital LLP

Tel : +44(0)20 3206 7172 / +44(0)20 3206 7206

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLSEUFWIFFSESF
Date   Source Headline
26th Nov 20121:00 pmRNSGold Room commissioned and first gold production
22nd Nov 20127:00 amRNSLomada de Leiva Permit
25th Oct 20126:15 pmRNSPlacing and Subscription
17th Oct 201212:31 pmRNSUpdate: Lomada de Leiva
21st Sep 20124:40 pmRNSSecond Price Monitoring Extn
21st Sep 20124:35 pmRNSPrice Monitoring Extension
17th Sep 20127:00 amRNSHalf Yearly Report
10th Sep 20127:00 amRNSCap-Oeste Resource Update
4th Sep 20124:35 pmRNSPrice Monitoring Extension
20th Aug 20124:35 pmRNSPrice Monitoring Extension
31st Jul 20124:35 pmRNSPrice Monitoring Extension
13th Jul 20124:40 pmRNSSecond Price Monitoring Extn
13th Jul 20124:35 pmRNSPrice Monitoring Extension
9th Jul 20124:35 pmRNSPrice Monitoring Extension
5th Jul 20127:00 amRNSDrilling Report
2nd Jul 20124:35 pmRNSPrice Monitoring Extension
28th Jun 20121:00 pmRNSDirector Shareholding
6th Jun 20125:45 pmRNSResult of AGM
6th Jun 20127:00 amRNSPlacing and Subscription
1st Jun 20127:00 amRNSExercise of Options
30th May 201211:44 amRNSReplacement - Operations Update: Lomada de Leiva
30th May 20127:00 amRNSOperations Update - Lomada de Leiva Gold Project
29th May 20127:00 amRNSExercise of Options
25th May 20127:00 amRNSExercise of Options
14th May 20129:38 amRNSPosting of Annual Report and Notice of AGM
25th Apr 20127:00 amRNS2011 Year End Financial Results
28th Mar 20127:00 amRNSDrilling Update - Cap-Oeste
16th Mar 20124:35 pmRNSPrice Monitoring Extension
14th Mar 20127:00 amRNSExercise of Options
7th Mar 20127:00 amRNSDirector Shareholding
6th Mar 20121:30 pmRNSExercise of Options
21st Feb 20127:00 amRNSCap-Oeste Metallurgical Test Update
20th Feb 20127:00 amRNSGrant of Options
18th Jan 201212:30 pmRNSDirector/PDMR Shareholding
12th Jan 20127:00 amRNSCap-Oeste Drilling Update
5th Jan 20127:00 amRNSACQUISITION OF ESTANCIA 'EL TRANQUILO'
20th Dec 20117:00 amRNSExercise of Options
14th Dec 20117:00 amRNSAppointment of Broker
7th Dec 201112:00 pmRNSCommencement of trading on TSX
6th Dec 20117:00 amRNSDual Listing on TSX
2nd Dec 20117:00 amRNSDirectorate Change
30th Nov 20117:00 amRNSCAP-OESTE UPDATED RESOURCE ESTIMATE
14th Nov 20117:00 amRNSChange of Registrar
3rd Nov 201111:38 amRNSDirector Declaration
2nd Nov 20117:00 amRNSDirectorate Change
31st Oct 20117:00 amRNSProgress Update - COSE
26th Oct 20117:00 amRNSFOMICRUZ SHAREHOLDERS AGREEMENT
24th Oct 20117:00 amRNSDrilling Report
3rd Oct 20113:01 pmRNSIssue of Equity
28th Sep 20117:00 amRNSInterim Statement

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.