Trading Update

25 Jan 2016 07:00

RNS Number : 7859M
Petra Diamonds Limited
25 January 2016
Β 

Β 

Β 

Β 

Β 

Β 

Β 

25 January 2016

LSE: PDL

Β 

Β 

Petra Diamonds Limited

("Petra" or the "Company" or the "Group")

Β 

Trading Update for the Six Months ended 31 December 2015

Β 

Β 

Petra Diamonds Limited announces the following trading update (unaudited) for the six months ended 31 December 2015 (the "Period", "H1 FY 2016" or "H1"), ahead of the publication of the Company's Interim Results for the Period on 22 February 2016.

Β 

Β 

HIGHLIGHTS

Β· Production up 2% to 1,629,403 carats (H1 FY 2015: 1,601,069 carats). The Company has exceeded its production target for H1 of 1.5 Mcts and remains on track to reach full year production guidance of 3.3 - 3.4 Mcts for FY 2016 and ca. 5 Mcts for FY 2019.

Β· Revenue down 28% to US$154.0 million (H1 FY 2015: US$214.8 million); excluding Exceptional Diamonds, revenue of US$144.0 million was down 18% (H1 FY 2015: US$176.1 million).

Β· Diamonds sold down 7% for the Period to 1,303,051 carats (H1 FY 2015: 1,401,575 carats). In line with past years, H2 is expected to be a stronger sales period due to timing of tenders; H2 FY 2016 sales volumes expected to be 1.9 - 2.0 Mcts.

Β· Rough diamond prices down ca. 9% for H1 FY 2016 on a like for like basis in comparison to Q4 FY 2015, however the expected improvement in product mix has favourably impacted the average value per carat achieved for each of the Company's operations. The cashflow impact of lower pricing on Petra's financial results has been mitigated by the significant weakening of the South African Rand over this Period.

Β· Capital expenditure ("Capex") of US$151.3 million (H1 FY 2015: US$125.2 million) including capitalised borrowing costs, in accordance with guidance and the roll out of the Group's expansion programmes; the increase is mainly due to the construction of the new Cullinan plant.

Β· Robust financial position as at 31 December 2015 with net debt of US$324.4 million (30 June 2015: US$171.7 million), cash at bank of US$41.6 million (30 June 2015: US$166.6 million) and debt facilities undrawn and available to the Group of US$177.1 million (30 June 2015: US$255.1 million).

Β· Kimberley Mines transaction completed on 18 January 2016. Petra's FY 2016 production guidance excludes input from the Kimberley Mines operations; the Company will provide an update in due course after the initial handover period.

Β 

Β 

Β 

H1 FY 2016 Sales, Production and Capex - Summary

Β 

Β 

Unit

6 months to

31 Dec 2015

("H1 FY 2016")

6 months to

31 Dec 2014

("H1 FY 2015")

Β 

Variance

12 months to 30 Jun 2015 ("FY 2015")

Sales

Β 

Β 

Β 

Β 

Β 

Revenue

US$m

154.0

214.8

-28%

425.0

Diamonds sold

Carats

1,303,051

1,401,575

-7%

3,168,650

Β 

Β 

Β 

Β 

Β 

Β 

Production

Β 

Β 

Β 

Β 

Β 

ROM diamonds

Carats

1,243,706

1,167,982

+7%

2,276,168

Tailings & other1 diamonds

Carats

385,697

433,087

-11%

910,307

Total diamonds

Carats

1,629,403

1,601,069

+2%

3,186,475

Β 

Β 

Β 

Β 

Β 

Β 

Capex

Β 

Β 

Β 

Β 

Β 

Expansion

US$m

127.0

93.8

+35%

212.0

Sustaining

US$m

12.8

24.8

-48%

47.4

Borrowing costs capitalised

US$m

11.5

6.6

+74%

14.7

Total

US$m

151.3

125.2

+21%

274.1

Β 

Note:

1. 'Other' includes mining of the Ebenhaezer satellite kimberlite pipe at Koffiefontein and alluvial diamond mining at Williamson.

Β 

Β 

Johan Dippenaar, Chief Executive Officer, commented:

"We have made a good start to the year, with production of 1.6 Mcts ahead of our target for H1 FY 2016 of 1.5 Mcts, placing us in a good position to achieve full year guidance of 3.3 - 3.4 Mcts.

Β 

"Importantly our expansion programmes remain on track to deliver the first significant input of undiluted ore from the new mining areas in H2 FY 2016, which will lead to improved ROM grades and a better product mix. Also, the construction of the new plant at Cullinan is on track, and we look forward to the significant benefits this new plant will bring to bear at the mine. As always we remain focused on operational delivery, while maintaining a tight control of our cost base."

Β 

Β 

CONFERENCE CALL

Petra's Chief Executive Officer, Johan Dippenaar, and Finance Director, David Abery, will host two conference calls at 9.30am and 4.00pm GMT today to discuss the H1 FY 2016 Trading Update with investors and analysts. Participants may join the calls by dialling one of the following numbers shortly before the call:

Β 

First Call - 9.30am GMT

From the UK (toll free): 0808 237 0040

From South Africa (toll free): 0800 222 290

From the rest of the world: +44 203 428 1542

Participant passcode: 62477976#

Β 

A replay of the conference call will be available on the following numbers from 12:00pm GMT on the same day:

From UK (toll free): 0808 237 0026

From South Africa and the rest of the world: +44 203 426 2807

Playback passcode: 666249#

Β 

Second Call - 4.00pm GMT / 11.00am EST

This will be a Q&A call only to cater for international investors. Participants are therefore advised to listen to the replay of the earlier conference call in advance, as the main management commentary on the Trading Update and Guidance announcements will not be repeated.

Β 

From the United States (toll free): 1866 928 7517

From the rest of the world: +44 203 428 1542

From the UK (toll free): 0808 237 0040

Participant passcode: 51670993#

Β 

Β 

COMMENTARY

Β 

Production

Β· H1 production increased 2% to 1,629,403 carats (H1 FY 2015: 1,601,069 carats).Β 

Β· Finsch performed well during H1 FY 2016, with overall carat production increasing by 8% to 1,095,078 carats (H1 FY 2015: 1,013,117 carats), driven by continued improvements in the ROM tonnes and grade achieved.

Β· Cullinan's diamond production decreased 18% to 322,366 carats (H1 FY 2015: 391,398 carats), in line with the Company's guidance that it will produce lower tonnages at the mine in FY 2016 in order to focus on grade control. This approach has had a positive impact, with the ROM grade further improving to 27.6cpht in Q2, following the 23.6 cpht achieved in Q1 FY 2016 (H1 2016: overall grade of 25.7 cpht). During the Period, the Company decided to use tailings processing capacity to treat ROM material to assist in addressing previously reported ROM grade challenges.

Β· Production at Koffiefontein increased by 61% to 31,760 carats (H1 FY 2015: 19,676 carats), further to the significant ramp up of the new SLC production area underground, with ROM tonnes treated up 119% to 289,217 tonnes (H1 FY 2015: 132,202 tonnes) and the achieved grade up 18% to 8.6 cpht (H1 FY 2015: 7.3 cpht).

Β· Kimberley Underground's production increased 17% to 84,358 carats (H1 FY 2015: 72,012 carats) due to the increased ROM grade of 15.8 cpht (H1 FY 2015: 12.4 cpht) and the continued treatment of tailings resources to utilise available plant capacity.

Β· Williamson's diamond production decreased 3% to 95,841 carats (H1 FY 2015: 98,949 carats), following planned downtime to effect plant modifications during the Period.

Β 

Sales and Diamond Market

Β· Revenue for H1 FY 2016 was down 28% to US$154.0 million (H1 FY 2015: US$214.8 million) and included the sale of the 23.16 carat pink stone from Williamson for US$10.05 million, as reported on 9 December 2015. Petra retains a 20% interest in the polished resulting from this pink stone, which is expected to be sold in calendar 2016.

Β· The number of carats sold (1,303,051) was lower than carats produced (1,629,403) due to the seasonal timing of Petra's tenders; Petra held two tenders in H1 and will hold four tenders in H2. The cut-off date for production sold in the second tender of FY 2016 was the end of October 2015 and therefore carats produced after this date will be offered for sale in the Company's upcoming first tender of H2 FY 2016.

Β· DiamondΒ inventoryΒ asΒ atΒ 31Β DecemberΒ 2015Β wasΒ 666,357Β caratsΒ valuedΒ atΒ US$57.4Β millionΒ (31Β December 2014: 521,987 carats valued at US$43.6 million).

Β 

Β 

Diamond Market

Β· The rough diamond market continued to be impacted by excess polished inventory in the pipeline, liquidity issues in the midstream, the strong US Dollar and a slowdown in retail demand from China.

Β· A number of steps have been taken to address the market challenges, including reduced supply from the major diamond producers (via production cuts and decreased sales volumes), reduced rough diamond pricing, and increased consumer marketing (both branded and generic diamond marketing). Initial data from the key Christmas sales period shows encouragingly solid results from North America (which accounts for +40% of the market).

Β· In line with most market commentators, Petra expects market conditions to remain stable in H2 FY 2016 (January to June 2016), with the prospect of improved trading conditions in H1 FY 2017 (July to December 2016).

Β 

Diamond Prices

Β· Rough diamond prices were down ca. 9% for H1 FY 2016 on a like for like basis in comparison to Petra's results for Q4 FY 2015. However the impact on Petra's financial results has been mitigated by the significant weakening of the South African Rand over this period, with a closing rate of ZAR15.46 / USD on 31 December 2015 compared to ZAR12.21 / USD on 30 June 2015, while the average rate for the Period was ZAR13.61 / USD (H1 FY 2015: ZAR10.99 / USD).

Β· The table below summarises diamond pricing achieved in H1 FY 2016 set against the last financial year. It also includes a column demonstrating the ranges of values achieved from tender to tender in FY 2015, thereby demonstrating the variability across the full year.

Β 

Mine

Actual1

Β 

Actual

Β 

Actual Ranges of Individual Tender Results3

H1 FY 2016

FY 2015

FY 2015

Carats

US$M

(US$/ct)

(US$/ct)

(US$/ct)

Finsch

912,069

75.2

82

90

82 - 112

Cullinan

227,759

25.0

110

1742

106 - 135

Koffiefontein

21,568

9.9

459

386

226 - 536

Kimberley Underground

61,113

15.5

254

302

246 - 376

Williamson

80,359

29.5

3674

298

217 - 354

Total

1,302,868

155.1

119

n/a

n/a

Β 

Notes:

1. Includes sales to Petra's in-house cutting and polishing subsidiary Tarorite (Pty) Ltd totalling 295.5 carats valued at US$1.28 million across the operations; excludes sales by Helam and Tarorite totalling 477.9 carats, US$0.21m.

2. Excluding Exceptional Diamonds, the average value per carat was US$119.

3. Excluding Exceptional Diamonds.

4. Excluding Exceptional Diamonds, the average value per carat was US$241.

Β 

Β 

Β 

Β 

Expansion projects, Cullinan plant and Capex

Β· The Group's expansion projects at Finsch, Cullinan and Koffiefontein continue to progress well. The development of the SLC at Finsch and the shaft deepening and underground development at Cullinan are key deliverables at these major projects and continue to progress in line with expectations.

Β· The construction of the new Cullinan plant is progressing in line with expectations. During H1, the on-site project teams focused on the completion of bulk earthworks and the commencement of civil and structural construction activities. Engineering design, procurement and off-site fabrication are all on track to meet the end of FY 2017 ramp-up.

Β· Capex for H1 FY 2016 was US$139.8 million (H1 FY 2015: US$118.6 million), split as to US$127.0 million on expansion Capex (H1 FY 2015: US$93.8 million) and US$12.8 million (H1 FY 2015: US$24.8 million) on sustaining Capex. Capex in H1 was in line with the Group's overall budgets for FY 2016.

Β 

Health and safety:

Β· The Group's lost time injury frequency rate ("LTIFR") for H1 FY 2016 was 0.37 (H1 FY 2015: 0.28).

Β 

Corporate

Β· Robust financial position as at 31 December 2015 with debt facilities undrawn and available to the Group of US$177.1 million (30 June 2015: US$255.1 million), cash at bank of US$41.6 million (30 June 2015: US$166.6 million) and net debt of US$324.4 million (30 June 2015: US$171.7 million). Net debt has increased by US$152.7 million largely due to Capex spend of US$151.3 million, in line with expectations.

Β· On 1 December 2015, Petra announced that it had entered into an agreement to acquire an interest in the Kimberley Mines in South Africa from De Beers Consolidated Mines Proprietary Limited in a consortium with Ekapa Mining (Pty) Ltd, an established Kimberley-based diamond tailings producer. The transaction introduces a number of tailings deposits in the Kimberley area, as well as a 6 Mtpa 'state-of-the-art' processing plant, and provides the opportunity to ensure a sustainable future for the diamond mining industry in Kimberley.

The transaction completed on 18 January 2016 and Petra's 49.9% share in the earnings from the Kimberley Mines production will be included within Petra's results reported from that date onwards.

Β· A summary of the Group's current cash, diamond inventories, debtors, borrowings and net debt is set out below.

Β 

Unit

31 December 2015

30 June 2015

31 December 2014

Closing exchange rate used for conversion

Β 

R15.46/US$1

R12.16/US$1

R11.57/US$1

Cash at bank

US$m

41.6

166.6

129.6

Diamond inventories

US$m

Carats

57.4

666,357

33.5

339,489

43.6

521,987

Diamond debtors

US$m

1.4

57.6

0.0

US$ loan notes (including accrued interest)

US$m

302.1

303.3

n/a

Bank loans and borrowings

US$m

63.9

35.0

175.4

Net debt

US$m

324.4

171.7

45.8

Bank facilities undrawn and available

US$m

177.1

255.1

45.2

Β 

Notes:

1. The following exchange rates have been used for this announcement:

a. closing rate as at 31 December 2015 US$1:ZAR15.46 (31 December 2014 US$1:ZAR11.57)

b. average rate H1 FY2016 US$1:ZAR13.61 (H1 FY2015 US$1:ZAR10.99)

2. The following definitions have been used in this announcement:

a. ct: carat

b. cpht: carats per hundred tonnes

c. Exceptional Diamonds: stones that sell for more than US$5 million each

d. LTIFR: lost time injury frequency rate

e. Mcts: million carats

f. mL: metre level

g. Mt: million tonnes

h. ROM: run-of-mine, i.e. relating to production from the primary orebody

i. SLC: sub-level cave, a variation of block caving

3. Diamond inventory carrying values are stated at the lower of cost of production on the weighted average basis or estimated net realisable value.

Β 

~ Ends ~

Β 

Β 

For further information, please contact:

Β 

Petra Diamonds, London Telephone: +44 20 7494 8203

Cathy Malins cathy.malins@petradiamonds.com

Cornelia Grant cornelia.grant@petradiamonds.com

Β 

Buchanan Telephone: +44 20 7466 5000

(PR Adviser)

Bobby Morse bobbym@buchanan.uk.com

Anna Michniewicz annam@buchanan.uk.com

Β 

RBC Capital Markets Telephone: +44 20 7653 4000

(Joint Broker)

Matthew Coakes matthew.coakes@rbccm.com

Jonathan Hardy jonathan.hardy@rbccm.com

Β 

Barclays Telephone: +44 20 7623 2323

(Joint Broker)

Bertie Whitehead bertie.whitehead@barclays.com

Philip Drake philip.e.drake@barclays.com

Β 

Β 

Β 

Β 

Β 

About Petra Diamonds Limited

Petra Diamonds is a leading independent diamond mining group and an increasingly important supplier of rough diamonds to the international market. The Company has interests in six producing operations: five mines in South Africa (Finsch, Cullinan, Koffiefontein and Kimberley Underground), extensive tailings operations in Kimberley (via its interest in the Kimberley Mines, and one mine in Tanzania (Williamson). It also maintains an exploration programme in Botswana.

Β 

Petra has a core objective to steadily increase annual production to ca. 5 million carats by FY 2019. The Group has a significant resource base of ca. 300 million carats.

Β 

Petra conducts all operations according to the highest ethical standards and will only operate in countries which are members of the Kimberley Process. Petra is quoted with a premium listing on the Main Market of the London Stock Exchange under the ticker 'PDL'. For more information, visit the Company's website at www.petradiamonds.com.Β 

Β 

Β 

Β 

APPENDIX - MINE BY MINE PRODUCTION TABLES

Β 

Β 

Finsch - South Africa

Β 

Β 

Unit

H1 FY 2016

H1 FY 2015

Variance

FY 2015

Β 

Sales

Β 

Β 

Β 

Β 

Β 

Revenue

US$m

75.2

77.3

-3%

185.4

Diamonds sold

Carats

912,069

906,214

+1%

2,067,933

Average price per carat

US$

82

85

-4%

90

Β 

Β 

Β 

Β 

Β 

Β 

ROM Production

Β 

Β 

Β 

Β 

Β 

Tonnes treated

Tonnes

1,656,256

1,530,455

+8%

3,016,385

Diamonds produced

Carats

749,954

651,068

+15%

1,298,914

GradeΒΉ

Cpht

45.3

42.5

+7%

43.1

Β 

Β 

Β 

Β 

Β 

Β 

Tailings Production

Β 

Β 

Β 

Β 

Β 

Tonnes treated

Tonnes

1,236,328

1,216,244

+2%

2,656,471

Diamonds produced

Carats

345,124

362,049

-5%

766,960

GradeΒΉ

Cpht

27.9

29.8

-6%

28.9

Β 

Β 

Β 

Β 

Β 

Β 

Total Production

Β 

Β 

Β 

Β 

Β 

Tonnes treated

Tonnes

2,892,584

2,746,699

+5%

5,672,856

Diamonds produced

Carats

1,095,078

1,013,117

+8%

2,065,875

Β 

Β 

Β 

Β 

Β 

Β 

Capex

Β 

Β 

Β 

Β 

Β 

Expansion Capex

US$m

25.4

28.4

-11%

65.1

Sustaining Capex

US$m

2.6

8.1

-68%

16.1

Borrowing Costs Capitalised

US$m

4.6

3.0

+53%

6.8

Total Capex

US$m

32.6

39.5

-17%

88.0

Β 

Note:

1. The Company is not able to precisely measure the ROM / tailings grade split because ore from both sources is processed through the same plant; the Company therefore back-calculates the grade with reference to resource grades.

Β 

Β 

Β 

Cullinan - South Africa

Β 

Β 

Unit

H1 FY 2016

H1 FY 2015

Variance

FY 2015

Sales

Β 

Β 

Β 

Β 

Β 

Revenue

US$m

25.0

77.7

-68%

122.2

Diamonds sold

Carats

227,759

314,957

-28%

700,896

Average price per carat

US$

110

2471

-56%

1742

Β 

Β 

Β 

Β 

Β 

Β 

ROM Production

Β 

Β 

Β 

Β 

Β 

Tonnes treated

Tonnes

1,180,399

1,292,895

-9%

2,513,004

Diamonds produced

Carats

303,400

333,770

-9%

611,993

Grade

Cpht

25.7

25.8

0%

24.4

Β 

Β 

Β 

Β 

Β 

Β 

Tailings Production

Β 

Β 

Β 

Β 

Β 

Tonnes treated

Tonnes

397,158

1,212,368

-67%

2,458,306

Diamonds produced

Carats

18,966

57,628

-67%

117,503

Grade

Cpht

4.8

4.8

0%

4.8

Β 

Β 

Β 

Β 

Β 

Β 

Total Production

Β 

Β 

Β 

Β 

Β 

Tonnes treated

Tonnes

1,577,557

2,505,263

-37%

4,971,310

Diamonds produced

Carats

322,366

391,398

-18%

729,496

Β 

Β 

Β 

Β 

Β 

Β 

Capex

Β 

Β 

Β 

Β 

Β 

Expansion Capex

US$m

73.2

47.0

+56%

104.8

Sustaining Capex

US$m

4.4

3.4

+29%

8.8

Borrowing Costs Capitalised

US$m

6.9

3.6

+92%

7.9

Total Capex

US$m

84.5

54.0

+57%

121.5

Β 

Notes:

1. Excluding Exceptional Diamonds, the average value for H1 FY 2015 was US$124 per carat.

2. Excluding Exceptional Diamonds, the average value for FY 2015 was US$119 per carat.

Β 

Β 

Koffiefontein - South Africa

Β 

Β 

Unit

H1 FY 2016

H1 FY 2015

Variance

FY 2015

Sales

Β 

Β 

Β 

Β 

Β 

Revenue

US$m

9.9

7.1

+39%

17.8

Diamonds sold

Carats

21,568

18,215

+18%

46,033

Average price per carat

US$

457

389

+17%

386

Β 

Β 

Β 

Β 

Β 

Β 

ROM Production

Β 

Β 

Β 

Β 

Β 

Tonnes treated

Tonnes

289,217

132,202

+119%

341,783

Diamonds produced

Carats

24,840

9,709

+156%

27,756

Grade

Cpht

8.6

7.3

+18%

8.1

Β 

Β 

Β 

Β 

Β 

Β 

Tailings / Ebenhaezer Production

Β 

Β 

Β 

Β 

Β 

Tonnes treated

Tonnes

262,542

329,965

-20%

524,244

Diamonds produced

Carats

6,920

9,967

-31%

17,628

Grade

Cpht

2.6

3.0

-13%

3.4

Β 

Β 

Β 

Β 

Β 

Β 

Β 

Β 

Total Production

Β 

Β 

Β 

Β 

Β 

Tonnes treated

Tonnes

551,759

462,167

+19%

866,027

Diamonds produced

Carats

31,760

19,676

+61%

45,384

Β 

Β 

Β 

Β 

Β 

Β 

Capex

Β 

Β 

Β 

Β 

Β 

Expansion Capex

US$m

14.0

12.3

+14%

23.1

Sustaining Capex

US$m

1.3

1.2

+9%

3.7

Total Capex

US$m

15.3

13.5

+13%

26.8

Β 

Β 

Kimberley Underground - South Africa

Β 

Β 

Unit

H1 FY 2016

H1 FY 2015

Variance

FY 2015

Sales

Β 

Β 

Β 

Β 

Β 

Revenue

US$m

15.5

18.1

-14%

41.8

Diamonds sold

Carats

61,113

56,470

+8%

138,052

Average price per carat

US$

253

321

-21%

302

Β 

Β 

Β 

Β 

Β 

Β 

ROM Production

Β 

Β 

Β 

Β 

Β 

Tonnes treated

Tonnes

483,110

578,761

-17%

1,196,269

Diamonds produced

Carats

76,240

72,012

+6%

137,226

Grade

Cpht

15.8

12.4

+27%

11.5

Β 

Β 

Β 

Β 

Β 

Β 

Tailings Production

Β 

Β 

Β 

Β 

Β 

Tonnes treated

Tonnes

198,203

n/a

n/a

n/a

Diamonds produced

Carats

8,118

n/a

n/a

n/a

Grade

Cpht

4.1

n/a

n/a

n/a

Β 

Β 

Β 

Β 

Β 

Β 

Total Production

Β 

Β 

Β 

Β 

Β 

Tonnes treated

Tonnes

681,313

578,761

+18%

1,196,269

Diamonds produced

Carats

84,358

72,012

+17%

137,226

Β 

Β 

Β 

Β 

Β 

Β 

Capex

Β 

Β 

Β 

Β 

Β 

Expansion Capex

US$m

6.0

4.5

+33%

10.5

Sustaining Capex

US$m

1.8

1.4

+29%

3.4

Total Capex

US$m

7.8

5.9

+32%

13.9

Β 

Β 

Williamson - Tanzania

Β 

Β 

Unit

H1 FY 2016

H1 FY 2015

Variance

FY 2015

Sales

Β 

Β 

Β 

Β 

Β 

Revenue

US$m

29.5

34.6

-15%

62.1

Diamonds sold

Carats

80,359

98,270

-18%

208,351

Average price per carat

US$

366

352

+4%

298

Β 

Β 

Β 

Β 

Β 

Β 

ROM Production

Β 

Β 

Β 

Β 

Β 

Tonnes treated

Tonnes

1,824,915

2,002,080

-9%

4,056,638

Diamonds produced

Carats

89,272

95,506

-7%

194,048

Grade

Cpht

4.9

4.8

+2%

4.8

Β 

Β 

Β 

Β 

Β 

Β 

Β 

Β 

Alluvial Production

Β 

Β 

Β 

Β 

Β 

Tonnes treated

Tonnes

207,221

170,052

+22%

369,406

Diamonds produced

Carats

6,569

3,443

+91%

8,216

Grade

Cpht

3.2

2.0

+60%

2.2

Β 

Β 

Β 

Β 

Β 

Β 

Total Production

Β 

Β 

Β 

Β 

Β 

Tonnes treated

Tonnes

2,032,136

2,172,132

-6%

4,426,044

Diamonds produced

Carats

95,841

98,949

-3%

202,265

Β 

Β 

Β 

Β 

Β 

Β 

Capex

Β 

Β 

Β 

Β 

Β 

Expansion Capex

US$m

8.7

1.6

+444%

8.3

Sustaining Capex

US$m

1.0

4.3

-77%

7.9

Total Capex

US$m

9.7

5.9

+64%

16.2

Β 

Β 

Capex reconciliation

Β 

Capex

Unit

H1 FY 2016

H1 FY 2015

Variance

FY 2015

Finsch

US$m

32.6

39.5

-17%

88.0

Cullinan

US$m

84.5

54.0

+57%

121.5

Koffiefontein

US$m

15.3

13.5

+13%

26.8

Kimberley Underground

US$m

7.8

5.9

+32%

13.9

Williamson

US$m

9.7

5.9

+64%

16.2

Helam

US$m

0.0

0.4

n/a

0.3

Subtotal - Capex incurred by operation

US$m

149.9

119.2

+26%

266.7

Corporate / exploration

US$m

2.2

5.9

-63%

7.2

Petra internal projects division - Capex under construction / invoiced to operations

US$m

0.1

0.1

0%

0.2

Other Corporate - Capex under construction / invoiced to operations

US$m

(0.9)

n/a

n/a

n/a

Total Group Capex

US$m

151.3

125.2

+21%

274.1

Β 

Notes:

1. Capex for the Period includes US$11.5 million (H1 FY 2015: US$6.6 million) of capitalised borrowing costs, which is also included in the applicable mine by mine tables above.

2. Petra's annual Capex guidance is cash based and excludes capitalised borrowing costs. Given that the majority of Petra's debt funding is in relation to its expansion and development programmes, Petra's guidance is to assume that the majority of interest and financing fees will be capitalised for the duration of the project phase and not expensed through the income statement.Β 

3. The Group (Petra internal projects and Other Corporate) incurs capital spend on behalf of the operations and although this spend is reported in the Group's total Capex, it is policy not to account for it on a specific mine's Capex until the work completed is invoiced to the relevant operation. Group Capex includes US$0.8 million for the Period (H1 FY 2015: US$0.1 million), which was incurred and invoiced by the Group's internal projects facility and Corporate division. Therefore the mine by mine tables plus the internal projects and other corporate Capex will add together to make the Capex total in the relevant sections above.

Β 

Β 

Β 

Β 

This information is provided by RNS
The company news service from the London Stock Exchange
Β 
END
Β 
Β 
TSTPGUBWGUPQGQP
Date   Source Headline
30th Mar 202112:00 pmPRNNotification of Q3 FY 2021 Trading Update
30th Mar 20217:00 amPRNUpdate re the Publication of Report on Williamson Mine
25th Mar 202111:36 amPRNResponse to report published by RAID
17th Mar 20214:11 pmPRNHolding(s) in Company
16th Mar 20211:31 pmPRNHolding(s) in Company
15th Mar 20216:30 pmPRNHolding(s) in Company
15th Mar 20214:01 pmPRNHolding(s) in Company
15th Mar 202112:58 pmPRNHolding(s) in Company
12th Mar 20213:43 pmPRNHolding(s) in Company
12th Mar 20213:39 pmPRNHolding(s) in Company
10th Mar 20218:05 amPRNCompletion of the Restructuring
10th Mar 20218:05 amPRNDirectorate Change
9th Mar 20212:42 pmPRNUpdate regarding the Restructuring
5th Mar 202112:00 pmPRNSale of 299 carat diamond for US$12.18 million
24th Feb 202110:53 amPRNNotice of Scheme Conditions Effective Date
16th Feb 20217:00 amPRNInterim Results for the six months to 31 Dec 2020
9th Feb 20212:46 pmPRNUpdate re Allegations of human rights abuses at WDL
19th Jan 20217:00 amPRNTrading Update for the Six Months ended 31 December 2020
15th Jan 20213:15 pmPRNBlocklisting - Interim Review
13th Jan 20219:47 amPRNResults of Special General Meeting
12th Jan 20213:13 pmPRNScheme Sanction Hearing Results
8th Jan 20212:02 pmPRNScheme Meeting Results
4th Jan 20214:24 pmPRNNotice of Scheme Sanction Hearing
30th Dec 20204:40 pmRNSSecond Price Monitoring Extn
30th Dec 20204:35 pmRNSPrice Monitoring Extension
24th Dec 202012:40 pmRNSSecond Price Monitoring Extn
24th Dec 202012:35 pmRNSPrice Monitoring Extension
22nd Dec 20204:41 pmRNSSecond Price Monitoring Extn
22nd Dec 20204:35 pmRNSPrice Monitoring Extension
22nd Dec 20203:29 pmPRNHolding(s) in Company
22nd Dec 20203:24 pmPRNAppointment of Non-Executive Director
22nd Dec 20203:19 pmPRNPublication of Prospectus
17th Dec 20204:40 pmRNSSecond Price Monitoring Extn
17th Dec 20204:36 pmRNSPrice Monitoring Extension
17th Dec 202011:55 amPRNResult of AGM
11th Dec 20204:40 pmRNSSecond Price Monitoring Extn
11th Dec 20204:35 pmRNSPrice Monitoring Extension
10th Dec 20206:22 pmPRNDetails of Scheme Meeting
10th Dec 20204:41 pmRNSSecond Price Monitoring Extn
10th Dec 20204:36 pmRNSPrice Monitoring Extension
7th Dec 20204:36 pmRNSPrice Monitoring Extension
3rd Dec 20205:33 pmPRNLock-Up Agreement accession results Early Bird Deadline
3rd Dec 202012:04 pmPRNIssue of Settlement Advisory Notice
2nd Dec 20205:29 pmPRNNotice of Scheme Convening Hearing
25th Nov 20207:00 amPRNLetlapa Tala Collection Tender achieves US$40.36m
24th Nov 202012:05 pmPRNHolding(s) in Company
17th Nov 20206:45 pmPRNPetra issues Practice Statement Letter
17th Nov 20206:24 pmPRNRestructuring: Signing of Lock-Up Agreement
17th Nov 20207:10 amPRNReport on Payments to Governments
17th Nov 20207:05 amPRNAnnual & Sustainability Reports & Notice of AGM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.