Â
OPG Power Ventures Plc, the developer and operator of group captive power plants in India, is pleased to announce that, further to the announcement dated the 9th February 2010, a new Air Pre-Heater unit (in place of the one that failed during commissioning trials) has been delivered to its 77MW Chennai plant by the vendor, Ansaldo Caldaie India Pvt Ltd.
Â
The installation, integration and fitting of this replacement unit has commenced at the site and, on completion of this activity, which is anticipated to take a few weeks, the Company expects to recommence final commissioning trials in April.
Â
A further announcement regarding the final commissioning will be issued as soon as the same is accomplished.
Â
Â
Â
For further information, please visit www.opgpower.com or contact:
Â
|
OPG Power Ventures Plc |
|
|
Arvind Gupta (Managing Director) |
+44 (0) 7814 830 893 +91 (0) 98400 96299 +91 (0) 44 429 11 222 Â |
|
V. Narayan Swami (Finance Director) |
+91 (0) 99400 17927 +91 (0) 44 42911214 Â |
|
Martin Gatto (Senior Non Executive Director) |
+44 (0) 7778 749 223 |
|
|
|
|
Cenkos Securities (Nominated Adviser & Broker) |
+44 (0) 20 7397 8900 |
|
Stephen Keys/ Camilla Hume |
|
|
|
|
|
Tavistock Communications |
+44 (0) 20 7920 3150 |
|
Simon Hudson / Nick Peters/ James Midmer |
|
Â
Â
Follow the stocks