2011 Outlook

17 Dec 2010 07:00

RNS Number : 1350Y
Melrose Resources PLC
17 December 2010
 



For immediate release 17 December 2010

 

 

 MELROSE RESOURCES PLC

 

2011 Production Outlook and Capital Expenditure Programme

 

 

Melrose Resources plc (LSE: MRS) ("Melrose" or "the Company"), the oil and gas exploration, development and production company, today provides a review of its 2011 production outlook and capital expenditure programme. 

 

Production Outlook

 

The Company currently forecasts an average daily production rate in 2011 of 21.7 Mboepd on a net entitlement basis, assuming a Brent oil price of $75 per barrel. This represents a 24 percent increase compared to the 2010 production level which is expected to average approximately 17.5 Mboepd for the year. The forecast comprises 87 percent gas and 13 percent hydrocarbon liquids.

 

The forecast is based on production from Melrose's existing oil and gas fields in Egypt, Bulgaria and East Texas USA which contribute 65 percent, 34 percent and 1 percent of the total, respectively. It excludes any contribution from the Company's Permian Basin assets in the USA and in the event that the Company does not proceed with plans to divest these assets the 2011 production forecast would be increased by 0.8 Mboepd.

 

On a working interest basis, the 2011 production forecast is 44.0 Mboepd, some 8 percent higher than the current 2010 market guidance of 40.7 Mboepd.

 

Capital Work Programme

 

Melrose is planning an active work programme during 2011, with an increased emphasis on exploration initiatives and with investment tailored to allow a reduction in the Company's financial gearing towards 100 percent by year end. The total capital expenditure is forecast at $112 million of which approximately 47 percent is allocated to seismic acquisition and exploration drilling on a number of potentially high impact exploration plays. On a country basis, Egypt, Bulgaria, Romania and Turkey account for 61 percent, 16 percent, 16 percent and 7 percent of the forecast, respectively.

 

The work programme retains some flexibility and approximately $77 million of the capital forecast is considered to be firm with the remaining $35 million contingent. The contingencies relate to the optimisation of incremental development projects on the Company's main producing fields in Egypt and finalisation of the concession agreements and other approvals required to commence seismic operations offshore Romania.

 

In parallel with the implementation of the capital work programme, the Company plans to secure one or more new business development opportunities during 2011 with the potential to add material reserves and value. Consistent with the Company's strategy, the focus will be on assets with term development and exploration activity located in low cost operating areas where the Company has, or can create, a competitive advantage.

 

Exploration

 

The seismic acquisition programme will evaluate several of the Company's exploration licences including the Rhone Maritime offshore southern France (where Melrose is carried for the costs of a 2D survey), Mesaha in southern Egypt, South Mardin in Turkey, Block Galata offshore Bulgaria and the Muridava (EX-27) and Est Cobalcescu (EX-28) blocks offshore Romania.

 

On the Rhone Maritime concession, a 7,500 kilometre 2D seismic survey commenced on 1 December 2010 and is expected to complete within approximately three months. The survey is designed to evaluate a number of exploration plays which have been successful elsewhere in the Mediterranean region including a shallow Pliocene channel sand system and structural Miocene plays beneath the Messinian salt layer. On Mesaha it is planned to acquire up to 1,500 kilometres of 2D data over the southern area of the basin. This survey will be acquired using modified acquisition parameters in an attempt to enhance the seismic imaging deep in the section and is expected to complete late in the second quarter. On South Mardin a provision has been made to acquire a 250 kilometre 2D data over the large Ceylanpinar structure in the third quarter of the year.

 

Elsewhere, in Bulgaria a 500 square kilometre 3D survey is planned on Block Galata to ascertain whether the Galata-Kaliakra gas play extends into the centre of the block and in Romania some 900 kilometres of 2D and 1,300 square kilometres of 3D data acquisition is planned on the Muridava and Est Cobalcescu concessions. The latter surveys are contingent on finalisation of the Concession Agreements for the blocks and timely receipt of the regulatory approvals required to commence seismic operations.

 

The drilling programme includes a number of key wells. In Turkey, the South West Kanun well will commence drilling in March to test a structure which lies to the east of the South Mardin concessions and has gross mean prospective resources of 85 MMbbls with a 20 percent chance of success. In Bulgaria, the Company plans to drill the East Kaliakra prospect which is on the Galata-Kaliakra field trend and has prospective resources of 59 Bcf and a 34 percent chance of success. In Egypt, two wells are planned in the second half of the year to test the undrilled Cretaceous oil play in the South East Mansoura concession. The resource potential estimate for this new play will be refined once the data from the 3D seismic survey which is currently being completed on the block have been processed and interpreted.

 

Development

 

The majority of the planned development expenditure, some $53 million, is allocated to the Company's main producing fields in Egypt. On the West Dikirnis field it is planned to expand the existing Liquid Petroleum Gas plant with a refrigeration unit to increase hydrocarbon liquids recoveries and to drill up to three horizontal wells. On West Khilala, wellhead compression facilities are being planned for installation late in the year, although the exact timing is contingent on production optimization studies. A small amount of capital, $5.0 million, is also included in the forecast to purchase long lead time equipment for the East Kavarna development, including the subsea tree.

 

Commenting on the above, David Thomas, Chief Executive, said:

 

"We are looking forward to 2011 when we will start to see the full benefit of the increase in cash flow from our new Bulgarian developments. This will provide the Company with a very strong platform and allow us to re-focus on exploration and business development initiatives whilst reducing financial gearing".

 

For further information please contact:

 

Melrose Resources plc

David Thomas, Chief Executive

Robert Adair, Executive Chairman

Diane Fraser, Finance Director

 

 

0131 221 3360

Buchanan Communications

Tim Thompson

Ben Romney

 

0207 466 5000

 

 

or visit www.melroseresources.com

 

 

Glossary:

Bcf - billion cubic feet of gas

MMbbls - million barrels

Mboepd - thousand barrels of oil equivalent per day

Disclaimer

This announcement contains certain forward-looking statements that are subject to the usual risk factors and uncertainties associated with the oil and gas exploration and production business. While Melrose believes the expectations reflected herein to be reasonable, the actual outcome may be materially different owing to factors either within or beyond Melrose's control, and accordingly no reliance may be placed on the figures contained in such forward looking statements.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCEAKAKFLLEFFF
Date   Source Headline
9th Jun 20067:01 amRNSProposed Placing & Open Offer
24th May 20065:57 pmRNSAnnual Information Update
22nd May 20061:16 pmRNSOperational Update
5th May 20064:01 pmRNSDocument Availability
21st Apr 200611:54 amRNSEgypt Exploration Update
13th Apr 20067:01 amRNSProposed Acquisition
31st Mar 20067:03 amRNSFinal Results
21st Mar 20062:57 pmRNSNotice of Results
6th Mar 20069:24 amRNSHolding(s) in Company
10th Feb 200612:02 pmRNSHolding(s) in Company
7th Feb 20064:16 pmRNSHolding(s) in Company
27th Jan 20069:27 amRNSAdditional Listing
23rd Jan 20065:51 pmRNSBlock Listing Return
23rd Jan 200612:39 pmRNSSubstantial Shareholder
12th Jan 20062:00 pmRNSSubstantial Shareholder
11th Jan 20067:00 amRNSOperational Update
8th Dec 20057:00 amRNSOperational Update
21st Nov 20053:11 pmRNSSubstantial Shareholder
21st Nov 20053:07 pmRNSSubstantial Shareholder
4th Nov 20057:00 amRNSOperational Update
21st Oct 20052:10 pmRNSSubstantial Shareholder
20th Oct 20057:00 amRNSOperational Update
4th Oct 20057:00 amRNSAppt. of Joint Broker
22nd Sep 200510:20 amRNSEgyptian Drilling Results
20th Sep 20057:02 amRNSDrilling Report
1st Sep 20057:01 amRNSInterim Results
18th Aug 200512:45 pmRNSNotice of Results
29th Jul 20057:01 amRNSOperations Update
1st Jul 20053:37 pmRNSGrant of Share Options
1st Jul 200512:50 pmRNSCompany Holding
30th Jun 20057:00 amRNSBlock Listing Return
27th Jun 20051:26 pmRNSDrilling Report
20th Jun 20052:43 pmRNSAGM Statement
6th Jun 20057:00 amRNSSale of Interest
1st Jun 20059:12 amRNSSubstantial Shareholding
6th May 20057:30 amRNSIssue of Equity
27th Apr 20052:58 pmRNSEl Mansoura Concession Update
18th Apr 20053:23 pmRNSDirector Dealings
6th Apr 20052:51 pmRNSDividend Timetable
31st Mar 20057:01 amRNSFinal Results
9th Mar 200512:09 pmRNSNew Concession Area
25th Feb 200510:18 amRNSAward of New Concession
24th Feb 20057:00 amRNSNotice of Results
24th Jan 20057:00 amRNSDrilling & Operations Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.