Progress with DFS at RCPP

21 Aug 2014 08:31

RNS Number : 7127P
Kibo Mining Plc
21 August 2014
 

Kibo Mining Plc (Incorporated in Ireland)

(Registration Number: 451931)

(External registration number: 2011/007371/10)

Share code on the JSE Limited:KBO Share code on the AIM:

KIBO ISIN:IE00B61XQX41

("Kibo" or "the Company")

 

 

21 August 2014

 

 

 

Updates on Progress with Rukwa Coal to Power Project ("RCPP") Definitive Mining Feasibility Study ("DFS")

 

· Phase 1 of Stage 1 of the DFS fully underway;

 

· Initial benchmarks met;

 

· Discussions on power coal and connection agreements progressing;

 

The initial focus of the DFS was to test the key benchmark assumptions that will determine the economic viability of the Rukwa coal mine, as a long-term reliable coal supplier to the planned 300MW mine mouth Rukwa Power Station. To date the following key benchmark assumptions have been subjected to a first pass assessment and delivered positive results, justifying further definitive feasibility work:

 

· Excellent potential to mine the Rukwa deposit successfully and economically, based on current coal quantity and quality;

· Suitable calorific values to match the fuel requirements for the planned Rukwa Power Plant;

· Acceptable ash and volatile matter content;

· Early principle decision that it will not be necessary to subject the coal feed to the Rukwa Power Plant to a washing process. (A final decision in this regard will follow upon completion of advanced feasibility work);

· Sufficient coal in the current Mineral Resource, to sustain the Rukwa Power Plant for a period of up to 40 years.

 

Louis Coetzee, CEO of Kibo Mining, said: "We are pleased with the positive progress and outcomes on the Rukwa DFS to date. It is important to note that the above results represent the findings from early assessments. The early DFS outcomes, referred to above, are also providing valuable support to the discussions on the finalization of the Heads of Terms for the Power Purchase Agreement, Grid Connection Agreement and Coal Sale Agreement.

 

These initial results bode well for a successful outcome from the DFS and we are confident of continued positive results as the studies continue."

 

 

 

 

 

Contacts

Louis Coetzee

+27 (0) 83 2606126

Kibo Mining plc

Chief Executive Officer

Andreas Lianos

+27 (0) 83 4408365

River Group

Corporate Adviser and Designated Adviser on JSE

Jon Belliss

Abigail Wayne

+44 (0) 20 3693 1470

Hume Capital Securities Plc

Broker

Oliver Morse

Trinity McIntyre

+61 8 94802500

+61 8 94802500

RFC Ambrian Limited

Nominated Adviser on AIM

Daniel Thöle

Lydia Eades

+44 (0) 203 772 2500

+44 (0) 203 772 2500

 Bell Pottinger

Investor and Media Relations

 

 

Kibo Mining - Notes to editors

 

Kibo Mining is listed on the AIM market in London and the AltX in Johannesburg. The Company is focused on exploration and development of mineral projects in Tanzania, and controls one of Tanzania's largest mineral right portfolios. Tanzania provides a secure and stable operating environment for the mineral resource industry and Kibo Mining therein.

 

Kibo Mining holds a thermal coal deposit at Rukwa, which has a significant JORC compliant defined resource, and is developing a 250-350MW mouth-of-mine thermal power station with an established management team that includes Standard Bank as Financial Advisor.

 

Kibo also holds the Haneti Licence on which the latest technical report confirms prospectivity for nickel, PGMs, gold and strategic metals.

 

The Company also has extensive gold focused interests including Lake Victoria Goldfields and Morogoro projects. At Lake Victoria, the Company has projects with a substantial existing JORC compliant gold resource and is seeking to materially increase this resource through exploration of known extensions to existing mineralisation.

 

Kibo Mining also holds the Pinewood (coal & uranium) projects.

 

The Company's projects are located in the established and gold prolific Lake Victoria Goldfields, the emerging goldfields of eastern Tanzania and the Mtwara Corridor in southern Tanzania where the Government has prioritised infrastructural development attracting significant recent investment in coal and uranium. The Company has a positive working relationship with the Tanzanian government at local, regional and national levels and works hard to maintain positive relationships with all communities where company interests are held. The Company recognises the potential to enhance the quality of life and opportunity for Tanzanian citizens through careful development of its projects.

 

Updates on the Company's activities are regularly posted on its website www.kibomining.com  

 

 

Johannesburg

21 August 2014

Corporate and Designated Adviser:

River Group

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCPBMRTMBTTMAI
Date   Source Headline
15th Jun 20177:00 amRNSImweru Drill Programme Update
14th Jun 20177:00 amRNSMCPP Gains Momentum after Talks with Stakeholders
8th Jun 201711:00 amRNSAnnual Report and Notice of AGM
8th Jun 20178:09 amRNSKibo Monthly Q&A for Investors
2nd Jun 20179:00 amRNSNotice of AGM
2nd Jun 20178:00 amRNSLake Victoria Early Stage Licence Portfolio Update
1st Jun 20177:00 amRNSMCPP Receives Formal Reconfirmation
31st May 20177:00 amRNSUpdate on Katoro Gold PLC: Imweru Gold Project
31st May 20177:00 amRNSWork on Imweru Gold Project Commences
26th May 201711:00 amRNSFull Year Results 2016
5th May 20178:14 amRNSUpdate on Opera Reverse Take Over Transaction
20th Apr 20177:00 amRNSMCPP: MOU Mbeya Cement
12th Apr 20179:00 amRNSKibo commences monthly Q&A for investors
30th Mar 20177:00 amRNSDiversified Production Strategy for Mbeya Mine
23rd Mar 20178:00 amRNSQ1 2017 Strategic Objectives successfully met
6th Mar 20172:15 pmRNSMCPP Delivers First Classrooms
2nd Mar 201710:30 amRNSUpdate on Proposed Acquisition by Opera
1st Mar 201712:50 pmRNSNotifiable Holding Change
24th Feb 201710:00 amRNSCessation of Metal Tiger Joint Ventures
15th Feb 20179:31 amRNSMbeya Coal to Power Project Update
15th Feb 20178:45 amRNSMbeya Coal to Power Project Update
27th Jan 20177:00 amRNSChange of Share Registrar
23rd Jan 20177:00 amRNSMCPP Update: Integrated Bankable Feasibility Study
16th Jan 20177:00 amRNSMCPP: Final Approval for ESIA Scoping Reports
3rd Jan 201711:45 amRNSAnnouncement regarding TANESCO press reports
21st Dec 20162:50 pmRNSShare Issue
21st Dec 20168:47 amRNSTerm Sheet with Sanderson Capital Partners Agreed
21st Dec 20167:16 amRNSMCPP Update
19th Dec 20169:18 amRNSMCPP Update: EPC Contract Awarded to SEPCO III
9th Dec 20167:30 amRNSShare Issue
2nd Dec 20167:00 amRNSUpdate on Acquisition by Opera
30th Nov 20167:00 amRNSMCPP Update: Integrated Financial Model Completed
21st Nov 20167:00 amRNSMCPP Update: Collaboration Agreement with GE
1st Nov 20167:00 amRNSMCPP Update: Kibo Receives Final Commercial Bids
13th Oct 20167:00 amRNSAgreement of Development Costs for MCPP
27th Sep 20169:00 amRNSHalf-year Report
23rd Sep 20168:00 amRNSMCPP Update: Date Extended to Finalize Agreement
23rd Sep 20167:45 amRNSSigned Heads of Agreement with Opera Investments
22nd Sep 20167:00 amRNSMCPP Update: Financial Advisory Mandate Letter
16th Sep 20167:00 amRNSMCPP Update: MOU with GE International Inc.
8th Sep 201610:00 amRNSTransfer of Kibo Shares to Sanderson
5th Sep 20167:30 amRNSMCPP SEPCO III Agreement Update
1st Sep 20167:00 amRNSSanderson Loan Facility Repayment
25th Aug 20167:00 amRNSMCPP Update: New Agreement with SEPCO III
17th Aug 20168:00 amRNSLetter of Engagement with Norton Rose Fulbright
10th Aug 20161:00 pmRNSShare Issue
10th Aug 20167:02 amRNSDefinitive Agreement with Lake Victoria Gold Ltd
3rd Aug 20168:00 amRNSMCPP and Imweru Gold Project Interim Update
22nd Jul 20167:00 amRNSNet Smelter Royalty Agreement with Acacia
21st Jul 201612:00 pmRNSResult of AGM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.