Operational Update: Q2 2023

3 Jul 2023 07:00

RNS Number : 6478E
Kibo Energy PLC
03 July 2023
 

Kibo Energy PLC (Incorporated in Ireland)

(Registration Number: 451931)

(External registration number: 2011/007371/10)

LEI Code: 635400WTCRIZB6TVGZ23

Share code on the JSE Limited: KBO

Share code on the AIM: KIBO

ISIN: IE00B97C0C31

('Kibo' or 'the Company')

 

Dated: 03 July 2023

Kibo Energy PLC ('Kibo' or the 'Company')

Operational Update: Q2 2023

 

Kibo Energy PLC (AIM: KIBO; AltX: KBO), the renewable energy focused development company, is pleased to provide an operational update as it enters the second half of 2023. This follows its update as provided in a Company RNS dated 6 April 2023.

 

Portfolio

 

The Kibo Group strategy, as previously announced in a Company RNS dated 19 April 2021, is focused on developing, owning and operating sustainable energy solutions that can immediately and progressively address the acute energy challenges in sub-Saharan Africa, the United Kingdom and Ireland.

 

The table below indicates the status of Kibo's project portfolio at present. Timelines beyond Q3 2023 remain as advised on 6 April 2023 and the Company will advise should these change in light of the below. This does not include opportunities that are currently the subject of advanced due diligence and commercial consideration.

 

Kibo Group Project Portfolio

Entity

Kibo Equity

Strategic Domain

Projects

Development Status

Current Status

MAST Energy Developments (UK)

57.86%

Reserve Power

Pyebridge (9 MW)

Operational and generating revenue

CM T-1 contract scheduled to begin on 1 October 2023 (see MED Results for the year ended 31 December 2022 as per the MED RNS dated 28 April 2023)

Bordesley (5 MW)

Advanced project development

In construction and commissioned by Q4 2023 (see MED Results for the year ended 31 December 2022 as per the MED RNS dated 28 April 2023)

Rochdale (4.4 MW)

Advanced project development

Planning consent granted in Q2 2023 (see MED Results for the year ended 31 December 2022 as per the MED RNS dated 28 April 2023)

Hindlip Lane (7.5 MW)

Concept stage

EPC and O&M contracts under review, further updates to follow (see MED Results for the year ended 31 December 2022 as per the MED RNS dated 28 April 2023)

Stather Road (2.5 MW)

Concept stage

EPC and O&M contracts under review, further updates to follow (see MED Results for the year ended 31 December 2022 as per the MED RNS dated 28 April 2023)

Sustineri (SA)

65%

Waste to Energy

CHP project to supply base-load electricity generation in South Africa with 4 revenue streams: electricity, gate fees and potentially from heat and steam output as well as the production of synthetic oil

Phase 1 (2.7 MW + study on synthetic oil production)

Advanced project development stage - financial close ready

- Laboratory tests received and confirm oil quality standards of offtaker

- Supplier's sustainability standards assessments are currently underway

- Integration study is being undertaken to align test results with feedstock characteristics in preparation for financial close - Integrated Environmental Authorisation (EA) has been granted

Phase 2 (targeted 20 MW)

Pre-concept stage

Milestones TBD once Phase 1 has been executed

National Broadband Solutions (SA)

51%

Long Duration Energy Storage

 

12.3 MW in development

Simultaneous concept and commercial development

Status remains unchanged from last update.

36.32 MW target for development

Under assessment

Mbeya Power Project ('MPP') (TZ)

100%

Biofuel

300 MW short-term conversion to renewable energy biofuel

Original project.

 

Fully permitted with Bankable Feasibility Study completed

TANESCO due diligence on Kibo as part of the MOU programme currently underway.

UK Portfolio

100%

Waste to Energy

Southport (10 MW, 2 MW long-duration energy storage and

5.5m m3 bio-methane)

Funding constraints, notably as the results of delays caused by shareholders not being able to cast their votes, resulted in no, other than in-house project planning, work being performed

Status remains unchanged from last update.

 

All funding activities, including the Company's proposed AIM-listed vehicle Ultimate Sustainable Energy ('USE'), were placed on hold due to delays as a result of EGM difficulties where shareholders were unable to cast their votes, which was partially resolved at the most recent EGM (see RNS dated 16 March 2023).

 

Louis Coetzee, CEO of Kibo Energy, says: "We are pleased with the overall progress during the last quarter, and we look forward to updating the market during the course of Q3 on a number of exciting initiatives currently underway on both operational as well as corporate level".

 

This announcement contains inside information as stipulated under the Market Abuse Regulations (EU) no. 596/2014.

 

**ENDS**

 

For further information please visit www.kibo.energy or contact:

 

Louis Coetzee

info@kibo.energy

Kibo Energy PLC

Chief Executive Officer

James Biddle

Roland Cornish

+44 207 628 3396

Beaumont Cornish Limited

Nominated Adviser

Claire Noyce

+44 20 3764 2341

Hybridan LLP

Joint Broker

Damon Heath

+44 207 186 9952

Shard Capital Partners LLP

Joint Broker

Zainab Slemang van Rijmenant

zainab@lifacommunications.com

Lifa Communications

Investor and Media Relations Consultant

 

Johannesburg

3 July 2023

Corporate and Designated Adviser

River Group

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDSSASUEEDSEDW
Date   Source Headline
10th Nov 20148:00 amRNSCommencement of Accelerated PFS for RCPP
28th Oct 20148:00 amRNSRukwa DMFS Project Update
14th Oct 20148:00 amRNSCommencement of DFS on Imweru
10th Oct 20148:11 amRNSClarification re CEO shareholding
9th Oct 20147:00 amRNSFirst Financial Indicators for RCPP
8th Oct 20149:15 amRNSKibo Mining raises £855,725 in Share Placing
29th Sep 20148:00 amRNSRCPP Update
25th Sep 20144:00 pmRNSInterim Results
18th Sep 20148:00 amRNSRCPP Update
9th Sep 20148:00 amRNSPreliminary Evaluation confirms Mining Viability
2nd Sep 20148:30 amRNSImweru Exploration Results
21st Aug 20148:31 amRNSProgress with DFS at RCPP
31st Jul 20148:00 amRNSResult of AGM & Completion of Placing
29th Jul 20148:00 amRNSRCPP to commence DMFS
15th Jul 20144:40 pmRNSSecond Price Monitoring Extn
15th Jul 20144:35 pmRNSPrice Monitoring Extension
14th Jul 20148:30 amRNSKibo Mining Plc Share Placing
7th Jul 20149:17 amRNSPosting of 2013 Annual Report
30th Jun 20143:56 pmRNSAnnual Financial Statements & Notice of AGM
27th Jun 201412:40 pmRNSFinal Results
27th May 20149:00 amRNS1st Quarter Results
2nd Apr 20141:00 pmRNSUK Investor Show & Registered Company Address
31st Mar 20149:00 amRNSKibo Mining raises £750,000 in Share Placing
17th Mar 20148:00 amRNSTechnical Report - Haneti
24th Feb 20148:00 amRNSTechnical Report Confirms Imweru Upside Potential
14th Feb 20149:30 amRNSAppointment of Director
23rd Jan 20149:00 amRNSShareholder Update: Financial Year 2013/14
14th Jan 20147:00 amRNSPositive Phase 1 Drilling Results From Imweru
20th Dec 20137:00 amRNSDistribution of Shareholding by Major Shareholder
19th Dec 20137:00 amRNSHaneti Nickel and Imweru Gold Projects Update
13th Dec 20137:30 amRNSHaneti Exploration Project Update
5th Dec 20133:48 pmRNSKibo Re-acquires 100% interest in Haneti
4th Dec 20137:30 amRNSIMWERU GOLD PROJECT COMPLETED AHEAD OF SCHEDULE
19th Nov 20137:30 amRNSUpdate on Exploration Activities
28th Oct 20137:30 amRNSKibo Commences 3,000 metre Drill Programme
8th Oct 20137:00 amRNSManagement Team and Financial Advisor Appointed
1st Oct 20137:00 amRNSKibo Issues of Shares for Cash
30th Sep 20139:45 amRNSHalf Year Results Announcement
16th Sep 20137:00 amRNSRecent Encouraging Stream Sampling Results
11th Sep 20137:00 amRNSRaises further £500,000 in Secondary Placement
9th Sep 20137:30 amRNSHaneti Joint Venture Project Update
30th Aug 201310:52 amRNSKibo raises £1,105,000 in Share Placing
13th Aug 20137:30 amRNSKibo Announces new Consolidated Lake Victoria Gold
1st Aug 20137:00 amRNSChange in UK Broking Arrangements
31st Jul 20134:45 pmRNSRESULTS OF THE ANNUAL GENERAL MEETING
31st Jul 20137:00 amRNSHaneti Project Interim Update
18th Jul 20137:00 amRNSMOU Signed with Korean East West Power
11th Jul 20137:00 amRNSHaneti Interim Project Update
8th Jul 201310:00 amRNSAnnual Report, AGM Date and Director Resignations
1st Jul 20137:00 amRNS15 months results for the period ended 31 Dec 2012

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.