Bordersley Update

10 Dec 2019 09:00

RNS Number : 3253W
Kibo Energy PLC
10 December 2019
 

Kibo Energy PLC (Incorporated in Ireland)

(Registration Number: 451931)

(External registration number: 2011/007371/10)

Share code on the JSE Limited: KBO

Share code on the AIM: KIBO

ISIN: IE00B97C0C31

("Kibo" or "the Company")

 

Dated: 10 December 2019

Kibo Energy PLC ('Kibo' or the 'Company')

Bordersley Update

 

Kibo Energy PLC, the multi-asset, Africa focused, energy company, is pleased to announce a further update with regards to its wholly owned subsidiary, Bordersley Power Ltd ('Bordersley'), which is developing a 5 MW gas-fuelled power generation plant in the UK in cooperation with the Company's 60% owned subsidiary, and manager and operator of Bordersley, MAST Energy Developments Limited ('MED').

 

Overview

·; Good progress towards de-risking 5 MW gas-fuelled power generation plant, Bordersley, which remains on target for commercial commissioning at the end of Q1 2020

·; Several milestones achieved by the Bordersley working/steering committee, which includes MED and its joint development partner, AB Impianti S.R.L ('AB')

o Agreed site work scope

o Advanced Engineering, Procurement, and Construction ('EPC') solution

o Advanced associated financing agreement for Bordersley's construction and commissioning

·; Further payment of 10,000,000 shares to be made to Bordersley's original MED vendors (see RNS dated 26 June 2019)

 

Louis Coetzee, CEO of Kibo Energy, commented, "The MED/AB partnership is working well and making excellent headway towards hitting the end of Q1 2020 target to commission our 100% owned 5 MW gas-fuelled power generation plant at Bordersley. This progress is reflective of similar advances being made across our portfolio; we are now well positioned to bring several projects to fruition during 2020."

 

Details

Kibo continues to make progress towards de-risking its 5 MW gas-fuelled power generation plant, Bordersley, which remains on target for commercial commissioning at the end of Q1 2020. This is the first reserve power generation project being developed by MED as it focuses on building an initial portfolio of 100 MW reserve energy projects in the UK.

 

In line with this, the Bordersley working/steering committee, which includes MED and its joint development partner, AB (see RNS dated 30 October 2019), has achieved several milestones. As well as agreeing the site work scope, both the EPC solution and associated financing agreement for Bordersley's construction and commissioning are nearing completion.

 

AB is a subsidiary of the AB Group, a global leader in engineering, manufacture, and after sales service of Combined Heat and Power generation solutions, which is present in 19 countries and has installed over 1,600 MW in over 1,250 plants.

 

In light of the progress and pursuant to the agreement for Kibo to consolidate full ownership of Bordersley by acquiring all of the original MED vendors, St' Anderton on Vaal Limited ('St' Anderton'), direct and indirect interests in Bordersley (see RNS dated 26 June 2019), the Company will now make a further payment of 10,000,000 shares in Kibo to St' Anderton, at a deemed issue price of 5.25 pence per share.

 

Accordingly, application will be made for the 10,000,000 shares to be admitted to trading on AIM and the JSE AltX markets. Trading in these shares is expected to commence on AIM and the JSE on or around 19 December 2019 ('Admission'). Following Admission, the Company will have 1,257,276,078 shares in issue. The foregoing figure may be used by shareholders as the denominator for the calculations to determine if they are required to notify their interest in, or a change to their interest in, the Company under the FCA's Disclosure Guidance and Transparency Rules.

 

**ENDS**

 

For further information please visit www.kibo.energy or contact:

 

Louis Coetzee

info@kibo.energy

Kibo Energy PLC

Chief Executive Officer

Andreas Lianos

+27 (0) 83 4408365

River Group

Corporate and Designated

Adviser on JSE

Jason Robertson

+44 (0) 20 7374 2212

First Equity Limited

Joint Broker

Philip Adler

+44 (0) 20 7392 1494

ETX Capital Limited

Joint Broker

Bhavesh Patel / Stephen Allen

+44 20 3440 6800

RFC Ambrian Limited

NOMAD on AIM

Isabel de Salis /

Beth Melluish

+44 (0) 20 7236 1177

St Brides Partners Ltd

Investor and Media Relations Adviser

 

Notes

Kibo Energy PLC is a multi-asset, Africa focused, energy company positioned to address the acute power deficit, which is one of the primary impediments to economic development in Sub-Saharan Africa. To this end, it is the Company's objective to become a leading independent power producer in the region.

 

Kibo is simultaneously developing three similar coal-fuelled power projects: the Mbeya Coal to Power Project ('MCPP') in Tanzania; the Mabesekwa Coal Independent Power Project ('MCIPP') in Botswana; and the Benga Independent Power Project ('BIPP') in Mozambique. By developing these projects in parallel, the Company intends to leverage considerable economies of scale and timing in respect of strategic partnerships, procurement, equipment, human capital, execution capability / capacity and project finance.

 

Additionally, the Company has a 60% interest in MAST Energy Developments Limited ('MED'), a private UK registered company targeting the development and operation of flexible power plants to service the UK Reserve Power generation market.

 

Johannesburg

10 December 2019

Corporate and Designated Adviser

River Group

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDFFASWSFUSESE
Date   Source Headline
15th Jun 20177:00 amRNSImweru Drill Programme Update
14th Jun 20177:00 amRNSMCPP Gains Momentum after Talks with Stakeholders
8th Jun 201711:00 amRNSAnnual Report and Notice of AGM
8th Jun 20178:09 amRNSKibo Monthly Q&A for Investors
2nd Jun 20179:00 amRNSNotice of AGM
2nd Jun 20178:00 amRNSLake Victoria Early Stage Licence Portfolio Update
1st Jun 20177:00 amRNSMCPP Receives Formal Reconfirmation
31st May 20177:00 amRNSUpdate on Katoro Gold PLC: Imweru Gold Project
31st May 20177:00 amRNSWork on Imweru Gold Project Commences
26th May 201711:00 amRNSFull Year Results 2016
5th May 20178:14 amRNSUpdate on Opera Reverse Take Over Transaction
20th Apr 20177:00 amRNSMCPP: MOU Mbeya Cement
12th Apr 20179:00 amRNSKibo commences monthly Q&A for investors
30th Mar 20177:00 amRNSDiversified Production Strategy for Mbeya Mine
23rd Mar 20178:00 amRNSQ1 2017 Strategic Objectives successfully met
6th Mar 20172:15 pmRNSMCPP Delivers First Classrooms
2nd Mar 201710:30 amRNSUpdate on Proposed Acquisition by Opera
1st Mar 201712:50 pmRNSNotifiable Holding Change
24th Feb 201710:00 amRNSCessation of Metal Tiger Joint Ventures
15th Feb 20179:31 amRNSMbeya Coal to Power Project Update
15th Feb 20178:45 amRNSMbeya Coal to Power Project Update
27th Jan 20177:00 amRNSChange of Share Registrar
23rd Jan 20177:00 amRNSMCPP Update: Integrated Bankable Feasibility Study
16th Jan 20177:00 amRNSMCPP: Final Approval for ESIA Scoping Reports
3rd Jan 201711:45 amRNSAnnouncement regarding TANESCO press reports
21st Dec 20162:50 pmRNSShare Issue
21st Dec 20168:47 amRNSTerm Sheet with Sanderson Capital Partners Agreed
21st Dec 20167:16 amRNSMCPP Update
19th Dec 20169:18 amRNSMCPP Update: EPC Contract Awarded to SEPCO III
9th Dec 20167:30 amRNSShare Issue
2nd Dec 20167:00 amRNSUpdate on Acquisition by Opera
30th Nov 20167:00 amRNSMCPP Update: Integrated Financial Model Completed
21st Nov 20167:00 amRNSMCPP Update: Collaboration Agreement with GE
1st Nov 20167:00 amRNSMCPP Update: Kibo Receives Final Commercial Bids
13th Oct 20167:00 amRNSAgreement of Development Costs for MCPP
27th Sep 20169:00 amRNSHalf-year Report
23rd Sep 20168:00 amRNSMCPP Update: Date Extended to Finalize Agreement
23rd Sep 20167:45 amRNSSigned Heads of Agreement with Opera Investments
22nd Sep 20167:00 amRNSMCPP Update: Financial Advisory Mandate Letter
16th Sep 20167:00 amRNSMCPP Update: MOU with GE International Inc.
8th Sep 201610:00 amRNSTransfer of Kibo Shares to Sanderson
5th Sep 20167:30 amRNSMCPP SEPCO III Agreement Update
1st Sep 20167:00 amRNSSanderson Loan Facility Repayment
25th Aug 20167:00 amRNSMCPP Update: New Agreement with SEPCO III
17th Aug 20168:00 amRNSLetter of Engagement with Norton Rose Fulbright
10th Aug 20161:00 pmRNSShare Issue
10th Aug 20167:02 amRNSDefinitive Agreement with Lake Victoria Gold Ltd
3rd Aug 20168:00 amRNSMCPP and Imweru Gold Project Interim Update
22nd Jul 20167:00 amRNSNet Smelter Royalty Agreement with Acacia
21st Jul 201612:00 pmRNSResult of AGM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.