Production and Financing Update

2 Jan 2014 07:00

RNS Number : 6911W
Jubilee Platinum PLC
02 January 2014
 

 

Registration number (4459850)

AltX share code: JBL

AIM share code: JLP

ISIN: GB0031852162

 

Not for release, publication or distribution in whole or in part in, into or from any jurisdiction where to do so would constitute a violation of the relevant laws or regulations of such jurisdiction.

 

2 January 2014

 

Jubilee Platinum PLC

("Jubilee" or the "Company" or the "Group")

 

Jubilee Middelburg Smelters Achieve New Record Production Rate

 And

Jubilee secures an Equity Financing Facility in Support of Targeted Acquisitions

 

Update on Middelburg Smelter

Jubilee, the AIM and AltX quoted Mine-to-Metals specialist, is pleased to announce that the Middelburg Smelter operation has achieved a new record production rate - more than 35 tons of Ferronickel metal within a single 24-hour shift - exceeding the previous record of 26 tons of metal.

This achievement comes following the Company's recent announcement (dated 23 December 2013) that it had secured funding for the final phase of the smelter renewable program, which includes the expansion of the Middelburg Smelter operation to three operating ARC furnaces.

 

Two of these furnaces will be dedicated to the production of ferronickel metal and the third furnace to the production of ferrosilicon metal, thereby increasing the total targeted smelter design capacity to 13,900 tons of metal per annum. All three furnaces have been fully contracted.

With proceeds in place to fund the commissioning of the remaining 3rd ARC furnace at Middelburg, the Board of Jubilee believes that the Middelburg Smelter is in a strong position to enhance its earnings profile.

 

Equity Financing Facility

With a view to expanding its access to platinum containing material, Jubilee is also pleased to announce that the Company has entered into a £10 million Equity Finance Facility ("EFF") with Darwin Strategic Limited ("Darwin"). The EFF can be utilised by the Company, at its sole discretion, over a commitment period of 60 months.

The EFF has been secured by Jubilee in support of its Mine-to-Metals strategy and more specifically towards potential acquisitions targeted by the Company in the platinum and other metals industry with a view to further utilizing the ConRoast process. The EFF will replace the current equity based funding structure held by Jubilee.

EFF Rationale:

Provides Jubilee with a flexible, highly cost efficient source of capital

Allows Jubilee to minimise dilution and maximise value for shareholders when issuing equity

The facility is available should the Company wish to capitalise on further opportunities within the Platinum Sector

Leon Coetzer CEO of Jubilee commented: "We are pleased with the continued improved performance of our Middelburg Smelter operation. This performance, thanks in large measure to the dedication of our production team, illustrates the success of our two-year smelter renewable program. 

 

"We will continue to engage with companies holding platinum-bearing assets near or at surface to grow Jubilee's access to these materials. The EFF funding structure offers the Company the support to access funding when pursuing companies holding such assets."

 

Principal Key Terms of the EFF include:

The EFF agreement with Darwin provides Jubilee with a facility of up to £10 million which (subject to certain limited restrictions) can be drawn down at any time over the next five years. The timing and floor subscription price of any draw down is always at the complete control and sole discretion of the Company. There are no penalty fees payable for not using the facility.

Jubilee is under no obligation to make a draw down and may make drawdowns at its discretion, up to the total value of the EFF, by way of issuing subscription notices to Darwin. Following delivery of a subscription notice, Darwin will subscribe and the Group will allot and issue to Darwin new ordinary shares in Jubilee ('Ordinary Shares').

The subscription price for any Ordinary Shares to be subscribed by Darwin will be set with reference to the average of the three lowest Closing Bid Prices in the period following the issue of the subscription notice.

Jubilee is able to specify in each subscription notice a minimum price below which Ordinary Shares will not be issued to Darwin. The Company will have the right (with the consent of Darwin) to modify that minimum price at any time during the relevant Pricing Period.

The number of Ordinary Shares which may be issued under any individual subscription notice may be up to the lower of 25 per cent of the Group's issued share capital following completion of the relevant subscription, or four times the average daily trading volume of Jubilee's Ordinary Shares over the 15 trading days preceding the issue of the relevant subscription notice. This may be reduced in certain circumstances, including where the minimum price is not maintained.

The maximum amount of an individual subscription notice may not exceed £500,000 without Darwin's permission. Darwin is entitled to a commission of up to 5 per cent of amounts subscribed but may agree with Jubilee in lieu thereof for the subscription price for the Ordinary Shares to be discounted by 5 per cent.

There is also an over-allotment facility available to Jubilee, under which the Company may authorise Darwin, at Darwin's discretion, to increase the amount of the draw down by up to the aggregate undrawn amount under the EFF.

Darwin and Jubilee may mutually agree at the end of the pricing period to a variation of subscription price. This may allow for a larger subscription via any over-allotment facility authorised by the Group.

The issuance of a Subscription Notice is conditional upon the satisfaction of certain Subscription Notice Conditions which have been agreed between Darwin and Jubilee. Any subscription notice which Jubilee may issue will only be valid to the extent that it has the requisite shareholder authority to issue the maximum number of Ordinary Shares that Darwin may be required to subscribe under the relevant subscription notice.

Darwin and Jubilee may terminate the EFF agreement if certain conditions are not met.

 

Contacts

 

Jubilee Platinum plc

Colin Bird

Tel +44 (0) 20 7584 2155

Leon Coetzer

Tel +27 (0)11 465 1913

Andrew Sarosi

Tel +44 (0) 1752 221937

 

JSE Sponsor

Sasfin Capital, a division of Sasfin Bank Limited

Angela Teeling-Smith/Sharon Owens

Tel +27 (0) 11 809 7500

 

NOMAD

finnCap Ltd

Matthew Robinson/Ben Thompson - corporate finance

Joanna Weaving - corporate broking

Tel +44 (0) 20 7220 0500

 

Darwin Strategic

Anand Sambasivan / Jamie Vickers

Tel: +44 (0) 207 491 6512

 

 

Bishopsgate Communications Ltd

Nick Rome/Anna Michniewicz

Tel +44 (0) 20 7562 3350

 

Notes to Editors

Jubilee Platinum

Jubilee Platinum is focused on growing its earnings profile with a view to developing its Mine-to-Metals strategy.

As such, the Company is focused on leveraging off the ConRoast process with a view to securing access to both platinum-containing chrome rich materials that are at or near surface as well as platinum-bearing waste materials at surface. The ConRoast process remains key to unlocking near-term value and the Company is continually evaluating opportunities that will consolidate its unique application in the industry.

In June 2011, Jubilee commissioned a smelter infrastructure renewable program to both replace out-dated smelter processes and turn its wholly owned subsidiary, Jubilee Smelting and Refining ("JSR"), into a positive earnings company.

 

The renewable program consists of four phases:-

 

• Phase 1 - Install and commission a new 5MVA continuous ARC furnace (completed);

• Phase 2 - Upgrade and expand the metal granulation facility (completed);

• Phase 3 - Upgrade the existing 2.2 MVA ARC furnace and supporting off-gas systems (completed); and

• Phase 4 - Upgrade the existing 2.6 MVA ARC furnace and supporting off-gas systems (work in progress)

 

To date, Phases 1 to 3 have been implemented and achieved their stated targets. JSR has consistently achieved increased revenues with improved gross profit margins through each phase of the program.

 

The final phase 4 of the renewable program will extend the production output of the Smelter operation to an estimated 13,900 tons of metal per annum. This production increase and infrastructure renewal ensures that the Smelter operation is able to achieve sustained positive earnings with the support of the new toll smelting contracts. At the conclusion of phase 4, the Smelter operation will have established itself as a premier smelter of waste material to produce ferrometals based on its patented ConRoast and reductive smelter technologies.

 

In addition, Jubilee owns 63% of the Tjate Platinum project in the eastern limb of the Bushveld Complex, a project which is independently judged to contain the world's largest undeveloped defined block of platinum ore. The property covers 5,140 hectares on three farms and the area has been independently appraised to contain a potential net 70 million ounces of platinum group metals ("PGMs") and gold. This represents the resource targeted by future exploratory and feasibility drilling.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUAUARSWAARUR
Date   Source Headline
29th May 20267:00 amRNSNotice of General Meeting
28th May 20262:10 pmRNSStrategic Investment to Support Copper Growth
6th May 20267:00 amRNSOperational and Production Update 9m FY2026
29th Apr 20267:00 amRNSCapital Reduction Court Approval
20th Apr 20264:05 pmRNSHolding(s) in Company
8th Apr 20262:57 pmRNSResults of GM & Proposed Capital Reduction
31st Mar 20267:01 amRNSImplementation of Mine Plan at Molefe
31st Mar 20267:00 amRNSFinancial report for 6 months to end-December 2025
25th Mar 20267:05 amRNSMolefe Mine Phase 1 Drilling Results
24th Mar 20267:00 amRNSMolefe Mine Phase 1 Drilling Results delayed
23rd Mar 202610:05 amRNSReduction of Share Premium Account & Notice of GM
23rd Mar 20267:00 amRNSReduction of Share Premium Account & Notice of GM
12th Mar 20267:00 amRNSHigh-Grade Feed Secured & Large Waste Rock Update
12th Mar 20267:00 amRNSHigh-Grade Feed Secured & Large Waste Rock Update
27th Feb 20267:00 amRNSShareholder update and Dealing in securities
19th Feb 20267:00 amRNSOperational and Projects update H1 FY2026
23rd Jan 20267:00 amRNSChanges to the Board
14th Jan 20262:19 pmRNSResults of Annual General Meeting
6th Jan 20267:00 amRNSReceipt of US$10 million in funds from SA sale
2nd Jan 20267:00 amRNSClosing of Sale of South African Operations
2nd Jan 20267:00 amRNSClosing of Sale of South African Operations
17th Dec 20257:00 amRNSAudited Results for FY2025 & Notice of AGM
28th Nov 20257:00 amRNSMolefe Mine Co-Operation and Development Agreement
21st Nov 20257:00 amRNSOperational Update Zambia Q1 FY2026
17th Nov 20257:00 amRNSCompetition Tribunal Approval
17th Oct 20257:00 amRNSOperational Update South Africa Q1 FY2026
6th Oct 20256:06 pmRNSTR-1: notification of major holdings
6th Oct 20257:00 amRNSZambia Copper Strategy and SA Disposal Update
8th Sep 20257:00 amRNSDealing in securities
28th Aug 20252:05 pmRNSResults of General Meeting
12th Aug 20257:00 amRNSPosting of Circular & Notice of General Meeting
6th Aug 20257:00 amRNSZambia Copper and SA Business Proposed Sale Update
21st Jul 20257:00 amRNSQ4 Operational Update - South Africa
10th Jul 20257:00 amRNSChange of Broker and Proposed Disposal Update
19th Jun 20257:00 amRNSDirectorate Change
5th Jun 20257:00 amRNSProposed Disposal of Chrome and PGM Operations
28th May 20257:02 amRNSZambia Projects Update & Issue of equity
30th Apr 20257:40 amRNSZambia Progress Update
16th Apr 20257:00 amRNSOperational Update Q3 FY2025
14th Apr 20257:00 amRNSDirectorate Change
9th Apr 20257:00 amRNSTransaction on Surplus PGM Feed Material
3rd Apr 20257:00 amRNSJubilee Transaction on Large Waste Project
31st Mar 20257:00 amRNSInterim Financial Report 6 Months to December 2024
14th Feb 20257:00 amRNSRoan Commences High Grade Copper Production
6th Feb 20257:00 amRNSZambia Projects Update
21st Jan 20257:00 amRNSAdditional power supply secured for Roan re-start
13th Jan 20257:00 amRNSOperational Update H1 FY2025
24th Dec 20247:00 amRNSHolding(s) in Company
16th Dec 20247:00 amRNSZambia Operations Update and Exercise of Options
21st Nov 20247:00 amRNSTR-1: notification of major holdings

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.