Chrome Operations Update

13 Aug 2020 07:00

RNS Number : 9824V
Jubilee Metals Group PLC
13 August 2020
 

Jubilee Metals Group PLC

Registration number (4459850)

Altx share code: JBL

AIM share code: JLP

ISIN: GB0031852162

("Jubilee" or "the Company" or "the Group")

 

 

Dissemination of a Regulatory Announcement that contains inside information according to REGULATION (EU) No 596/2014 (MAR). Not for release, publication or distribution in whole or in part in, into or from any jurisdiction where to do so would constitute a violation of the relevant laws or regulations of such jurisdiction.

 

Jubilee's Chrome Processing Capacity at Windsor Fully Committed and

Acquisition of Rights to new Chrome Processing Facility

 

 

Jubilee Metals Group ("Jubilee" or the "Company"), the AIM and Altx traded metals processing company, is pleased to announce that it has entered into a third party Run-Of-Mine ("ROM") chrome ore offtake agreement that fully commits its Windsor chrome beneficiation plant ("Windsor") for the next three years (the "Offtake Agreement"), with an option for this to be extended further.

 

Under the terms of the Offtake Agreement, Jubilee commits to the production of 40 000 tonnes per month of chrome concentrate or, subject to the chrome content in the ROM, saleable chrome concentrate, while also retaining the rights to all discard material including the contained PGMs.

 

In addition, Jubilee has also successfully entered into a joint venture agreement ("JV Agreement") with a privately held South African company ("JV Partner") to secure the rights to a further 35 000 tonnes per month chrome processing capacity ("Windsor 8"). Under the JV Agreement Jubilee will assume operational control of the Windsor 8 facility (the 'Facility") while also committing to upgrade it by incorporating Jubilee's processing solutions.

 

Highlights

· Jubilee secures third party ROM Offtake Agreement for Windsor targeting the production of 40 000 tonnes per month of chrome concentrate for the next three years

· The Offtake Agreement secures supply of quality feed to Windsor and supports 100% operating capacity for the next three years, while continuing to further supplement the existing PGM feed material to Jubilee's PGM plants

· Jubilee has locked in a chrome sale price for the chrome production under the Offtake Agreement to secure a firm chrome earnings margin in addition to the earnings generated by the recovery of PGMs from the chrome discard

· Jubilee also executes a JV Agreement to secure Windsor 8, being the rights to an additional 35 000 tonnes per month chrome processing capacity at the Facility

· The Facility is strategically located to provide Jubilee with more opportunities to secure further third party ROM supply and associated PGM material

· Commencement of production at Windsor 8 is targeted by end September 2020

 

Leon Coetzer, CEO of Jubilee, commented: "Jubilee continues to aggressively drive its expansion across both its South African and Zambian operations. Our significant progress in Zambia, as announced last week, is followed by the successful implementation of these two key agreements supporting the expansion of our South African chrome and PGM operations. These agreements have been secured on the back of Jubilee's track record of continuously driving to set new industry standards.

 

"The Offtake Agreement, which supports Windsor's capacity to produce 40 000 tonnes per month of chrome concentrate, secures not only a constant feed source for Windsor under a protected operational margin, but also significantly increases Jubilee's surface PGM resources from the discard of the chrome operations. The successful completion of the Offtake Agreement is credit to the Jubilee team's ability to consistently achieve exceptional chrome recovery efficiencies well above the norm in the industry.

 

"With Windsor fully committed to working at full capacity, Jubilee has also successfully secured Windsor 8 under a JV Agreement, being the rights to a further 35 000 tonnes per month of chrome processing capacity. The new Facility and JV partner were carefully selected to establish a presence in a strategic location which will provide Jubilee with further opportunities to increase our chrome ore supply."

 

Key Terms of the Agreements

Under the terms of the Offtake Agreement, Windsor will receive a minimum guaranteed ROM supply targeting the production of 40 000 tonnes per month of chrome concentrate, linking to the chrome content of the ROM. The Offtake Agreement secures both a committed feed of material to Windsor as well as the continued production of upgraded PGM discard material for further processing at Jubilee's PGM recovery plants.

On the back of this Offtake Agreement Jubilee has also successfully entered into the Joint Venture Agreement with its JV Partner to secure the rights to a further 35 000 tonnes per month chrome processing capacity (being Windsor 8). Under the JV Agreement Jubilee will assume operational control of the Facility while also committing to upgrade the Facility by incorporating Jubilee's processing solutions. The Facility is strategically located to expand Jubilee's reach providing it with more opportunities to secure further third party chrome material supplies.

Jubilee has locked in the forward sale price of the produced chrome concentrate at its Windsor operation to hedge the Company against a volatile chrome price driven mainly by uncertainty in the current supply and demand fundamentals of the metal. The fixed forward sale price secures a firm earnings margin for Windsor while allowing Windsor 8 to take advantage of any short-term price fluctuations. The earnings margin of Windsor is strongly influenced by the efficiencies achieved by Windsor and excludes the added benefit of the recovered PGM ounces from the discard. Windsor is budgeted to operate at a chrome alone margin ranging between a minimum of 14% to a maximum of 25% per tonne of chrome concentrate with the additional PGM margin secured for Jubilee's PGM operations.

Under the terms of the JV Agreement, Jubilee and its JV Partner formed an unincorporated joint venture ("Joint Venture") with Jubilee holding the rights to 70% of all earnings generated by the Joint Venture. Jubilee may at any time during the next five years elect to incorporate the Joint Venture under a new subsidiary. All capital plus interest invested into the Joint Venture by Jubilee shall first be repaid prior to any distribution of earnings from the Joint Venture. Jubilee has committed to invest an estimated ZAR 10 million (GBP 440 000) towards the upgrade of Windsor 8. Jubilee is further appointed as the manager of the Joint Venture and the operator of Windsor 8, currently owned by the JV Partner. Windsor 8 benefits from the shared services offered by Windsor to dilute its overhead and position itself as one of the lowest cost, third party chrome beneficiation facilities. The PGM containing discard from Windsor 8 will be acquired by Jubilee under an existing agreement with the JV Partner.

 

 

 

United Kingdom

13 August 2020

**ENDS**

For further information visit www.jubileemetalsgroup.com or contact:

Jubilee Metals Group PLC

Colin Bird/Leon CoetzerTel +44 (0) 20 7584 2155 / Tel +27 (0) 11 465 1913

Nominated Adviser - SPARK Advisory Partners LimitedAndrew Emmott/James KeeshanTel: +44 (0) 20 3368 3555

Broker - Shard Capital Partners LLPDamon Heath/Erik WoolgarTel +44 (0) 20 7186 9900

Joint Broker - WHIreland

Harry Ansell/Katy Mitchell 

Tel: +44 (0) 20 7220 1670/+44 (0) 113 394 6618

 

JSE Sponsor - Sasfin Capital (a member of the Sasfin group)

Sharon OwensTel +27 (0) 11 809 7500

 

PR & IR Adviser - St Brides Partners Limited

Catherine Leftley/Beth Melluish

Tel +44 (0) 20 7236 1177

 

 

 

 

 

 

 

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDFFFSITIIFLII
Date   Source Headline
21st Nov 20247:00 amRNSTR-1: notification of major holdings
20th Nov 20243:15 pmRNSExercise of Warrants
12th Nov 20242:20 pmRNSResult of AGM
7th Nov 20247:00 amRNSOperational Update Q1 FY2025
6th Nov 20242:30 pmRNSTR-1: Notification of major holdings
5th Nov 20247:00 amRNSAppointment of Remuneration Committee Chairperson
31st Oct 20247:00 amRNSBoard changes
16th Oct 20247:00 amRNSIntegrated Annual Report FY2024 & Notice of AGM
7th Oct 20247:00 amRNSNotice of Full Year Results Investor Presentation
7th Oct 20247:00 amRNSProject G Acquisition and Power Update
3rd Oct 20247:00 amRNSAudited Results for the year ended 30 June 2024
23rd Sep 20247:00 amRNSCopper Projects Update
19th Sep 20247:00 amRNSManagement changes
27th Aug 20247:00 amRNSPrivate Power Purchase Agreement in Zambia
21st Aug 20247:00 amRNSOperational Update Q4 FY2024
13th Aug 20247:00 amRNSRoan Front-End Module’s First Copper Concentrate
8th Aug 20247:30 amRNSRoan Upgrade Project Commences Operations
24th Jul 20241:00 pmRNSDirector/PDMR Shareholding
23rd Jul 20247:00 amRNSDirector/PDMR Shareholding
15th Jul 20247:00 amRNSChange of Broker
24th Jun 20247:00 amRNSRoll-out of Integrated Copper Strategy in Zambia
10th Jun 20242:10 pmRNSTR-1: Notification of major holdings
3rd Jun 20248:00 amRNSExercise of Warrants and Options
23rd Apr 20247:00 amRNSAppointment of Joint Corporate Broker
18th Apr 20247:00 amRNSOperational Update Q3 FY2024
28th Mar 20247:00 amRNSProjects Update
6th Mar 20243:00 pmRNSExercise of Options
6th Mar 20247:00 amRNSChanges to the Board & New Dedicated Exec Boards
29th Feb 20247:00 amRNSInterim Results 2023 Presentation
28th Feb 20249:31 amRNSInterim Results 2023 Presentation Re-scheduled
26th Feb 20247:00 amRNSInterim Financial Report 6 months to December 2023
8th Feb 20247:00 amRNSZambia Copper Expansion Update
23rd Jan 20247:00 amRNSOperational and Projects Update Q2 FY2024
4th Jan 20243:00 pmRNSTR-1: Notification of major holdings
3rd Jan 202412:00 pmRNSResults of General Meeting
15th Dec 20231:53 pmRNSResults of Placing and Notice of General Meeting
15th Dec 20237:00 amRNSProposed Placing
13th Dec 20232:30 pmRNSReply to Shareholder Correspondence Regarding a GM
12th Dec 20237:00 amRNSInvestment in Historical Waste Rock Dump in Zambia
21st Nov 20233:30 pmRNSInvestor Webcast
17th Nov 20237:00 amRNSNew Corporate Presentation
3rd Nov 20231:30 pmRNSResult of AGM
1st Nov 20237:05 amRNSQ1 Operational Report to 30 September 2023
17th Oct 20237:00 amRNSAward of New Slag Project with Mopani Copper Mines
11th Oct 20237:00 amRNSFinal Results and Notice of AGM
5th Oct 20237:00 amRNSNotice of Results
21st Aug 20237:00 amRNSSouth Africa and Zambia Project Expansion Update
14th Aug 20237:00 amRNSAppointment of CFO and Head of Energy Metals
20th Jul 20237:00 amRNSOperational Update for full year to 30 June 2023
6th Jun 20237:00 amRNSEXPANSION OF CHROME AND PGM FOOTPRINT

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.