Russian Project Update

3 Feb 2011 07:00

RNS Number : 5929A
JKX Oil & Gas PLC
03 February 2011
 



 

 

6 Cavendish Square, London W1G 0PD, England, UK

Tel: +44 (0)20 7323 4464 Fax: +44 (0)20 7323 5258

Web site: http://www.jkx.co.uk

 

 03 February 2011

 

JKX Oil & Gas plc ("JKX")

Announces

RUSSIAN PROJECT UPDATE

 

 

JKX is pleased to provide a status update of the redevelopment of the Koshekhablskoye field in southern Russia.

 

Gas Processing Facility & First Gas

Fabrication of the key components of the GPF plant in Sharjah was completed during the last quarter of 2010 with the final shipment leaving port at the end of December, slightly ahead of schedule. All equipment has now been off-loaded and cleared through customs in the Russian port of Novorossiysk, some 300km from the field. Trucking to site commenced in early January, with final deliveries scheduled for the end of this week. Foundations for the equipment are in place and the construction teams have begun installation. Installation and construction of locally sourced equipment and buildings is nearing completion with hook-up and commissioning of the plant scheduled to commence by the end of the first quarter. First commercial gas production remains on target for mid-year.

 

Flowlines and Export Lines

Installation and testing of all flowlines, together with control and injection lines, has been completed. The twin export lines have been installed tested and tied-in to the Gazprom trunk line and are awaiting connection to the manifolds at the GPF.

 

Well Recompletions

Development Wells 20 and 27 have been successfully completed and tested in the Oxfordian limestone reservoir and are suspended ready for production. Together they have a potential delivery capacity of 30 MMcfd.

 

Development Well 25 on the north flank of the field has been re-entered using the Geostream KES-536 rig, and the remainder of the tubing recovered. Drilling of the 260m sidetrack into the limestone reservoir will kick-off this week at 5,490m with a targeted TD of 5,700m. Completion and testing of Well 25 is scheduled for the end of the first quarter.

 

Development Well 15, deep on the east flank of the field, was sidetracked to a depth of 5,755m with strong gas shows and encouraging logs. Disappointingly, the sidetracked well bore did not stay open during testing with an obstruction preventing deployment of the coiled tubing to TD in the open hole section. Due to the priority given to the other wells in the remainder of the first phase, remedial action, which may include a new sidetrack, would be undertaken as part of the second phase of well recompletions later in 2012.

.

Tubing has now been recovered from the Callovian appraisal Well 09 to a depth of 5,312m using the Kremco-900 rig. Preparations are currently underway to sidetrack the well through the Callovian sandstone reservoirs to a TD of 5,500m. Completion and testing of Well 09 is now scheduled for the second quarter of the year.

 

A smaller A-125 rig has been used to prepare exploration Well 22 for deepening. The well has been suspended at 4,885m awaiting mobilisation of the Geostream KES-536 rig to deepen the well to the Callovian sandstone reservoirs with a TD of 5,570m. Completion and testing of Well 22 is scheduled for the third quarter of the year.

 

 

JKX Chief Executive, Dr Paul Davies, said: "We are very pleased with the progress made on the Koshekhablskoye field in Russia, which is on track to commence gas production by the end of H1 at the plant design capacity of 40 MMcfd. This keeps us on track to achieve the Group's overall near term production objective of 20,000 boepd."

 

For further information please contact:

Catherine Maitland/ Alexandra Stoneham: Cardew Group 020 7930 0777

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCEAXAAEFSFEFF
Date   Source Headline
31st Jul 20137:00 amRNSProgress Report on R-103 Frac in Ukraine
29th Jul 20137:00 amRNSHalf Yearly Report
18th Jul 20137:00 amRNSSuccessful Recompletion of NN-71 Well in Ukraine
12th Jul 20137:00 amRNSBonds Admission to the Luxembourg Stock Exchange
8th Jul 20137:00 amRNSProduction Update and Notice of Results
2nd Jul 20137:00 amRNSCommencement of Ukraine Frac Operations
12th Jun 20138:00 amRNSLetter to shareholders
5th Jun 20132:23 pmRNSResult of AGM
5th Jun 201311:30 amRNSAGM Trading Statement
5th Jun 20137:00 amRNSAGM Update
31st May 201311:24 amRNSAGM Update
30th May 20137:00 amRNSUkrainian Well Sidetrack Exceeds Expectations
29th May 20137:00 amRNSLetter to shareholders
16th May 20137:00 amRNSInterim Management Statement
9th May 20131:40 pmRNSDirector/PDMR Shareholding
9th May 20131:40 pmRNSDirector/PDMR Shareholding
9th May 20131:40 pmRNSDirector/PDMR Shareholding
9th May 20131:40 pmRNSDirector/PDMR Shareholding
9th May 20131:40 pmRNSDirector/PDMR Shareholding
9th May 20131:40 pmRNSDirector/PDMR Shareholding
9th May 20131:40 pmRNSDirector/PDMR Shareholding
9th May 20131:40 pmRNSDirector/PDMR Shareholding
26th Apr 201312:17 pmRNSDirector/PDMR Shareholding
26th Apr 201312:16 pmRNSDirector/PDMR Shareholding
26th Apr 201312:16 pmRNSDirector/PDMR Shareholding
24th Apr 20137:00 amRNSNotice of AGM
22nd Apr 20133:00 pmRNSHolding(s) in Company
22nd Apr 20132:49 pmRNSHolding(s) in Company
18th Apr 20139:00 amRNSAnnual Report & AGM
9th Apr 20137:00 amRNSFinal Results
2nd Apr 201310:14 amRNSKoshekhablskoye Update
22nd Mar 20133:12 pmRNSHolding(s) in Company
18th Mar 201312:13 pmRNSEclairs Group
15th Mar 20134:42 pmRNSSecond Price Monitoring Extn
15th Mar 20134:37 pmRNSPrice Monitoring Extension
8th Mar 20135:30 pmRNSHolding(s) in Company
8th Mar 20132:28 pmRNSHolding(s) in Company
28th Feb 20137:01 amRNSNotice of Results
19th Feb 20134:12 pmRNSIssue of Convertible Bonds
15th Feb 20137:00 amRNSZaplavskoye Licence Update
13th Feb 20137:00 amRNSUkraine LPG Plant Upgrade
13th Feb 20137:00 amRNSResult of Firm Placing and Open Offer
12th Feb 20137:00 amRNSRudenkovskoye Multi-Stage Frac Update
11th Feb 20137:00 amRNSElizavetovskoye Reserves Upgrade
7th Feb 20137:00 amRNSKoshekhablskoye Acidisation Programme
6th Feb 20134:30 pmRNSHolding(s) in Company
5th Feb 20137:00 amRNSUkrainian Rig Remobilisation
28th Jan 20136:00 pmRNSUpdate to Timetable
28th Jan 20137:00 amRNSSUCCESSFUL PLACING OF US$40M CONVERTIBLE BOND
25th Jan 20131:30 pmRNSOFFERING OF CONVERTIBLE BONDS

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.