Quicklime Project Update

5 Nov 2024 07:00

RNS Number : 8706K
Firering Strategic Minerals PLC
05 November 2024
 

Firering Strategic Minerals plc / EPIC: FRG / Market: AIM / Sector: Mining

 

5 November 2024

Firering Strategic Minerals plc

("Firering" or "the Company")

 

Quicklime Operational Update

 

The first gasifier's arrival marks a major milestone in Limeco's plant renovation

 

Firering Strategic Minerals plc, an emerging quicklime production and critical mineral exploration company, is pleased to announce an operational update with regards to its quicklime project in Zambia ("Limeco"), which is being fast-tracked towards the start of phased commissioning in Q4 2024.

 

HIGHLIGHTS

· Key modifications to the first of eight kilns are nearly complete, which will significantly improve operational efficiency and lower the plant's operating costs.

· Aggregate crushing operation continues to perform well, supporting positive cash flow.

· Positioned to commence production immediately on commissioning of Kiln 1 in Q4 2024 with kiln stockpile now standing at +15,000 tonnes.

· Newly built pilot kiln performing effectively, with promising burn test results.

· Positive off-take discussions progressing well, driven by Limeco's strong production capacity and commitment to quality control, attracting notable market interest.

· Updated JORC-compliant Mineral Resource Estimate anticipated in November 2024.

 

Yuval Cohen, Chief Executive of Firering, said: "We are delighted by the rapid progress at Limeco, including the installation works for the first gasifier, which marks a key milestone in the plant renovation strategy. Modifications to the first kiln are nearly complete, with commissioning of both the kiln and gasifier targeted for Q4 2024. Laboratory test work has also accelerated, supported by the completion of a pilot kiln, which has yielded initial quicklime (CaO) results between 92% and 94%. This progress is driving productive discussions with prospective clients, and accordingly we are optimistic about securing long-term offtake agreements.

 

"The upcoming two months promise to be extremely busy as we work toward the production start target, with a steady stream of news expected. This includes the release of an updated Mineral Resource Estimate as Limeco positions itself to meet the rising demand from Zambia's growing copper production market."

 

DETAILS

Limeco's quicklime project remains on track for phased commissioning to start in Q4 2024 with critical modifications to the first of eight kilns largely complete. Key to this is the conversion of the fuel source for these kilns from Heavy Fuel Oil ("HFO") to coal gasification, which will significantly enhance the operational efficiency and reduce operating costs of the plant.

 

Additionally, the aggregate crushing operation is continuing to perform very well, underpinning positive operational cashflow as well as providing an increasing stockpile for the kilns, which is now in excess of 15,000 tonnes.

 

Coal gasifier

The first gasifier arrived on site and is now being erected.

 

Figure 1: Parts of gasifier arriving at Limeco, 29 October 2024.

 

Figure 2: Parts of gasifier being off loaded at lime plant, 29 October 2024.

Figure 3: Erection of gasifier

 

Modifications to Kiln 1

Work is progressing well for the commissioning of Kiln 1 by the end of Q4 2024 with the following activities concluded or in progress:

 

Item

Status

Comment

Discharge cone

Completed & operational

Increased discharge opening

Rotary table

Completed & operational

Modified opening

New skip hoist brakes

Completed & operational

Single drum changed to double

New discharge gates

Not completed

Awaiting arrival on site

New burner ports

Not completed

Arrived & being installed

Feed conveyor to skip hoist

Completed & operational

-

Skip hoist

Completed & operational

-

Pan conveyor

Completed & operational

-

Roller crusher

Completed & operational

-

Bucket elevator

Completed & operational

-

Silo discharge end

Not completed

Work in progress

Modified exhaust stack

Completed

Installed on 30 October 2024

 

Figure 4: View of refurbished hoist structure (blue) and refurbished skip (orange).

 

Coal storage facility

Work on the coal storage facility, from where the coal will be conveyed to the coal gasifier, is 40% completed.

 

Figure 5: View of incline ramp from coal storage facility to coal gasifier.

 

Crushing plant

The newly installed impact crusher is performing well with over 60,000 tonnes of limestone crushed. The kiln feed, sized -90mm to +60mm, is stockpiled near the lime plant and now totals 15,000 tonnes. Furthermore, aggregate production from the minus 60mm stream is also going well and contributing 50% to Limeco's positive operational cashflow.

 

 

Figure 6: View of part of the kiln feed with lime plant in the background.

 

Laboratory

The recently constructed pilot kiln is performing well with burn tests giving good results; initial test results showed available quicklime ranging between 92% and 94%.

 

 

Figure 7: Burnt limestone from the pilot kiln awaiting further testwork to determine available quicklime (CaO).

 

Mineral Resource Estimate

Earthlab Exploration and Mining Consulting ("Earthlab") has been engaged by Firering to update the current Mineral Resource Estimate ("MRE") of 73.7Mt @ 95.3% CaCO3  produced by Golder Associates in October 2017. This update, incorporating data from the recently awarded 392.51 hectare exploration licence adjacent to Limeco's current licence (see RNS dated 3 September 2024), has the potential to increase the MRE by between 60Mt to 70Mt at similar grades. Earthlab's updated JORC compliant report is expected in November 2024.

 

Long-term offtake agreements

Discussions are advancing with clients across various sectors for long-term offtake agreements. This includes negotiations with local and regional industries currently reliant on imported quicklime, principally from South Africa. Limeco's robust production capacity, combined with its commitment to quality control, is generating considerable market interest.

 

*** ENDS ***

 

For further information visit www.fireringplc.com or contact:

 

Firering Strategic Minerals

Yuval Cohen E: info@firering-holdings.com

SPARK Advisory Partners Limited (Nominated Adviser)

Neil Baldwin / James Keeshan / Adam Dawes T: +44 20 3368 3550

Optiva Securities Limited (Joint Broker)

Christian Dennis / Daniel Ingram T: +44 20 3137 1903

Shard Capital Partners LLP (Joint Broker)

Damon Heath / Erik Woolgar T: +44 20 7186 9950

St Brides Partners Limited (Financial PR)

Isabel de Salis / Susie Geliher / Seb Weller E: firering@stbridespartners.co.uk

 

Notes

Firering Strategic Minerals plc is an AIM listed resource company set to commence commissioning a significant quicklime project in Zambia in Q4 2024 to produce 600-800 tonnes of quicklime per day along with ancillary products. With over US$100 million in historical investment, the project is strategically positioned to support the expanding copper producers in the Zambian Copper Belt, which are currently reliant on imported quicklime from South Africa. Firering currently holds an SPA over a 20.5% stake in Limeco Resources Limited ("Limeco") with 10% already paid and an option to increase this to 45%. Additionally, the Company is advancing the Atex Lithium-Tantalum Project in northern Côte d'Ivoire, an exploration project rich in lithium and tantalum-niobium, with drilling results indicating significant resource potential in this established mining jurisdiction.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDQKQBQPBDDNDK
Date   Source Headline
27th May 20267:00 amRNS4th Tranche Limeco Option Exercised & Ops Update
20th May 20261:17 pmRNSHolding(s) in Company
19th May 202610:49 amRNSExtension to Bridge Loan Notes
18th May 202611:14 amRNSResult of General Meeting
24th Apr 20267:00 amRNSFunding to Raise £2.5m & Notice of General Meeting
20th Apr 20267:00 amRNSCommercial and Operational Update
2nd Apr 20267:00 amRNSOperations Update
16th Mar 20267:00 amRNSOperations Update
16th Mar 20267:00 amRNSOperations Update
10th Feb 20267:00 amRNSOperations Update
5th Feb 20262:57 pmRNSHolding(s) in Company
21st Jan 20267:00 amRNSCorporate and Operations Update
15th Jan 20267:00 amRNSHolding(s) in Company
14th Jan 20267:00 amRNSOperations Update
24th Dec 20257:00 amRNSFundraising and Limeco Operations Update
12th Dec 20257:00 amRNSRicca Resources US$1M Settlement Finalised
19th Nov 20257:00 amRNSUpdate on Ricca EGM Date & Settlement
12th Nov 20257:00 amRNSFirering Secures US$1M Debt Settlement
9th Oct 20257:00 amRNSExercise of second tranche of Limeco Option
29th Sep 20257:00 amRNSInterim Results
19th Sep 20257:00 amRNSQuicklime Operations Update
21st Aug 20259:28 amRNSHolding(s) in Company
19th Aug 20258:11 amRNSJV Partner withdrawal from Lithium Projects
15th Aug 20259:40 amRNSHolding(s) in Company
7th Aug 202510:20 amRNSHolding(s) in Company
31st Jul 20257:00 amRNSExercise of first tranche of Limeco Option
30th Jul 202510:13 amRNSFunding & Ops Update Replacement
29th Jul 202511:00 amRNSDirectors’ subscription; Further subscription
29th Jul 20257:34 amRNSFunding & Quicklime Operations Update
24th Jul 20251:12 pmRNSIssue of Equity; TVR
24th Jul 20251:05 pmRNSResult of AGM
30th Jun 20257:00 amRNSFinal Results
2nd Jun 20257:00 amRNSFirst Quicklime Sales & Expansion Ongoing
24th Apr 20257:00 amRNSIncreases Interest in Zambian Quicklime Project
23rd Apr 20257:00 amRNSCommercial Production Gains Momentum at Limeco
24th Mar 20257:00 amRNSResult of Placing and Subscription
21st Mar 20254:34 pmRNSProposed Placing & Subscription
27th Feb 20257:00 amRNSFirst Quicklime Production at Limeco, Zambia
19th Feb 20257:00 amRNSCommencement of First Quicklime Production Process
28th Jan 202512:45 pmRNSHolding(s) in Company
22nd Jan 20257:00 amRNSAggregate Production Achieves Nameplate Capacity
18th Dec 20249:19 amRNSHolding(s) in Company
12th Dec 20247:00 amRNSQuicklime Operational Update
27th Nov 20247:00 amRNSMaiden JORC-Code Compliant MRE at Limeco
15th Nov 20247:00 amRNSNon-dilutive funding strategy
5th Nov 20247:00 amRNSQuicklime Project Update
4th Nov 20243:45 pmRNSHolding(s) in Company
30th Sep 20247:00 amRNSTotal Voting Rights
25th Sep 20249:33 amRNSReplacement: Interim Results & Presentation
25th Sep 20247:00 amRNSInterim Results & Investor Presentation

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.