Wressle Development Update

26 Nov 2020 07:00

RNS Number : 5467G
Europa Oil & Gas (Holdings) PLC
26 November 2020
 

Europa Oil & Gas (Holdings) plc / Index: AIM / Epic: EOG / Sector: Oil & Gas

 

Europa Oil & Gas (Holdings) plc ('Europa' or 'the Company')

 Wressle Development Update

 

Europa Oil & Gas (Holdings) plc, the UK, Ireland and Morocco focused oil and gas exploration, development and production company, is pleased to provide an update on the development of the Wressle Oil Field ('Wressle' or the 'Project') in North Lincolnshire. Wressle lies on licences PEDL180 & 182 (the Licences') in which Europa holds a 30% working interest alongside Egdon Resources (30% and operator), and Union Jack Oil (40%).

 

Installation of surface facilities

Reconfiguration works at the Wressle site have now been completed and surface facilities are currently being installed. To date, the storage tanks and inspection gantry have been installed while work is advanced in respect of the electrical and control system installation. Delivery of all remaining equipment is expected to be completed during December, despite the challenges posed by the impact of COVID-19 restrictions on the current supply chain operating environment. All works have been completed safely in line with the operator's "COVID secure" operating procedures.

 

Recent photographs of the Wressle development site can be found on Europa's Twitter feed: https://twitter.com/Europaoilandgas

 

Timing of workover operations

In order to eliminate any possible operating and supply chain issues associated with the December festive period shutdown, the partners in the Wressle development have elected to defer the workover operations and final commissioning of the oil field until January 2021. In line with this, mobilisation of the workover rig will now take place immediately in the New Year, with the workover being completed and initial oil flows now anticipated during late January 2021.

 

Wressle set to increase Europa's production to over 200bopd

Under the development plan, Wressle is expected to commence production at an initial gross rate of 500bopd, which would more than double Europa's existing UK onshore production to over 200bopd. With an estimated breakeven oil price of US$17.62 per barrel, production at Wressle is expected to be very profitable at current oil prices of over US$45 per barrel.

 

Additional development potential on the Licences

During testing at Wressle, a total of 710 barrels of oil equivalent per day were recovered from three separate reservoirs: the Ashover Grit; the Wingfield Flags; and the Penistone Flags. In September 2016, a Competent Person's Report ('CPR') provided independent estimates of reserves and contingent and prospective oil and gas resources for the Wressle discovery of 2.15 million stock tank barrels classified as discovered (2P+2C). Further development of the Wressle field, including producing additional reserves existing in the Penistone Flags formation, is expected in the future. The CPR assigned a geological chance of success of 49% for the Penistone Flags and 40% for the Ashover Grit.

 

In addition, the Licences hold Broughton North, a low risk exploration prospect lying on the footwall side of a fault, adjacent to the historic Broughton-B1 discovery made by BP in 1984 which the CPR assigned gross mean un-risked prospective resources of 0.6 million boe.

 

Simon Oddie, CEO of Europa, said: "Much work has been and continues to be carried out to prepare the Wressle site for production, despite the challenges posed by COVID-19 and the associated lockdowns. This ongoing activity will enable workover operations to commence as soon as the rig is mobilised to the site following the festive break. We are evaluating the effect of the new schedule on our cashflow and are examining financing options to cover any potential shortfall. Importantly, with first oil targeted by end of January 2021, oil prices rallying strongly towards the US$50 per barrel level, and a low breakeven oil price of US$17.62 per barrel, production at Wressle, which will more than double Europa's net production to over 200bopd, will not only transform our financial profile in the near term but it will also be highly profitable.

 

"Our objective is to expose our shareholders to significant value creating opportunities while minimising risk. Our exploration projects, which include our industry leading position in the proven gas play of the Slyne Basin offshore Ireland and the large Inzegane permit offshore Morocco where initial work has identified 30 targets that could hold up to 10 billion barrels of oil, provide significant value creating opportunities. Our UK onshore production provides a low risk cash flow generative platform with which to pursue higher reward opportunities. Production at Wressle will dramatically scale up this low risk platform and with this in mind I look forward to providing further updates on our progress."

 

* * ENDS * *

 

For further information please visit www.europaoil.com or contact:

 

Simon Oddie

Europa

+ 44 (0) 20 7224 3770

Murray Johnson

Europa

+ 44 (0) 20 7224 3770

Christopher Raggett

finnCap Ltd

+ 44 (0) 20 7220 0500

Simon Hicks

finnCap Ltd

+ 44 (0) 20 7220 0500

Frank Buhagiar

St Brides Partners Ltd

+ 44 (0) 20 7236 1177

Megan Dennison

St Brides Partners Ltd

+ 44 (0) 20 7236 1177

 

Notes

Europa Oil & Gas (Holdings) plc has a diversified portfolio of multi-stage hydrocarbon assets which includes production, development and exploration interests, in countries that are politically stable, have transparent licensing processes, and offer attractive terms. In terms of production, in 2019 Europa produced 91 boepd. Production is set to increase to over 200 boepd in January 2021 once the Wressle field in the UK, which is currently under development, comes on stream at a gross rate of 500 bopd.

 

The Company holds four exploration licences offshore Ireland which have the potential to host gross mean un-risked prospective resources of 3.9 billion barrels oil equivalent and 2.7* trillion cubic feet ('tcf') gas (*subject to regulatory approval for the transfer of FEL 3/19). The Company's flagship projects offshore Ireland are Inishkea and Edge, two near field gas prospects in the Slyne Basin which the Company classifies as lower risk infrastructure-led exploration due to their close proximity to the producing Corrib gas field and associated gas processing infrastructure. In September 2019, Europa was awarded a 75% interest in the Inezgane permit offshore Morocco. Initial results of technical work have identified 30 prospects and leads that have the potential to hold close to 10 billion barrels of unrisked oil resources.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDFELEFIESSEIF
Date   Source Headline
5th Jun 20263:00 pmRNSNotice of AGM
29th May 20267:00 amRNSMMHD Approval of Farm-out to Fuhai
27th May 20267:00 amRNSFinal results for 17-months to 31 December 2025
18th May 20267:00 amRNSCloughton Well - Planning Application Update
27th Apr 20267:00 amRNSNorth Yorkshire Council Decision: Cloughton Well
31st Mar 20267:00 amRNSTotal Voting Rights
27th Mar 20267:00 amRNSFEL 4/19 Licence Extension Approval
5th Mar 20262:00 pmRNSPOST TRANSACTION REPORT
5th Mar 202612:10 pmRNSHolding(s) in Company
3rd Mar 202611:50 amRNSResult of General Meeting, Admission & TVR
12th Feb 20264:13 pmRNSNotice of GM and Posting of Circular
12th Feb 20263:43 pmRNSEG-08 PSC Phase 1 Extension Finalised
12th Feb 202610:20 amRNSDirector/PDMR Shareholding
12th Feb 20267:23 amRNSResult of increased WRAP Offer, Amended GM & TVR
10th Feb 20264:30 pmRNSNotice of GM and Posting of Circular
10th Feb 20263:00 pmRNSWRAP Retail Offer for up to £350,000
10th Feb 20267:15 amRNSResults of the Placing
10th Feb 20267:00 amRNSConditional Placing to raise up to £3.5m and GM
30th Jan 20262:30 pmRNSHolding(s) in Company
30th Jan 20267:01 amRNSTotal Voting Rights
30th Jan 20267:00 amRNSFEL 4/19 - Status of Licence
16th Jan 20267:00 amRNSPEDL343 (Cloughton) Extension
6th Jan 20262:55 pmRNSIssue of Shares, TVR and Director/PDMR Dealings
31st Dec 20258:37 amRNSDirector/PDMR Dealing
31st Dec 20258:37 amRNSDirector/PDMR Dealing
30th Dec 20253:30 pmRNSResult of AGM
30th Dec 20253:30 pmRNSResult of AGM
30th Dec 20257:00 amRNSEG-08 Farm-out Agreement Signed
30th Dec 20257:00 amRNSEG-08 Farm-out Agreement Signed
8th Dec 20257:00 amRNSNotice of AGM
20th Nov 20257:00 amRNSDL003 Extension
6th Oct 20257:00 amRNSEG-08 PSC Phase 1 Extension
15th Sep 20257:00 amRNSInterim Results
8th Sep 20257:00 amRNSNotice of Investor Presentation and Q&A Session
7th Aug 20254:23 pmRNSNotification of change in significant shareholding
5th Aug 20253:09 pmRNSDirector/PDMR Dealing
5th Aug 202512:58 pmRNSDirector/PDMR Dealing
4th Aug 20257:00 amRNSEG-08 Farm-out update
27th May 202512:06 pmRNSRevenue Swap Agreement ("RSA") Consideration
21st May 20257:00 amRNSRevenue Swap Agreement
9th Apr 20254:46 pmRNSAward of Options
8th Apr 20253:34 pmRNSDirector/PDMR Dealing
8th Apr 202511:58 amRNSDirector/PDMR Dealing
8th Apr 202511:53 amRNSHolding(s) in Company
20th Mar 202511:54 amRNSDirector/PDMR Dealing
20th Mar 20257:00 amRNSInterim Results
7th Mar 20257:00 amRNSCloughton Planning Application & Website Launch
11th Feb 20257:00 amRNSBoard Changes
31st Jan 20259:41 amRNSDirector/PDMR Dealing
31st Jan 20257:00 amRNSOperations Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.