Colombia - Capella No.1 Well Result

Emerald Energy Plc ("Emerald" or the "Company") would like to provide the following update on operations in Colombia.

Drilling of the Capella No.1 exploration well, in the Ombu block, commenced on 10th July and reached its total depth of 3,802 feet on 30th JulyHydrocarbon shows were encountered while drilling the target Mirador formation and wireline logging indicated the presence of 189 feet of potential hydrocarbon bearing intervals.

After the wireline logging evaluation, the lower non-prospective section of the borehole was isolated with a cement plug set at 3,420 feet and casing was run to a depth of 3,303 feet leaving the middle 117 feet of potential hydrocarbon paybelieved to be of lower porosity and permeability, uncased in open hole and the upper 72 feet of potential hydrocarbon pay in mainly higher porosity sandstones behind casing.

Flow testing of the open-hole interval has been achieved using a progressive cavity mechanical pump. During this testing over a period of days, the production stabilised at a rate of approximately 155 barrels per day of 10.5 degree API gravity oil with a water cut of approximately 15% which may have been the return of drilling fluids lost to the formation while drilling. The lower open hole section was subsequently isolated with a retrievable bridge plug so that it may be re-entered later.

The upper cased zone was then perforated and flow tested, also using a progressive cavity mechanical pump, operating at a reduced rate to avoid the potential inflow of solids from the higher porosity sandstones. During this testing over a period of days, the production stabilised at a rate of approximately 85 barrels per day of 10.5 degree API gravity oil with only traces of water.

On completion of this initial testing the rig will be demobilised from the well site. It is then planned to conduct longer term production testing of the well for a period of up to six months which may involve the use of alternative pump configurations and cyclic steam injection.

Under the terms of the farmout agreement announced on 14th July 2008, the cost of drilling, evaluating, and testing the Capella No.1 well, including the longer term production testing, is being paid by Canacol Energy Inc. to earn a 10% interest in the Ombu block. In total, Canacol may earn up to a 30% interest in the Ombu block, subject to the approval of the National Hydrocarbon Agency of Colombia ("ANH"), in three stages by paying 100% of the cost of up to 15 wells plus 2D and 3D seismic surveys. 

The Company has notified the ANH of the results to date of this discovery. Following these encouraging results from the first well on this potentially large structurethe Company has decided to drill the Capella No.2 well approximately 1.3 kilometres from the Capella No.1 discovery well. Drilling of the Capella No.2 well will commence once the rig has been mobilised to the location and the well is expected to take up to three months to drillevaluate and flow test.

Emeralds' Chief Executive Officer, Angus MacAskill, said:

“We are pleased with the results of the Capella No.1 well demonstrating the presence of oil in this material structure and providing an encouraging total cold flow production rate of approximately 240 barrels of oil per day from the tested zones in this vertical well. We are optimistic that these results, together with the data expected from the Capella No.2 well, will support the commercial development of this conventional heavy oil discovery.”

 

Enquiries: Lisa Hibberd 020 7925 2440

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLSFIFDMSASEIU
Date   Source Headline
14th Jul 20097:00 amRNSUpdate
13th Jul 20092:32 pmRNSRule 8.3- Emerald Energy Plc
13th Jul 20097:00 amRNSStatement regarding recent share price movement
30th Jun 200910:57 amRNSTotal Voting Rights
23rd Jun 20097:00 amRNSWell update
17th Jun 20093:09 pmRNSHolding(s) in Company
16th Jun 20097:00 amRNSOperations Update - Syria, Block 26
9th Jun 200911:58 amRNSShare award
9th Jun 20097:00 amRNSOperations Update
8th Jun 20094:27 pmRNSHolding(s) in Company
8th Jun 20097:00 amRNSSyrian Presentation
4th Jun 200911:01 amRNSHolding(s) in Company
29th May 200911:10 amRNSTotal Voting Rights
27th May 20097:00 amRNSOperations Update - Syria, Block 26
7th May 20092:29 pmRNSTotal Voting Rights
6th May 20097:00 amRNSOperations Update
30th Apr 20097:00 amRNSOperations Update - Syria, Block 26
24th Apr 20093:50 pmRNSResult of EGM
24th Apr 20093:48 pmRNSResult of AGM
24th Apr 20097:00 amRNSInterim Management Statement
23rd Apr 20097:00 amRNSOperations Update
22nd Apr 200910:35 amRNSHolding(s) in Company
20th Apr 200912:35 pmRNSHolding(s) in Company
15th Apr 20094:12 pmRNSConversion of Convertible Bonds
8th Apr 200911:55 amRNSAnnual Information Update
24th Mar 20097:00 amRNSDrilling Report
18th Mar 20091:05 pmRNSRule 9 waiver
18th Mar 200912:55 pmRNSNotice of documents for Inspection
18th Mar 200912:52 pmRNSDirector/PDMR Shareholding
16th Mar 20097:00 amRNSFinal Results
6th Mar 20097:00 amRNSDrilling Update
4th Mar 200910:00 amRNSOperations update
2nd Mar 20098:53 amRNSBlock listing six monthly return
24th Feb 20097:00 amRNSOperations update
11th Feb 20097:00 amRNSColombia - Operations Update
29th Jan 20099:19 amRNSNew Licence
26th Jan 20097:00 amRNSOperations Update
21st Jan 20098:00 amRNSDrilling Update
15th Jan 20097:00 amRNSDrilling Report
22nd Dec 20087:00 amRNSDrilling Update: Gigante No.2 Well
18th Dec 20084:35 pmRNSPrice Monitoring Extension
26th Nov 20082:52 pmRNSDirectorate Change
25th Nov 20084:39 pmRNSPrice Monitoring Extension
19th Nov 20087:00 amRNSYousefieh No.1 Exploration Well Result, Block 26
11th Nov 200810:59 amRNSDrilling results correction
10th Nov 20087:00 amRNSCapella Number 2 Drilling Results
5th Nov 200810:25 amRNSDrilling Report - Correction
5th Nov 20087:50 amRNSDrilling Report
20th Oct 20087:00 amRNSInterim Management Statement
6th Oct 20087:21 amRNSDrilling Commences on Yousefieh-1 Exploration Well

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.