Operational Update

24 Jun 2009 16:30

RNS Number : 4532U
Diamondcorp Plc
24 June 2009
 



DiamondCorp Plc

JSE share code: DMC & AIM share code: DCP

ISIN: GB00B183ZC46

(Incorporated in England and Wales)

(Registration number 05400982)

(SA company registration number 2007/031444/10)

("DiamondCorp" or "the Company")

LACE MINE UPDATE AND CAUTIONARY ANNOUNCEMENT

BOTSWANA EXPLORATION JOINT VENTURE

DiamondCorp plc, the South African diamond mining company provides the following update on activities at the Lace diamond mine in South Africa and announces details of a new exploration joint venture signed in Botswana.

LACE MINE UPDATE

PRIMARY CRUSHING CIRCUIT

Commissioning of the new primary crushing circuit at the Lace diamond mine in South Africa has been successfully completed and kimberlite dump material processed during the commissioning process yielded 1,533.95 carats of gem diamonds, including a 14.74 carat clear white stone. 

The diamonds were tendered in Johannesburg in May and sold for R963,541, representing a price of US$79 per carat. The US dollar per carat exceeded management's revised forecast, but was slightly lower than forecast on a rand per carat basis due to the strengthening of the rand.

In addition, 292.61 carats of non- or near-gem diamonds were recovered, meaning approximately 85 per cent of the diamonds recovered from the kimberlite were gem quality, which is in line with management estimates. The non-gem diamonds were tendered and sold at US$3.74 per carat. A further 2,367.51 carats of gem diamonds recovered earlier in the year from tailings re-crush were also tendered and sold for R890,368, representing US$47 per carat. 

Commenting on the tender priceDiamondCorp managing director and CEO Paul Loudon said: 'Demand for the Lace diamonds in May was strong as cutters and polishers sought to fill holes in inventories.

'We expect prices to remain around these levels for the remainder of 2009, but no significant price appreciation is anticipated until the second half of 2010.'

UNDERGROUND MINING PLAN

Management's mine planning for access to the remaining kimberlite at Lace has been assisted by the location last month in a Government archive in Pretoria of all the level plans from mining operations which took place between 1901 and 1931. Management has been searching for the plans for four years, and had previously been advised by the Department of Minerals and Energy that they suspected the plans had been destroyed in a fire in Welkom some years ago.

The plans reveal that more kimberlite has been extracted above the -240m level than was previously estimated in independent competent persons' reports (CPR). The CPRs do not incorporate kimberlite above the -240m level in resource estimates but concluded that a significant volume of Main Pipe and Satellite Pipe kimberlite existed between -100m and -240mAs a consequence of the level plan data, it is apparent that until the 4m x 4m access decline reaches the -240m level in the second half of 2010, DiamondCorp's mining will be limited to 1,000 tonnes per day. The reduced mining rate until the -240m level is reached will have a negative impact on cashflow from operations, the full extent of which will be determined when grade and carat value from the current sampling programme is completed by the end of July. 

Accordingly shareholders are advised to exercise caution when dealing in their shares until details of the sampling programme are announced, which is expected on or about 31 July 2009. 

On the positive side, the plans reveal more than 9,000m of development is in place between the -240m and -330m levels. Once the -240m level is reached it is anticipated that mining will be able to increase to 4,000 tonnes per day through the existing vertical shaft on the current schedule in the second half of 2010. In addition, the Directors expect that the plan data will have a positive impact on the Company's resource statement as the estimated 6.57 million tonnes of kimberlite between the 240m and the 345m levels, which has previously not been included in resource estimates, is now expected to be upgraded to an indicated resource under the SAMREC code. Between the -345m level and the -855m level there is an inferred resource of 24.24 million tonnes of kimberlite at an estimated grade of 42 carats per hundred tonnes, containing 11.91 million carats of diamonds

Processing of bulk samples of kimberlite from the Satellite Pipe and from the CK Pillar of the Main Pipe at Lace is now underway. The results from these samples are anticipated by the end of July. The Satellite Pipe is predominantly volcaniclastic kimberlite (VK)* and was historically reported to be a lower grade than the Main Pipe. While not integral to the proposed mining plan, the Satellite Pipe grade results will be incorporated into a review of the Company's resource statement now underway as well as provide important information with respect to diamond quality, value and stone size distribution. The CK Pillar, which is adjacent to DiamondCorp's spiral decline progressing to the -240m level and surrounds the original Lace mine prospect shaft, is anticipated to contain a proportion of potentially high-grade coherent kimberlite (CK)** as well as remnant VK facies and is integral to the proposed mine plan until the end of 2010.

BOTSWANA EXPLORATION JOINT VENTURE

DiamondCorp has reached agreement with Botswana exploration company Geoperspectives (Pty) Limited to earn a 77.5% interest in three diamond exploration licences in Botswana. The licences total 109.2 sq km and contain nine known kimberlites. DiamondCorp can earn its interest in the joint venture by completing a definitive feasibility study within five years on developing a new diamond mine in the project area.

The primary exploration target is kimberlite J-01 within Licence PL071/2007, which is approximately 8km southeast of De Beers Jwaneng Mine. Previous limited exploration indicates J-01 has a possible size of 9.9ha and a potential grade of 35 carats per hundred tonnes.

An initial work programme for the Botswana joint venture areas is now being prepared.

NOTES

* VK - Volcaniclastic Kimberlite. Kimberlite which has been diluted with non-diamond bearing country rock due to fragmentation processes at the time of emplacement. Previously referred to as TKB, tuffisitic kimberlite breccia.

** CK - Coherent Kimberlite. Kimberlite which, because it was emplaced without fragmentation processes, has not been diluted with non-diamond bearing country rock. Previously referred to as hypabyssal kimberlite.

Information in this announcement relating to exploration results in Botswana is based on data reviewed by Mr Paul Zweistra B.Sc.(Hons) Pr.Sci.Nat., a director of VP3 GeoServices (Pty) Limited, who is registered as a Professional Natural Scientist with the South African Council for Natural Scientific Professions in the field of geological science, and has more than 27 years relevant experience in mineral exploration and is a Qualified Person under AIM rules. Mr Zweistra consents to the inclusion of the information in the form and context in which it appears.

24 June 2009

London

Sponsor:

Investec Bank Limited

For further information, please contact:

Paul Loudon

DiamondCorp plc

+44 20 7256 2651 

Joe Nally/Yvonne Cantu/Liz Bowman

Cenkos Securities plc

+44 20 7397 8900

Robert Smith/Tanis Crosby

Investec Bank Limited

+27 11 286 7662

Charmane Russell

Russell & Associates

+27 11 880 3924

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSEUFILSUSESM
Date   Source Headline
19th Oct 20163:20 pmRNSForm 8.3 - DiamondCorp Plc
19th Oct 20161:57 pmRNSForm 8.3 - DiamondCorp Plc
19th Oct 20167:13 amRNSForm 8.3 - Diamondcorp Plc
18th Oct 20162:40 pmRNSForm 8.3 - DiamondCorp Plc
18th Oct 201612:59 pmRNSForm 8.3 - Diamondcorp Plc
18th Oct 201612:17 pmRNSForm 8.3 - Diamondcorp Plc
18th Oct 20167:00 amRNSSTRATEGIC REVIEW
18th Oct 20167:00 amRNSMining Resumes at the Lace Diamond Mine
14th Oct 20167:00 amRNSFunding Update
13th Oct 201610:10 amRNSOPERATIONAL AND FINANCIAL UPDATE
12th Oct 20167:00 amRNSProject and Financial Update
20th Sep 201612:45 pmRNSUpdate on Diamond Sales from the Lace Diamond Mine
13th Sep 20167:00 amRNSInterim Results and Operational Update
9th Aug 20167:00 amRNSLace Diamond Mine Operational Update
26th Jul 20163:00 pmRNSLACE DIAMOND MINE UNDERGROUND MINING RESUMES
18th Jul 20167:00 amRNSLace Diamond Mine
14th Jul 20167:00 amRNSDirector/PDMR Shareholding & Amendment
12th Jul 20167:00 amRNSExercise of Broker Option and Directors' Dealings
7th Jul 20169:59 amRNSPlacing and Subscription & Broker Option
16th Jun 20167:50 amRNSResult of AGM
14th Jun 20167:00 amRNSLace Diamond Mine - Diamond Sales & Project Update
19th May 20167:00 amRNSAnnual Financial Report
4th May 20167:00 amRNSFinal Results
19th Apr 20167:00 amRNSPolished Diamond Sales and Project Update
5th Apr 20167:00 amRNSLace Diamond Mine - March Quarter Update
2nd Mar 20167:00 amRNSResource Statement
1st Feb 20167:00 amRNSDirectorate Change
26th Jan 20167:00 amRNSLace Diamond Mine Project Update
7th Jan 20161:30 pmRNSResult of General Meeting
23rd Dec 20157:00 amRNSPosting of Circular
22nd Dec 20157:00 amRNSAdditional Listing
16th Dec 20157:00 amRNSLace Mine Ramp Up Commences From Uk4 Block
3rd Dec 20154:20 pmRNSResults of Placing and Directors' Dealings
3rd Dec 20157:00 amRNSIDC Loan & £4m Proposed Placing
2nd Dec 20154:37 pmRNSIDC Loan & £4m Proposed Placing
20th Nov 20157:00 amRNSLace Mine - 290M Level Development Resumes
12th Nov 20157:00 amRNSConveyor Belt Commissioned
3rd Nov 20157:00 amRNSLace Diamond Mine Project Update
13th Oct 20157:00 amRNSConveyor Belt Installation Diamond Sales Valuation
1st Sep 20157:03 amRNSInterim Results
31st Jul 20157:00 amRNSLace Diamond Mine Project Update
9th Jul 20151:00 pmRNSDirector/PDMR Shareholding
6th Jul 20157:00 amRNSResult of Open Offer
26th Jun 20157:00 amRNSResult of AGM
17th Jun 20157:00 amRNSOpen Offer
5th Jun 20157:00 amRNSPlacing and Subscription to raise £3.18 million
3rd Jun 20157:44 amRNSAnnual Financial Report
26th May 20158:14 amRNSFinal Results
15th May 20157:00 amRNSChange of Registered Office
14th May 20158:30 amRNSAdditional Listing

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.