Less Ads, More Data, More Tools Register for FREE

Pin to quick picksDCP.L Regulatory News (DCP)

  • There is currently no data for DCP

LACE MINE PROJECT UPDATE

30 Jan 2014 07:00

RNS Number : 8001Y
Diamondcorp Plc
30 January 2014
 



30 January 2014

 

 

DiamondCorp plc

 

AIM share code: DCP & JSE share code: DMC

ISIN: GB00B183ZC46

(Incorporated in England and Wales)

(Registration number 05400982)

(SA company registration number 2007/031444/10)

 

("DiamondCorp", "the Group" or "the Company")

 

Lace mine Project update

 

DiamondCorp, the Southern African diamond development and exploration company, is pleased to provide the following update on the underground development and tailings re-treatment activities at the Lace diamond mine in the Free State province of South Africa.

 

 

Highlights

 

· Underground development remains close to schedule and under budget.

· The owner-operated mining fleet continues to provide over 90% availability and is operating under budget.

· Steel sets are now being installed in the boxcut ramp to provide tunnel support before the excavation is backfilled.

· The underground conveyor belt system is on schedule and the first leg for installation has been delivered to site.

· Surface piling for the raise boring of the life of mine vent shaft has commenced.

· A 400 tonne per hour (tph) in-pit screening system which has the potential to increase tailings throughput to 150,000 tonnes per month has been installed and is about to be commissioned.

· Drilling of the Bulge area from underground continues to confirm the potential for additional kimberlite between the 260m and 470m levels which is not currently in the mine plan.

· The Company has experienced no labour issues.

· The weakening of the rand is forecast to have a positive impact on operating margins and the Group debt position.

· Diamond sales for 2014 will commence next month with prices reportedly improving by 5-10% since December.

 

Underground development

 

The Company's 74%-owned Lace Diamond Mines (Pty) Limited (LDM) continues to ramp up underground development close to schedule and within budget.

 

At the end of December 2013, underground tunnel development was 15% complete versus a scheduled 16% (1,113m against 1,187m) and is being achieved at 94% of the budgeted cost per metre (R27,470/m against R29,360/m). Hiring of an additional two mining crews is underway and the full underground complement is expected to be reached by the end of March.

 

The Company has experienced no labour issues and continues to hire the personnel it requires. The labour force in December 2013 totalled 233 and is forecast to grow to approximately 350 by the end of this year.

 

Safety remains a major priority for the Company, with Lace achieving a 64% improvement in the lost time injury frequency rate (LTIFR) from 0.90 in 2012 to 0.55 in 2013. Management aims for zero harm to its employees and targets a LTIFR of less than 0.5.*

 

Surface piling for the life of mine vent shaft has commenced and is expected to be completed by the end of February 2014, well ahead of the raise bore contractor mobilising in the second half of the year.

 

The underground mining fleet continues to provide over 90% availability, with operating costs running at 95% of budget. The mining fleet rebuild costs are also running at 95% of budget. The last two rebuilt 20 tonne low profile dump trucks required to achieve maximum underground development rates have been commissioned on time. The last two underground loaders are currently being assembled and are scheduled for completion next month.

 

Twin decline development from the base of the boxcut continues downwards to meet the development tunnels coming up from the 92m level. To date, ground conditions in the upper levels are more competent than those experienced in the exploration decline at a similar elevation. Installation of the steel sets for reinforcement of the portal area is complete and double sets are now being installed up the ramp of the boxcut. Once installed, timbered and shotcreted, the boxcut will be partially backfilled and profiled with shallow batter angles.

 

The design and detail drawings for the underground conveyor belt system are on schedule (85% complete) and under budget. Fabrication of the first leg of the conveyor to be installed has been completed and delivered to site; fabrication of the second leg is 40% complete.

 

Tailings retreatment

 

Following adjustments to the bottom screen size cut reported previously, tailings retreatment continued on one shift in October and two shifts in November and December 2013.

 

During the three month period ended December 31 2013, the plant processed 138,475 tonnes against a budget 140,000 tonnes and recovered 6,522.71 carats at a recovered grade of 4.71 carats per hundred tonnes (cpht) against a budget 5 cpht. Mining during the latter part of the period was in the oldest lower grade section of the dump to clear space for the installation of a 400 tph in-pit high frequency sand screen.

 

The sand screen was installed in January and commissioning by the manufacturer Osborn is about to commence. The screen has the potential to increase tailings throughput to 150,000 tonne per month. At an expected average grade of 5 cpht, the screen is forecast to increase diamond recoveries from tailings retreatment to 7,500 carats per month and reduce plant operating costs to R22/t on a three shift basis.

 

Diamond Sales

 

Diamond sales for 2014 will commence in February, with ten sales scheduled for the year. The Company's diamontaires in Antwerp report that demand for rough diamonds has improved and that prices have increased 5-10% over the prices achieved in December 2013.

 

The Company is forecasting an average of $63/ct for its tailings goods in 2014, which would give revenue of R35/t at an exchange rate of R11 to the dollar.

 

The 20% weakening of the rand since the middle of 2013 has resulted in potential tailings retreatment margins increasing by 30% from a forecast R10/t to R13/t. The weaker rand also has a beneficial impact on potential underground operating costs with forecast operating breakeven grade falling from 10 cpht to 9 cpht after adjusting for the negative impact on diesel price inputs. The Lace kimberlite grade ranges from 24 cpht in the upper levels to an estimated 57 cpht in the lower levels of the pipe.

 

The weaker rand and stronger sterling also has a positive impact on the Group debt position as the majority of the Company's project finance is denominated in rand and reported in sterling. Diamond sales being denominated in US dollars provide a natural hedge against the weakening rand.

 

 

Bulge drilling

 

Drilling of the Bulge area continues from inside the kimberlite. At the end of December 2013, a total of 1,220m of diamond core drilling had been completed. The nine holes drilled to date continue to confirm that the Bulge area has the potential to host significant additional kimberlite between the 260m and 470m levels which is not currently in the mine plan. The drilling will form the basis of a resource upgrade for the Bulge area in the first half of 2014 and thereafter a feasibility study on the economics of mining this area.

 

 

Contact details:

 

DiamondCorp plc

Paul Loudon, Chief Executive

Tel: +27 (0) 56 212 2930

Euan Worthington, Chairman

Tel: +44 (0) 7753 862 097

 

UK Broker & Nomad

Panmure Gordon (UK) Limited

Dominic Morley/Adam James

Tel: +44 20 7886 2500

 

JSE Designated Advisor

Sasfin Capital (a division of Sasfin Bank Limited)Leonard Eiser

Tel: +27 11 809 7738

 

* LTIFR is an industry standard calculation based on the number of lost time injuries multiplied by 200,000, divided by the number of lost time injuries multiplied by 9. Lace had one lost time injury in 2013 and 40,185 lost time injury free shifts during the year to 31 December 2013.

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
STREADFNADPLEFF
Date   Source Headline
20th Apr 20107:30 amRNSOperational Update
13th Apr 20103:32 pmRNSHolding(s) in Company
8th Apr 20104:06 pmRNSHolding(s) in Company
8th Apr 20102:42 pmRNSHolding(s) in Company
6th Apr 20104:02 pmRNSHolding(s) in Company
1st Apr 20103:45 pmRNSResult of EGM - Replacement
1st Apr 20101:00 pmRNSResult of EGM
15th Mar 20102:56 pmRNSIssue of Equity Replacement
15th Mar 20107:00 amRNSIssue of Equity
12th Feb 201010:30 amRNSAppointment of Joint Broker
10th Feb 20107:00 amRNSMarket Update
21st Jan 201012:45 pmRNSIssue of Equity
16th Dec 20095:00 pmRNSNotice of EGM
24th Nov 20097:30 amRNSDrilling Update
17th Nov 20097:00 amRNSBotswana Drilling Update
16th Nov 20093:30 pmRNSIssue of Equity
3rd Nov 20091:45 pmRNSIssue of Equity
14th Oct 20097:00 amRNSUpdate on Offer Talks and Financial Position
5th Oct 20097:00 amRNSStatement re Possible Offer
30th Sep 200912:30 pmRNSHalf Yearly Report
31st Jul 200911:00 amRNSLace Mine Update
24th Jun 20094:30 pmRNSOperational Update
7th May 20097:30 amRNSAGM Statement
31st Mar 20097:30 amRNSFinal Results
30th Mar 20097:30 amRNSOperational Update - Crushing Circuit
5th Feb 200912:00 pmRNSGrant of mining right
27th Jan 200910:00 amRNSTrading Statement
17th Dec 20089:00 amRNSHolding(s) in Company
14th Nov 20083:49 pmRNSHolding(s) in Company
14th Nov 20088:42 amRNSDirectorate Change
14th Nov 20088:00 amRNSDirector/PDMR Shareholding
13th Nov 20088:00 amRNSHolding(s) in Company
12th Nov 200810:10 amRNSEIIB announces increased private equity investment
7th Nov 200811:26 amRNSIssue of Equity
29th Sep 20088:00 amRNSInterim Results
1st Sep 20084:00 pmRNSResult of EGM
15th Aug 200812:00 pmRNSNotice of GM and posting of c
28th Jul 20089:00 amRNSLoan Facility
4th Jul 20082:00 pmRNSResult of AGM
3rd Jul 20087:30 amRNSMARKET UPDATE - JULY 2008
20th Jun 200811:00 amRNSHolding(s) in Company
30th May 200812:00 pmRNSDirector/PDMR Shareholding
28th May 20084:00 pmRNSAGM statement and Annual Repo
23rd May 20084:00 pmRNSIssue of Equity
30th Apr 20089:00 amRNSExercise of warrants
8th Apr 20087:30 amRNSSenior Management Appointment
31st Mar 20087:02 amRNSNotice of dual listing
20th Mar 200810:00 amRNSNotice of dual listing
4th Mar 20087:00 amRNSFinal Results
15th Feb 20087:00 amRNSIssue of Equity

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.