LACE MINE PROJECT UPDATE

30 Jan 2014 07:00

RNS Number : 8001Y
Diamondcorp Plc
30 January 2014
 



30 January 2014

 

 

DiamondCorp plc

 

AIM share code: DCP & JSE share code: DMC

ISIN: GB00B183ZC46

(Incorporated in England and Wales)

(Registration number 05400982)

(SA company registration number 2007/031444/10)

 

("DiamondCorp", "the Group" or "the Company")

 

Lace mine Project update

 

DiamondCorp, the Southern African diamond development and exploration company, is pleased to provide the following update on the underground development and tailings re-treatment activities at the Lace diamond mine in the Free State province of South Africa.

 

 

Highlights

 

· Underground development remains close to schedule and under budget.

· The owner-operated mining fleet continues to provide over 90% availability and is operating under budget.

· Steel sets are now being installed in the boxcut ramp to provide tunnel support before the excavation is backfilled.

· The underground conveyor belt system is on schedule and the first leg for installation has been delivered to site.

· Surface piling for the raise boring of the life of mine vent shaft has commenced.

· A 400 tonne per hour (tph) in-pit screening system which has the potential to increase tailings throughput to 150,000 tonnes per month has been installed and is about to be commissioned.

· Drilling of the Bulge area from underground continues to confirm the potential for additional kimberlite between the 260m and 470m levels which is not currently in the mine plan.

· The Company has experienced no labour issues.

· The weakening of the rand is forecast to have a positive impact on operating margins and the Group debt position.

· Diamond sales for 2014 will commence next month with prices reportedly improving by 5-10% since December.

 

Underground development

 

The Company's 74%-owned Lace Diamond Mines (Pty) Limited (LDM) continues to ramp up underground development close to schedule and within budget.

 

At the end of December 2013, underground tunnel development was 15% complete versus a scheduled 16% (1,113m against 1,187m) and is being achieved at 94% of the budgeted cost per metre (R27,470/m against R29,360/m). Hiring of an additional two mining crews is underway and the full underground complement is expected to be reached by the end of March.

 

The Company has experienced no labour issues and continues to hire the personnel it requires. The labour force in December 2013 totalled 233 and is forecast to grow to approximately 350 by the end of this year.

 

Safety remains a major priority for the Company, with Lace achieving a 64% improvement in the lost time injury frequency rate (LTIFR) from 0.90 in 2012 to 0.55 in 2013. Management aims for zero harm to its employees and targets a LTIFR of less than 0.5.*

 

Surface piling for the life of mine vent shaft has commenced and is expected to be completed by the end of February 2014, well ahead of the raise bore contractor mobilising in the second half of the year.

 

The underground mining fleet continues to provide over 90% availability, with operating costs running at 95% of budget. The mining fleet rebuild costs are also running at 95% of budget. The last two rebuilt 20 tonne low profile dump trucks required to achieve maximum underground development rates have been commissioned on time. The last two underground loaders are currently being assembled and are scheduled for completion next month.

 

Twin decline development from the base of the boxcut continues downwards to meet the development tunnels coming up from the 92m level. To date, ground conditions in the upper levels are more competent than those experienced in the exploration decline at a similar elevation. Installation of the steel sets for reinforcement of the portal area is complete and double sets are now being installed up the ramp of the boxcut. Once installed, timbered and shotcreted, the boxcut will be partially backfilled and profiled with shallow batter angles.

 

The design and detail drawings for the underground conveyor belt system are on schedule (85% complete) and under budget. Fabrication of the first leg of the conveyor to be installed has been completed and delivered to site; fabrication of the second leg is 40% complete.

 

Tailings retreatment

 

Following adjustments to the bottom screen size cut reported previously, tailings retreatment continued on one shift in October and two shifts in November and December 2013.

 

During the three month period ended December 31 2013, the plant processed 138,475 tonnes against a budget 140,000 tonnes and recovered 6,522.71 carats at a recovered grade of 4.71 carats per hundred tonnes (cpht) against a budget 5 cpht. Mining during the latter part of the period was in the oldest lower grade section of the dump to clear space for the installation of a 400 tph in-pit high frequency sand screen.

 

The sand screen was installed in January and commissioning by the manufacturer Osborn is about to commence. The screen has the potential to increase tailings throughput to 150,000 tonne per month. At an expected average grade of 5 cpht, the screen is forecast to increase diamond recoveries from tailings retreatment to 7,500 carats per month and reduce plant operating costs to R22/t on a three shift basis.

 

Diamond Sales

 

Diamond sales for 2014 will commence in February, with ten sales scheduled for the year. The Company's diamontaires in Antwerp report that demand for rough diamonds has improved and that prices have increased 5-10% over the prices achieved in December 2013.

 

The Company is forecasting an average of $63/ct for its tailings goods in 2014, which would give revenue of R35/t at an exchange rate of R11 to the dollar.

 

The 20% weakening of the rand since the middle of 2013 has resulted in potential tailings retreatment margins increasing by 30% from a forecast R10/t to R13/t. The weaker rand also has a beneficial impact on potential underground operating costs with forecast operating breakeven grade falling from 10 cpht to 9 cpht after adjusting for the negative impact on diesel price inputs. The Lace kimberlite grade ranges from 24 cpht in the upper levels to an estimated 57 cpht in the lower levels of the pipe.

 

The weaker rand and stronger sterling also has a positive impact on the Group debt position as the majority of the Company's project finance is denominated in rand and reported in sterling. Diamond sales being denominated in US dollars provide a natural hedge against the weakening rand.

 

 

Bulge drilling

 

Drilling of the Bulge area continues from inside the kimberlite. At the end of December 2013, a total of 1,220m of diamond core drilling had been completed. The nine holes drilled to date continue to confirm that the Bulge area has the potential to host significant additional kimberlite between the 260m and 470m levels which is not currently in the mine plan. The drilling will form the basis of a resource upgrade for the Bulge area in the first half of 2014 and thereafter a feasibility study on the economics of mining this area.

 

 

Contact details:

 

DiamondCorp plc

Paul Loudon, Chief Executive

Tel: +27 (0) 56 212 2930

Euan Worthington, Chairman

Tel: +44 (0) 7753 862 097

 

UK Broker & Nomad

Panmure Gordon (UK) Limited

Dominic Morley/Adam James

Tel: +44 20 7886 2500

 

JSE Designated Advisor

Sasfin Capital (a division of Sasfin Bank Limited)Leonard Eiser

Tel: +27 11 809 7738

 

* LTIFR is an industry standard calculation based on the number of lost time injuries multiplied by 200,000, divided by the number of lost time injuries multiplied by 9. Lace had one lost time injury in 2013 and 40,185 lost time injury free shifts during the year to 31 December 2013.

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
STREADFNADPLEFF
Date   Source Headline
27th Jun 20123:00 pmRNSResult of AGM
12th Jun 20129:00 amRNSOperational Update
31st May 20127:00 amRNSFinal Results
23rd May 201210:31 amRNSHoldings in Company
21st May 20127:00 amRNSLoan Funding Term Sheet with IDC
1st May 20127:00 amRNSDirectorate Change
20th Mar 20127:00 amRNSLACE MINE INDEPENDENT ENGINEERING AND RESOURCE REP
10th Feb 20129:59 amRNSOperations Update
30th Jan 20127:00 amRNSOperational Update
20th Dec 20112:00 pmRNSBotswana Exploration Update
19th Dec 20119:45 amRNSDirectors' Shareholdings
15th Dec 201110:45 amRNSInsurance Settlement
31st Oct 20118:45 amRNSTotal Voting Rights
24th Oct 201110:00 amRNSHolding in Company
20th Oct 201110:00 amRNSDirector's Shareholding
20th Oct 20117:00 amRNSPlacing to raise GBP2.05 million - Replacement
19th Oct 20117:00 amRNSPlacing to raise GBP2.05 million
5th Oct 20117:00 amRNSOperational Update
22nd Sep 20117:00 amRNSHalf Yearly Report
19th Sep 201112:30 pmRNSDirectorate Change
7th Sep 20117:00 amRNSOperational Update
2nd Aug 20117:00 amRNSOperational Update
29th Jul 201111:00 amRNSTotal Voting Rights
8th Jul 20114:30 pmRNSHolding in Company
30th Jun 20111:52 pmRNSTotal Voting Rights
29th Jun 20117:00 amRNSAnnual Report and Notice of Annual General Meeting
16th Jun 20117:00 amRNSIssue of Equity
6th Jun 20117:30 amRNSLace Mine Development Costs
27th May 20117:00 amRNSHolding in Company
10th May 20117:30 amRNSOperational Update
30th Mar 201110:30 amRNSHolding in Company
4th Mar 201111:00 amRNSChange of Adviser
3rd Feb 20117:00 amRNSOperational Update
10th Jan 20117:30 amRNSAppointment Of Joint Broker
22nd Dec 20102:21 pmRNSHolding(s) in Company
22nd Dec 20102:00 pmRNSResult of EGM
9th Dec 20107:00 amRNSIssue of Equity
7th Dec 20107:00 amRNSIssue of Equity
8th Nov 20107:30 amRNSOperational Update
8th Sep 20107:00 amRNSBOTSWANA EXPLORATION UPDATE
20th Aug 201012:30 pmRNSIssue of Equity
20th Aug 20107:00 amRNSAGM Statement
18th Aug 20108:00 amRNSHalf Yearly Report
12th Aug 201010:59 amRNSHolding(s) in Company
12th Aug 201010:15 amRNSHolding(s) in Company
7th Jul 20107:00 amRNSOperational Update
25th Jun 201012:00 pmRNSFinal Results
1st Jun 20107:00 amRNSChange of Adviser
6th May 20107:00 amRNSSenior Management Appointment
21st Apr 201012:00 pmRNSDirectorate Change

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.