Update on Definitive Feasibility Study

18 Jun 2014 07:00

RNS Number : 8577J
Chaarat Gold Holdings Ltd
18 June 2014
 

Chaarat Gold Holdings Limited

("Chaarat" or the "Company")

 

Update on Definitive Feasibility Study

 

Road Town, Tortola, British Virgin Islands (18th June 2014)Chaarat (AIM - CGH), the AIM quoted exploration and development company with assets in the Kyrgyz Republic, is pleased to provide a further progress update on the Definitive Feasibility Study ("DFS") for the Chaarat Project ("the Project").

Highlights

· Projected production expected to be increased significantly to at least 250,000 ounces of gold per annum - a level appropriate to the size of the Chaarat deposit

· Two stage option to implement the Project identified which would enable production to commence with a lower up-front capital cost

· Heap leach operation estimated to generate circa 120,000 ounces of gold per year

· Production rate from sulphide ore yet to be determined but likely to be higher than the heap leach level of production

· Layout of whole Project revised to improve efficiency, reduce possible environmental impact and eliminate access issues

· Small amount of additional drilling underway to support the implementation strategy and secure more geotechnical information

· Cheaper processing option for refractory ore under investigation

· Timing for completion of DFS revised to early 2015, reflecting the assessment of the enlarged heap leach opportunity

As announced in March 2014, the team of DFS consultants visited the Chaarat site when it opened at the end of April. Their findings have now been evaluated. The first stage of the work involved studying various alternatives and options to conclude on an optimal scope for the development of the Chaarat Project. The DFS will then be prepared in accordance with the agreed scope.

Strategic development of the deposit

The optimal strategic development of the deposit has been identified as two production lines which share elements of the infrastructure, but are economically feasible as standalone Projects. The decision whether to implement the two lines sequentially or in parallel will be based on the likely financing options available to the Company, for example, whether Chaarat will self-develop the deposit or whether it will be developed by a JV with a large operating partner or a strategic investor.

The Chaarat deposit hosts two types of ore which can be treated by different processes. One zone (the Tulkubash Project) is predominantly low sulphur and amenable for heap leaching. The other part of the deposit is more refractory and requires oxidation before gold can be leached out of the ore. 

The involvement and provision of financing from a joint venture partner or strategic investor should enable both stages of the process to be undertaken at once. If this involvement does not materialise, the processes can be undertaken sequentially, dependent on the availability of finance to Chaarat.

The DFS will evaluate the heap leach and refractory options as separate standalone Projects.

Layout of the Project

The Chaarat deposit is located in a narrow valley which could inhibit the expansion of the Project once in production. As part of the DFS, the consultants reviewed other options for the location of the processing plant and associated infrastructure. A trade off study has concluded that there are considerable economic, environmental and operational benefits to locating the production facility in an adjacent valley. 

In order to connect the plant to the mine site a 10km tunnel will need to be constructed through the mountain. The preliminary results of the trade off study have demonstrated that the reduction in haulage and other operating costs will significantly outweigh the capital cost of the tunnel, while also delivering major environmental benefits. Further work is now underway to finalise the design and costs of the tunnel construction.

Scale considerations

A staged development will mean that the heap leach option, which requires significantly less capital investment and is less complex to operate, will be built initially. The indicative capital cost of the tunnel and power line necessary to take the first stage heap leach Project into production will have an impact on the economics of this Project on a standalone basis, but the anticipated increased level of production to 120,000 ounces of gold per annum should support the attractive return on this investment. Conversely, the economics of the second larger refractory Project will benefit very considerably from the capital expenditure carried by the heap leach Project.

Heap leach operational scale

The main feed of ore for the heap leach operation is from the Tulkubash zone. A preliminary mine design of the Tulkubash pit has indicated the economic benefits of processing not only the material grading above 1 g/t cut-off but also the lower grade material situated inside the pit envelope. This early plan shows reserves included in the initial pit will be about 17 million tonnes of ore at a grade of 0.93 g/t being 523,000 ounces of heap leachable reserves. The strip ratio is currently estimated at about 2:1. The low strip ratio, with the consequent reduction in the mining costs of diesel and labour (which are in any case relatively low in the Kyrgyz Republic), will increase the returns generated from the heap leach operation. It has therefore been decided that the heap leach operation will be designed to process 5 million tonnes per annum or 15,000 tonnes per day and produce approximately 120,000 ounces of gold per annum.

As this revised production level is significantly higher than previously expected, additional drilling of about 4-5,000 metres is required to support a sustainable standalone heap leach operation. This drilling has commenced and is expected to be concluded in September. The mineralised zone very clearly extends towards the north which gives us confidence that the required resource can be added.

Scale of the refractory operation

The mine design of both the refractory open pit and underground operation is also in progress. The optimal scale of the operation can only be determined once the mine design is complete. However, the results of the DFS to date indicate that the scale of the Project can be significantly larger than the originally anticipated production of 200,000 ounces per year included in the Prefeasibility Study prepared in 2011. The heap leach Project alone is being designed for 5 million tonnes of ore annually or production of about 120,000 ounces of gold per year. The refractory operation (which will be fed from both the open pit and underground) can support a greater production profile.

Process update

We initially considered that the refractory ore, due to its sulphur content, would need to be processed by oxidation which would probably take the form of flotation followed by pressure oxidation. The capital cost of this process is significant.

Initial work on bio-oxidation of the crushed refractory ore has shown promising results by using a simpler process of heap bio-oxidation followed by heap leaching. The results were achieved following a short oxidation period by a generic culture. More work has been commissioned to develop a tailor made culture and to run larger scale tests. If this process proves to be suitable there will be considerable positive effects on the economics of the Project, by the reduction of both capital and operating costs.

Timing

The results to date of the DFS have exciting implications for the economics of the Project. However in order to complete the work and analyse the results we now expect to complete the DFS in early 2015. The Board firmly believes that the additional work will add value to the Chaarat Project by increasing production, reducing operating costs and reducing the environmental impact.

The Board has carefully reviewed the revised budget and cash flow for the group and is taking measures to source additional funding from the sale of equipment (originally purchased for small scale production so not immediately needed following the revision to the strategy) and other exploration assets to cover the impact of the additional work and enlargement of scope of the DFS. Some equipment has already been sold and further advanced negotiations are in progress. In addition, we have already received expressions of interest in acquiring some of our exploration assets.

Dekel Golan CEO of Chaarat commented: "As the Project starts to take shape we are all excited by the emerging initial results. The purpose of the study is not merely to develop a "spreadsheet" Project but to demonstrate how project risk can be mitigated and the Project as a whole simplified and made more robust.

The decision to build a tunnel removes almost entirely issues of access to site and concerns about environmental protection in a restricted location; considerations which more than outweigh the increase in upfront costs and the delay to production caused by the construction of the tunnel. Having a heap leach operation that, in itself, underpins the economics of all the development- whether or not a second stage is built - is another major positive.

A projected production capacity of 250,000 ounces per annum confirms Chaarat's potential as a top gold producer, and the two stage option delivers flexibility, while not compromising overall returns.

We continue to be of the belief that Chaarat is one of the largest and best undeveloped Projects in the world and the uncompromising objectives of the DFS are to demonstrate both the economic merit of the Project as well as to chart a clear route for its development. On this basis the increased scope of the DFS and additional data collection now underway is more than justified.

Updates will be issued once we have further results to report. I will be giving a presentation at the Proactive Investors event on 26 June and in the meantime the Annual Report will reflect on our progress to date."

Enquiries:

Chaarat Gold Holdings Limited

+ 44 23 800 11747

c/o Central Asia Services Limited

info@chaarat.com

Dekel Golan CEO

 

Linda Naylor FD

 

 

Numis Securities Limited

+44 (0) 20 7260 1000

John Prior, Stuart Skinner (NOMAD)

 

James Black (Broker)

 

Further information is available at www.chaarat.com

NOTES TO EDITORS:

About Chaarat Gold

Chaarat Gold is an exploration and development company operating in the Kyrgyz Republic with a large, high grade resource - the Chaarat Gold Project. The Company's key objective is to become a low cost gold producer generating significant production from the development of the Chaarat Gold Project. Chaarat is preparing a Definitive Feasibility Study (DFS) and continuing its active community engagement programme to optimise the value of the Chaarat investment proposition. Chaarat has several other promising prospects also located within the Kyrgyz Republic.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCGGUUAQUPCGAM
Date   Source Headline
16th Jan 20197:00 amRNSKapan Acquisition - update on transaction status
15th Jan 20197:00 amRNSCompletion of US$350k fundraise
8th Jan 201911:40 amRNSHolding in Company
7th Jan 20199:53 amRNSHolding in Company
2nd Jan 20193:24 pmRNSSignificant Increase in Resource at Tulkubash
31st Dec 201812:40 pmRNSSecond Price Monitoring Extn
31st Dec 201812:35 pmRNSPrice Monitoring Extension
31st Dec 201811:24 amRNSKapan Acquisition - Results of General Meeting
31st Dec 20187:00 amRNSHolding in Company
31st Dec 20187:00 amRNSKapan Acquisition - update on transaction progress
28th Dec 20181:53 pmRNSHolding in Company
21st Dec 20184:27 pmRNSFurther US$350,000 fundraise
20th Dec 20189:10 amRNSGrant of Concert Party waiver
20th Dec 20188:32 amRNSTR-1: Notification of major holdings
14th Dec 201811:30 amRNSRestoration - Chaarat Gold Holdings Limited
14th Dec 201811:10 amRNSAdmission Document and Restoration of Trading
14th Dec 20187:42 amRNSRestoration of Trading, Readmission & Corp Update
28th Nov 201810:59 amRNSFurther US$1 million fundraise
15th Nov 20187:00 amRNSDrilling Further Extends Tulkubash Mineralisation
15th Nov 20187:00 amRNSNew US$10 million loan agreement
31st Oct 20187:00 amRNSUpdate on Proposed Offer for the Kumtor Mine
30th Oct 20187:07 amRNSAgreement to Acquire Kapan Mining Company CJSC
17th Oct 201810:44 amRNSTR1 - Notification of Major Holdings
16th Oct 20187:00 amRNSFundraise update
16th Oct 20187:00 amRNSCorrecting announcement - 13th September 2018
28th Sep 20187:00 amRNSInterim statement for six months ended 30 Jun 2018
20th Sep 20187:00 amRNSTulkubash gold deposit construction update
14th Sep 20181:10 pmRNSTR1 - Notification of Major Holdings
14th Sep 20181:07 pmRNSTR1 - Notification of Major Holdings
13th Sep 20187:00 amRNSAppointment to the Board
13th Sep 20187:00 amRNSClosing of first phase of fundraise
6th Sep 20184:20 pmRNSCorrecting Announcement
4th Sep 20187:00 amRNSSignificant Increases at Tulkubash gold deposit
28th Aug 20187:00 amRNSFundraise and Proposed Acquisition
15th Aug 20187:00 amRNSBoard Changes
31st Jul 20187:00 amRNSExploration Drilling Update
27th Jul 201811:30 amRNSSenior Management Changes
12th Jul 20185:06 pmRNSResult of AGM
12th Jul 20187:00 amRNSKyrgyz Republic Investment Forum
10th Jul 20187:00 amRNSDrilling Extends Tulkubash Mineralisation
4th Jul 20187:00 amRNSAppointment to the Board
25th Jun 20187:00 amRNSExecutive and Board changes
22nd Jun 20187:00 amRNSDrilling Extends Tulkubash Mineralisation
18th Jun 20187:00 amRNSKyrgyz Republic Investment Forum - 28 June 2018
14th Jun 20187:00 amRNSAnnual Report and Notice of Annual General Meeting
11th Jun 20187:00 amRNSPRELIMINARY AUDITED FINANCIAL STATEMENTS
6th Jun 20182:22 pmRNSWhite paper on proposed offer for the Kumtor Mine
4th May 20182:43 pmRNSUpdate on Suspension
1st May 20187:00 amRNS2018 Drilling Commences at Tulkubash
1st May 20187:00 amRNSUpdate on Proposed Offer for the Kumtor Mine

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.