Operational Update

9 May 2018 07:00

RNS Number : 4206N
Caspian Sunrise plc
09 May 2018
Β 

Caspian Sunrise PLC

("Caspian Sunrise" or the "Company")

Β 

Operational update

Β 

Introduction

Β 

Caspian Sunrise the Central Asian oil and gas company, with a focus on Kazakhstan, is pleased to update the market with news at the BNG Contract Area of progress at its Deep and Shallow Wells.

Β 

Deep Wells

Β 

As previously reported we got off to a slow start in January and February following a prolonged period of exceptionally cold weather when little meaningful work was possible on our deep wells, A5, 801 and A6.

Β 

Deep Well A5

Β 

This well had been on a 90-day flow test at the end of Q4 2017 with flow rates reaching 3,800 bopd using a 16mm choke. Blockages in the well led us to reduce the choke size to 6mm and flow rates fell to some 1,000 bopd.

Β 

To maximise the results of the flow test and supply the best information on which to calculate reserves we decided to suspend the flow test and clean out the well.

Β 

The cheapest and potentially quickest way to accomplish this was by use of coil tubing equipment. However, after considerable time and effort was expended we decided coil tubing was unlikely to produce the outcome desired. Accordingly, the coil tubing operation has been discontinued.

Β 

A rig has been mobilised to remove the entire tubing string from the well. This is a more expensive but more certain solution but one that would have been difficult to use earlier in the year in the extreme low temperatures.

Β 

Pressure in the well remains high at 300 bar at the wellhead, which suggests there is still good communication throughout the length of the well.

Β 

Our expectation is that, if successful, the well could be flowing and be ready to be put back on a new 90-day test.

Β 

Deep Well 801

Β 

As previously announced our plan to bring Deep Well 801 into production was by drilling a side track of between 450 - 500 meters from a starting depth of 4,501 meters. After weather delays and initial difficulties in drilling through the metal pipes and casing the recent progress of the side track has been encouraging.

Β 

To date we have drilled 132 meters of the total but expect to increase significantly the pace of drilling such that we would reach total depth in Q2 2018, following which this well would also be ready for a 90-day flow test.

Β 

As with well A5 the pressure in Well 801 remain high.

Β 

Deep Well A6

Β 

Our plan with Deep well A6 remains to re-perforate the well using more powerful explosive charges.

Β 

The drill pipes to be used in this operation are currently in use at Deep Well 801 and work at Deep well A6 will not commence until the pipes at Deep Well 801 are released.

Β 

Shallow wells

Β 

MJF

Β 

We continue to produce from 4 of the six wells drilled at the MJF structure. The aggregate production from wells 141, 143, 144 & 145 has over the past three months averaged 1,900 bopd.

Β 

The issue at wells 142 and 146 is the proportion of water produced with the oil. We intend to engage a leading international contractor to isolate the water from both wells so that they might each produce at the rate of some 200 bopd.

Β 

The Company's management consider the probability of success at Well 142 high as it has already demonstrated that it is capable of sustained production at economic rates.

Β 

Soviet Era wells

Β 

As previously reported, in July 2017 well 54 was successfully re- completed.

Β 

The previous average daily oil production from sandstone of the middle Jurassic was some 90 bopd. In addition wells 805, 806 & 807 also had a combined production rate of 110 bopd form the same Jurassic sandstone intervals.

Β 

Examination of the core and logs from these wells indicates that although individual production zones are relatively thin at c 5 meters, the potential for multiple pay intervals, high reservoir quality and high oil saturation makes these potentially good reservoirs to consider for exploration by horizontal drilling.

Β 

In additional to the known Jurassic sandstone reservoirs additional prospectivity exists with a thin (10 meter) but laterally extensive dolomite interval within the late Jurassic sandstone section.

Β 

A pilot study to test the viability of horizontal drill programme to produce from these intervals is planned to begin in 2019.

Β 

Move to full production licence

Β 

As previously announced we are able from 1 July 2018 to apply to move individual structures to a full production licence under which we would expect to double the price achieved per barrel for oil produced.

Β 

The MJF structure will be the first of the BNG structures to apply for full production status. Recent changes to Kazakh regulations have abolished the bonus payment typically made to the state on such a move, which is likely to save some $6 million.

Β 

Comment

Β 

Clive Carver, Chairman said:

Β 

"Progress in Q1 2018 was slow, partly through weather related delays and partly through equipment failures. Encouragingly progress in Q2 has picked up so that we have expectations of the blockages currently in Deep Wells A5 and 801 being cleared to allow 90-day flow tests to resume later in Q2.

Β 

Production at our shallow wells continues to fund the bulk of our day to day work at BNG where the price derived per barrel is set to double from Q3 2018."

Β 

Ends

Β 

Caspian Sunrise PLC

Β 

Clive Carver

Executive Chairman

+7 727 375 0202

Β 

Β 

WH Ireland, Nominated Adviser & Broker

Β 

James Joyce

Jessica Cave

James Sinclair-Ford

Β 

+44 (0) 207 220 1666

Yellow Jersey PR

Tim Thompson

Henry Wilkinson

Β 

+44 (0) 203 735 8825

Β 

Qualified Person

Β 

Mr. NurlybekOspanov, Caspian Sunrise PLC's Chief Geologist / Technical Director who is a member of the Society of Petroleum Engineers ("SPE"), has reviewed and approved the technical disclosures in this announcement.

Β 

This announcement has been posted to:

www.caspiansunrise.com/investors

Β 

The information contained within this announcement is deemed by the Company to constitute inside information under the Market Abuse Regulation (EU) No. 596/2014.

Β 

Β 

Β 

Β 

This information is provided by RNS
The company news service from the London Stock Exchange
Β 
END
Β 
Β 
UPDZMGGKVRFGRZM
Date   Source Headline
7th Nov 202211:05 amRNSSecond Price Monitoring Extn
7th Nov 202211:00 amRNSPrice Monitoring Extension
4th Nov 20224:40 pmRNSSecond Price Monitoring Extn
4th Nov 20224:35 pmRNSPrice Monitoring Extension
4th Nov 20227:00 amRNSOperational Update and Dividend Declaration
3rd Oct 20224:41 pmRNSSecond Price Monitoring Extn
3rd Oct 20224:36 pmRNSPrice Monitoring Extension
26th Sep 202210:14 amRNSReplacement Announcement for Interim Results
26th Sep 20227:00 amRNSInterim results for six months ended 30 June 2022
11th Aug 20227:00 amRNSResult of GM
30th Jun 20222:21 pmRNSResult of AGM
30th Jun 20228:53 amRNSOraziman family holdings
27th Jun 20227:00 amRNSAnnual Report and Financial Statements
22nd Jun 20228:32 amRNSUK High Court confirms Capital Reduction
6th Jun 20227:00 amRNSOperational and impact of Russian sanctions update
31st May 20227:00 amRNSNotice of AGM
30th May 20227:00 amRNSUK Oil Company Windfall Tax & Dividend Update
25th May 20227:00 amRNSOperational update
22nd Apr 202211:27 amRNSProposed cancellation of share premium account
8th Apr 20229:05 amRNSSecond Price Monitoring Extn
8th Apr 20229:00 amRNSPrice Monitoring Extension
7th Apr 20223:17 pmRNSReview of Q1 2022
5th Apr 20227:00 amRNSProposed cancellation of share premium account
9th Mar 20222:12 pmRNSDebt Conversion and Operational Updates
15th Feb 20227:00 amRNSProposed Debt Conversion and General Meeting
25th Jan 20227:48 amRNSDeep Well Production at BNG
19th Jan 202211:36 amRNSHolding(s) in Company
19th Jan 202211:31 amRNSHolding(s) in Company
19th Jan 202211:26 amRNSHolding(s) in Company
19th Jan 202211:24 amRNSHolding(s) in Company
10th Jan 20224:27 pmRNSGrant of options
10th Jan 20227:46 amRNSOperational update
6th Jan 202212:19 pmRNSOperational update
23rd Dec 20218:35 amRNSOperational update
22nd Dec 20217:00 amRNSOperational, financial and shareholding update
13th Oct 20217:00 amRNSBNG operational update
21st Sep 20217:00 amRNSInterim Results
18th Aug 202112:03 pmRNSTotal Voting Rights
6th Aug 20217:00 amRNSStrategic, Financial, Operational Update
27th Jul 20211:11 pmRNSCompany’s first horizontal well is successful
23rd Jul 202112:06 pmRNSAGM Voting
29th Jun 20217:00 amRNSAnnual Report and Financial Statements
3rd Jun 20217:00 amRNSOperational Update
13th May 20217:00 amRNSShare issue
16th Apr 20217:00 amRNSIncrease in price for oil sold to domestic market
8th Apr 202110:27 amRNSBNG Operational Update
4th Mar 20217:50 amRNSAppointment of Director
5th Feb 20217:00 amRNSCommercial, operational & regulatory update
29th Jan 202110:15 amRNSHolding(s) in Company
29th Jan 202110:15 amRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.