BNG Operational Update

12 Jul 2019 07:00

RNS Number : 3010F
Caspian Sunrise plc
12 July 2019
 

 

Caspian Sunrise PLC

("Caspian Sunrise" or the "Company")

BNG Operational Update

 

The Board of Caspian Sunrise is pleased to provide an operational update on progress across the structures already identified at the BNG Contract Area.

 

Deep Wells

 

A5

 

The Board is pleased to report success in milling away the 2.6-meter metallic obstruction in Well A5 at a depth of 3,887 meters, following which an 85-meter section of lining has been removed from the well much sooner than expected. 

 

While we believe this already provides sufficient room to start the planned 500 meter side-track below the salt layer, for operational ease we have decided to continue to seek to remove approximately a further 30 meters of the lining.

 

If successful, the side-track will commence at a depth of 4,006 meters. If it is not possible to remove these additional 30 meters of liner the side track would start at a depth of 3,976 meters.

 

Once started the side-track is expected to take up to two months to complete.

 

A8

 

Deep Well A8, is the third deep well drilled on the Airshagyl structure. We have in previous announcements referred to the exitence from a depth of 4,342 of a 159-meter carbonate interval, of which 52.5 meters is of porous oil-bearing rock.

 

Since our last announcement, casing has now been set to a depth of 4,520 meters and the associated cementing completed. We are waiting on an independent assessment of the quality of the cementing before deciding how to proceed.

 

Our other Deep Wells

 

We are pleased to report that, in conjunction with a leading international contractor, we are looking to use technology new to Caspian Sunrise to deal with the issues present at both Deep Well A6 and Deep Well 801.

 

A6

 

At Deep Well A6, the principal challenge is establishing connectivity between the wellbore and the reservoir due to the presence of near wellbore damage caused by heavy drilling mud and previous perforating attempts.

 

We now have a two-fold strategy to address and establish connectivity. The first part of the strategy utilises the technology referred to above, by seeking to perforate an interval of potentially oil-bearing rock using acid stimulation techniques, which do not require a rig.

 

The second part of the strategy, if required, involves the utilization and application of more powerful, deeper penetrating perforating charges to help establish reservoir to wellbore connectivity.

 

Should this second part of the strategy be required, it is anticipated that the work would be conducted in Q4, 2019 following drilling of the A5 side-track.

 

801

 

The issues with Deep Well 801 are the blockages, first in the main well and then in the side-track already drilled to get around the pipes stuck towards the bottom of the main well. The blockages result from the use of heavy density drilling mud to contain the extreme pressures in the well.

 

Until recently our approach in dealing with this was to use extremely powerful coil tubing equipment to clear out the well. We have now, in conjunction with a leading International contractor, decided to first attempt to clear the well ready for testing by the use of the same technology as at Deep Well A6.

 

In particular, we will use the same acid treatment to both clear the well and to create longer than standard penetration of the potentially oil-bearing rock.

 

As at A6 this approach does not require a rig and once started is expected to produce results later in Q3, 2019.

 

Shallow Wells

 

MJF

 

Now the licence upgrade has been received we intend to commence a 10-well infill drilling programme following which we expect production from the MJF structure to have increased to approximately 4,000 bopd.

 

Each infill well is expected to cost $1.2 million and to take up to two months to drill.

 

For reasons of economy, we intend to purchase a significant portion of the equipment required for these shallow infill wells.

 

New Structure

 

At the potential new structure, on which well 808 was drilled, two new intervals have been perforated but to date without the discovery of commercial quantities of oil. Perforation work is set to continue at intervals higher than those recently perforated.

 

Monthly production numbers

 

The Board also announces that for the month of June 2019 total production from BNG was 38,571 barrels (May 42,434 barrels) and that the daily average production was 1,286 barrels (May 2019 1,396 bopd).

 

The average domestic sales price achieved was $19 per barrel (May 2019 $19 per barrel).

 

The decrease in production volumes was expected and is the result of postponing much needed remedial work on the MJF wells. Now we have received the MJF licence upgrade we are in a better position to schedule the MJF well workovers to restore production to previous levels.

 

Comments:

 

Clive Carver, Executive Chairman said:

 

"The progress at BNG since our last update is encouraging and we look forward to reporting on the results from our use of the new technologies."

 

Caspian Sunrise PLC

 

Clive Carver

Executive Chairman

+7 727 375 0202

 

 

WH Ireland, Nominated Adviser & Broker

 

James Joyce

Jessica Cave

James Sinclair-Ford

 

+44 (0) 207 220 1666

Yellow Jersey PR

Tim Thompson

Henry Wilkinson

 

+44 (0) 203 735 8825

 

Qualified Person

 

Mr. Nurlybek Ospanov, Caspian Sunrise PLC's Chief Geologist / Technical Director who is a member of the Society of Petroleum Engineers ("SPE"), has reviewed and approved the technical disclosures in this announcement.

 

This announcement has been posted to:

www.caspiansunrise.com/investors

 

The information contained within this announcement is deemed by the Company to constitute inside information under the Market Abuse Regulation (EU) No. 596/2014.

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDCKDDNABKDDOD
Date   Source Headline
9th Nov 20158:27 amRNSUpdate on Operations at BNG
3rd Nov 20157:00 amRNSUpdate on Operations at BNG
7th Oct 20159:40 amRNSDirector/PDMR Shareholding
6th Oct 20153:47 pmRNSExercise of Options
29th Sep 20153:59 pmRNSExercise of Options
29th Sep 20157:01 amRNSOperational Update
29th Sep 20157:00 amRNSInterim Results
4th Sep 20157:00 amRNSUpdate on operations at BNG
24th Jul 20153:53 pmRNSResults of AGM
24th Jul 20157:00 amRNSCancellation of Royalty
15th Jul 20157:00 amRNSUpdate on operations at BNG
3rd Jul 20157:00 amRNSExercise of Options
30th Jun 20157:00 amRNSOperational Update
26th Jun 201512:51 pmRNSPosting of Accounts and Notice of AGM
25th Jun 20157:01 amRNSExercise of Options
25th Jun 20157:00 amRNSThree year BNG Licence extension granted
23rd Jun 20157:00 amRNSFinal Results
19th Jun 20157:00 amRNSUpdate on the sale of Galaz
12th Jun 201511:05 amRNSUpdate on the sale of Galaz
1st Jun 20157:00 amRNSOperational Update
20th May 20151:30 pmRNSUpdate on the sale of Galaz
8th May 20157:34 amRNSExercise of Options
6th May 20157:02 amRNSExercise of Options
1st May 20157:00 amRNSUpdate on operations at BNG
30th Apr 20157:00 amRNSExtension to the completion date of the Galaz sale
17th Apr 20157:00 amRNSUSD20 million subscription
1st Apr 20159:30 amRNSDirector/PDMR Shareholding
1st Apr 20157:00 amRNSUpdate on operations at BNG, the sale of Galaz
24th Mar 20157:00 amRNSExercise of Options
12th Mar 201511:24 amRNSUpdate re Admission of New Shares
9th Mar 20157:00 amRNSOperational Update
24th Feb 20154:00 pmRNSUpdate re Admission of New Shares
19th Feb 20157:00 amRNSIssue of equity
13th Feb 20157:00 amRNSOperational Update
10th Feb 20151:29 pmRNSSale of interest in the Galaz Contract Area
2nd Feb 20157:00 amRNSProposed Sale of the Galaz Contract Area
23rd Jan 20158:11 amRNSDirector/PDMR Shareholding
20th Jan 20157:00 amRNSDrawdown on facility
8th Jan 20157:00 amRNSProposed Sale of the Galaz Contract Area
15th Dec 201411:18 amRNSOperational Update
1st Dec 20147:00 amRNSOperational Update
7th Nov 20147:00 amRNSOperational Update
15th Oct 20147:00 amRNSOperational Update
25th Sep 201410:12 amRNSAward of Options
23rd Sep 20147:00 amRNSInterim Results
8th Sep 20147:00 amRNSOperational Update
1st Sep 20147:00 amRNSFurther update on the Deep Discovery at BNG
27th Aug 201411:55 amRNSExercise of Options
19th Aug 20147:00 amRNSDeep Well Update
11th Aug 20147:01 amRNSExercise of options

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.