SpaceX IPO is the biggest IPO in stock market history. Join the conversation.Click here

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksCentral Asia Metals Regulatory News (CAML)

Share Price Information for Central Asia Metals (CAML)

Share Price is delayed by 15 minutes
Get Live Data
136.20    0.00 (0.00%)
Bid:
136.00
Ask:
136.60
Spread: 0.60 (0.441%)
Market Cap: £232.09m
CAML Live PriceLast checked at - London Stock Exchange

Intraday Central Asia Metals Share Chart

H1 2024 Operations Update

11 Jul 2024 07:00

RNS Number : 9390V
Central Asia Metals PLC
11 July 2024
 

 

11 July 2024

 

CENTRAL ASIA METALS PLC

('CAML' or the 'Company') H1 2024 Operations Update

Central Asia Metals plc (AIM: CAML) provides its H1 2024 operations update for the Kounrad dump leach, solvent extraction and electro-winning ('SX-EW') copper recovery plant in Kazakhstan ('Kounrad') and the Sasa zinc-lead mine in North Macedonia ('Sasa').

H1 2024 operational summary

- Zero lost time injuries ('LTIs') at Kounrad

- One LTI at Sasa

- Kounrad copper production of 6,608 tonnes

- Sasa zinc-in-concentrate production of 9,014 tonnes

- Sasa lead-in-concentrate production of 12,872 tonnes

 

Group cash

 

- Cash in the bank at 30 June 2024 of $56.4 million

 

Outlook

 

- Kounrad on track to achieve 2024 full-year guidance for copper production (13,000 to 14,000 tonnes)

- Sasa expected to achieve production towards the lower end of 2024 guidance:

Zinc-in-concentrate: 19,000 to 21,000 tonnes

Lead-in-concentrate: 27,000 to 29,000 tonnes

 

CAML production summary

Metal production (tonnes)

Q2 2024

Q1 2024

H1 2024

H1 2023

Copper

3,488

3,120

6,608

6,716

Zinc

4,272

4,741

9,014

9,764

Lead

6,343

6,529

12,872

13,734

Nigel Robinson, Chief Executive Officer, commented:

"Kounrad performed well during Q2 2024, bringing H1 production into line with prior years, after facing some difficult winter weather conditions in Q1 of this year.

"Production at Sasa in both Q2 and H1 2024 has been impacted by a modest reduction in mined tonnage, owing principally to the short-term challenges inherent in the transition to a new mining method. This transition, which continued during the quarter, will be of material benefit in the longer-term, by sustaining the life of both the underground mine and its associated tailings storage facilities.

"We look forward to an improvement in mined tonnage at Sasa during H2 2024, as the mining transition progresses. However, taking into account the production levels achieved during H1, we expect full-year production at Sasa to be towards the lower end of our previously announced guidance.

"Our H1 2024 financial results will be released on 10 September 2024, when we will also announce our interim dividend."

Health and Safety

Sasa recorded one LTI during Q2 2024, towards the end of the period.

Kounrad had no LTIs during H1 2024, and at 30 June 2024 had achieved 2,236 days LTI free. 

Kounrad

Production and sales update

Kounrad Q2 2024 copper production of 3,488 tonnes brings output for the first six months of 2024 to 6,608 tonnes. Copper sales during H1 2024 were 6,415 tonnes.

Sasa

Production and sales update

In Q2 2024, 181,525 tonnes of ore were mined and 183,996 tonnes were processed, bringing the H1 2024 totals to 365,652 tonnes mined and 368,075 tonnes processed. The average head grades for the Q2 2024 period were 2.73% zinc and 3.66% lead, and for H1 2024 averaged 2.86% and 3.70% respectively. The average H1 2024 metallurgical recoveries were 85.5% for zinc and 94.4% for lead. 

Sasa produces a zinc concentrate and a separate lead concentrate. In Q2 2024, 8,419 tonnes of concentrate containing 50.8% zinc, and 9,009 tonnes of concentrate containing 70.4% lead were produced. This brings total production for H1 2024 to 17,913 tonnes of zinc concentrate at a grade of 50.3% and 18,186 tonnes of lead concentrate at a grade of 70.8%.

Sasa typically receives from smelters approximately 84% of the value of its zinc-in-concentrate and approximately 95% of the value of its lead-in-concentrate. Accordingly, Q2 2024 payable production was 3,599 tonnes of zinc and 6,026 tonnes of lead, bringing total payable production for H1 2024 to 7,581 tonnes of zinc and 12,228 tonnes of lead.

Payable base metal-in-concentrate sales for H1 2024 were 7,674 tonnes of zinc and 12,535 tonnes of lead, broadly in line with production.

During H1 2024, Sasa sold 174,916 ounces of payable silver to Osisko Gold Royalties, in accordance with its streaming agreement.

Units

Q2 2024

Q1 2024

H1 2024

H1 2023

Ore mined

t

181,525

184,127

365,652

396,234

Plant feed

t

183,996

184,079

368,075

396,673

Zinc grade

%

2.73

3.00

2.86

2.90

Zinc recovery

%

85.0

85.9

85.5

84.9

Lead grade

%

3.66

3.75

3.70

3.72

Lead recovery

%

94.2

94.7

94.4

93.1

Zinc concentrate

t (dry)

8,419

9,494

17,913

19,257

- Grade

%

50.8

49.9

50.3

50.7

- Contained zinc

t

4,272

4,741

9,014

9,764

Lead concentrate

t (dry)

9,009

9,177

18,186

19,302

- Grade

%

70.4

71.1

70.8

71.2

- Contained lead

t

6,343

6,529

12,872

13,734

 

Capital projects - the transition to paste-fill mining

During H1 2024, the Paste Backfill Plant operated consistently, with approximately 130,000 tonnes of paste placed in the voids between the 990 and 910 metre levels and in the cut-and-fill production stopes on the 800 metre level. Some of these previously mined voids proved of greater volume than anticipated, requiring more paste fill, which in turn restricted initial stoping operations under the new mining method. However, this void-filling provides the necessary ground stability for current and future mining, whilst increasing the volume of tailings stored underground and thus further reducing the quantity that needs to be stored on surface. The first long-hole stopes have also been put into production, and additional stopes will follow during H2 2024 and in 2025.

Construction of the Dry Stack Tailings Plant remains on track, with initial placement of filter cake on the engineered landform scheduled for H2 2024.

A total of 3,183 metres of the Central Decline have now been developed, connecting with the 800 metre level during Q2 2024. Completion and connection with the 750 metre level is planned for Q4 2024.

Group cash and debt position

At 30 June 2024, CAML had cash in the bank of $56.4 million and no significant debt.

 

For further information contact:

Central Asia Metals

Tel: +44 (0) 20 7898 9001

Nigel Robinson

CEO

Gavin Ferrar

CFO

Louise Wrathall

louise.wrathall@centralasiametals.com

Director of Corporate Development

Richard Morgan

richard.morgan@centralasiametals.com

Investor Relations Manager

 

 

Peel Hunt (Nominated Advisor and Joint Broker)

Tel: +44 (0) 20 7418 8900

Ross Allister

 

David McKeown

Emily Bhasin

 

 

 

BMO Capital Markets (Joint Broker)

Tel: +44 (0) 20 7236 1010

Thomas Rider

 

Pascal Lussier Duquette

 

 

 

BlytheRay (PR Advisors)

Tel: +44 (0) 20 7138 3204

Tim Blythe

 

Megan Ray

 

 

Note to editors:

 

Central Asia Metals, an AIM-listed UK company based in London, owns 100% of the Kounrad SX-EW copper project in central Kazakhstan and 100% of the Sasa zinc-lead mine in North Macedonia. The Company also owns an 80% interest in CAML Exploration, a subsidiary that was formed to progress early exploration opportunities in Kazakhstan, and a 28.7% interest in Aberdeen Minerals Ltd, a privately owned UK company focused on the exploration and development of base metals opportunities in northeast Scotland.

 

For further information, please visit www.centralasiametals.com and follow CAML on X at @CamlMetals and on LinkedIn at Central Asia Metals Plc

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDQBLFFZDLXBBQ
Date   Source Headline
11th Jun 20265:40 pmRNSTR-1: Form for notification of major holdings
10th Jun 20267:00 amRNSTrading Update and Outlook
9th Jun 20265:14 pmRNSTR-1: Notification of major holdings
9th Jun 20267:00 amRNSTR-1: Notification of major holdings
8th Jun 202612:25 pmRNSShare Purchase by a Director
2nd Jun 20269:36 amRNSTR-1: Notification of major holdings
2nd Jun 20267:06 amRNSProposed acquisition of Cygnus Metals Limited
29th May 20266:03 pmRNSTR-1: Notification of major holdings
20th May 202612:14 pmRNSTR-1: Notification of major holdings
19th May 20265:47 pmRNSTR-1: Notification of major holdings
18th May 20262:37 pmRNSResults of 2026 Annual General Meeting (AGM)
11th May 202612:03 pmRNSShare Premium Cancellation Effective
6th May 20266:00 pmRNSTR-1: Notification of major holdings
5th May 202610:59 amRNSTR-1: Notification of major holdings
1st May 20263:24 pmRNSTR-1: Notification of major holdings
30th Apr 202611:32 amRNSChange of registered office address
16th Apr 20267:00 amRNSQ1 2026 Operations Update
15th Apr 20269:17 amRNSAnnual Report and Accounts 2025 and Notice of AGM
15th Apr 20267:00 amRNSPublication of 2025 Sustainability Report
10th Apr 20261:14 pmRNSTR-1: Notification of major holdings
31st Mar 202612:49 pmRNSTotal Voting Rights
30th Mar 202611:40 amRNSResults of Extraordinary General Meeting
30th Mar 20268:28 amRNSTR-1: Notification of major holdings
19th Mar 20267:00 amRNS2025 Full-Year Results
11th Mar 20264:11 pmRNSTR-1: Notification of major holdings
11th Mar 20264:11 pmRNSTR-1: Notification of major holdings
10th Mar 20267:00 amRNSProposed Share Premium Cancellation and EGM Notice
5th Mar 20267:00 amRNSTransaction in Own Shares
4th Mar 20267:00 amRNSTransaction in Own Shares
3rd Mar 20267:00 amRNSSasa Mineral Resource and Ore Reserve Statement
3rd Mar 20267:00 amRNSNotice of Results
3rd Mar 20267:00 amRNSTransaction in Own Shares
2nd Mar 20267:00 amRNSTransaction in Own Shares
27th Feb 20265:43 pmRNSTotal Voting Rights
18th Feb 20267:00 amRNSTransaction in Own Shares
17th Feb 20267:00 amRNSTransaction in Own Shares
16th Feb 20267:00 amRNSTransaction in Own Shares
13th Feb 20267:00 amRNSTransaction in Own Shares
12th Feb 20267:00 amRNSTransaction in Own Shares
6th Feb 20265:04 pmRNSTR-1: Notification of major holdings
5th Feb 20267:00 amRNSTransaction in Own Shares
4th Feb 20267:00 amRNSTransaction in Own Shares
3rd Feb 20267:00 amRNSTransaction in Own Shares
2nd Feb 20267:00 amRNSTransaction in Own Shares
30th Jan 20265:46 pmRNSTotal Voting Rights
28th Jan 20267:00 amRNSTransaction in Own Shares
23rd Jan 20267:00 amRNSTransaction in Own Shares
22nd Jan 20267:00 amRNSTransaction in Own Shares
20th Jan 20267:00 amRNSTransaction in Own Shares
19th Jan 20267:00 amRNSTransaction in Own Shares

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.