Drilling Operations Update

8 Mar 2018 07:00

RNS Number : 0487H
Cabot Energy PLC
08 March 2018
 

Prior to publication, the information contained within this announcement was deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 ("MAR"). With the publication of this announcement, this information is now considered to be in the public domain.

 

 

Cabot Energy Plc

("Cabot Energy", the "Group" or the "Company")

Drilling operations update

Cabot Energy (AIM: CAB), the AIM quoted oil and gas company focused on production led growth, provides an update on the Company's first quarter winter work programme in Alberta, Canada, which comprises the drilling of four new sidetrack wells.

The work programme is ahead of schedule with three wells successfully drilled and tested and the fourth well scheduled to finish drilling shortly.

 

Summary results table

Sidetrack well

Test rate

(equivalent bopd)

Expected initial production rate

(bopd)

06-08

570

160

15-31

100

100

10-06

626

160

03-07

Currently drilling

 

06-08 sidetrack well

The well targeted a high porosity area within the reef using 3D seismic attribute analysis

Evidence of this high porosity was seen during drilling operations and confirmed by the well test result with an equivalent production rate of 570 bopd

Following completion, the well was put into production and is currently producing at a restricted rate of approximately 160 bopd to best manage the long term performance of the reservoir

15-31 sidetrack well

Following drilling, the well was tested over a short period at an equivalent rate of 100 bopd

During the test the overall fluid production rate was 300 barrels per day and the water cut was continuously reducing

Technical analysis indicated that reef porosity would be less than the other wells in the programme, but would still produce at a significant rate and the result supports that analysis

The well is expected to produce at an initial rate of 100 bopd with a low water cut

10-06 sidetrack well

The original vertical well drilled by the previous operator in 2009 produced little oil from the reef due to completion issues

The new 10-06 sidetrack well drilled 325 metres in the reservoir and tested at an equivalent rate of 626 bopd while still cleaning up

Following completion, the well is expected to be put on production at an initial rate of 160 bopd to manage the long term reservoir performance

03-07 - currently drilling

The 03-07 well has been drilled out of the existing well bore and is currently drilling in the reservoir

It is expected that drilling operations will finish within a week, after which the well will be tested and, if successful, put into production

 

All four wells are tied in via existing pipelines to the Company's 13-36 processing and sales facility. An operations and production update will be provided in April 2018 after the winter work programme completes.

 

Keith Bush, Chief Executive Officer of Cabot Energy, commented:

"The winter work programme is progressing well and each successful sidetrack well supports our technical approach to the redevelopment of the Rainbow region through the use of 3D seismic to identify the properties within each reef and target productive zones. With the completion of the fourth well likely to occur in the coming weeks, the programme will complete ahead of schedule and before the annual spring thaw, which is a credit to our operational team in Canada.

"These sidetrack wells provide excellent data reference points as we look to replicate this success in the summer programme and plan the ongoing development of production and reserves in the region next year."

For further information please contact:

Cabot Energy Plc

+44 (0)20 7469 2900

Keith Bush, Chief Executive Officer

Nick Morgan, Finance Director

SP Angel Corporate Finance LLP

+44 (0)20 3470 0470

Nominated Adviser and Joint Broker

Richard Morrison, Richard Redmayne, Charlie Bouverat

GMP FirstEnergy LLP

+44 (0)20 7448 0200

Joint Broker

Jonathan Wright, David van Erp

FTI Consulting

+44 (0)20 3727 1000 

Financial PR

Edward Westropp

 

In Accordance with AIM Rules - Guidance for Mining and Oil & Gas Companies, the information contained in this announcement has been reviewed and signed off by the CEO of Cabot Energy, Mr Keith Bush, who has 26 years' experience as a petroleum engineer. He has read and approved the technical disclosure in this regulatory announcement. The technical disclosure in this announcement complies with the SPE standard.

 

Note to Editors:

Cabot Energy is an oil and gas company focused on production led growth. The Company is building production from a redevelopment project in north west Alberta, Canada, and has a portfolio of exploration and appraisal opportunities in Italy. Comprehensive information on Cabot Energy and its oil and gas operations, including press releases, annual reports and interim reports are available from Cabot Energy's website: www.cabot-energy.com.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLFKODDKBKBBNK
Date   Source Headline
24th Oct 20069:27 amPRNCommencement of Drilling in the Netherlands
20th Oct 20067:00 amPRNNetherlands Exploration Well to Spud
11th Oct 200610:19 amPRNAdditional Listing
12th Sep 20063:31 pmPRNHolding(s) in Company
23rd Aug 20067:00 amPRNFarmout Agreement
18th Aug 20067:00 amPRNAppointment of Director
28th Jul 20069:58 amPRNExtension and Issue of Warrants
26th Jul 200611:02 amPRNAGM Statement
14th Jul 200612:05 pmPRNAdditional Listing & Issue of Warrants
10th Jul 20067:00 amPRNTRANSFER OF ANDEL LICENCE
26th Jun 200612:30 pmPRNAvington-3 Update
20th Jun 20067:00 amPRNAdditional Listing
19th Jun 200612:00 pmPRNNotice of AGM
19th Jun 20067:00 amPRNFinal Results
12th Jun 20067:00 amPRNReserves Upgrade
9th Jun 20067:00 amPRNAward of Production Licence & Reserve Upgrade
7th Jun 20064:25 pmPRNHolding(s) in Company
25th May 200610:47 amPRNHolding(s) in Company
19th May 20069:21 amPRNHolding(s) in Company
18th May 200610:20 amPRNHolding(s) in Company
16th May 20067:00 amPRNRe. Placing to Raise GBP20 Million
26th Apr 20069:40 amPRNAdditional Listing
25th Apr 20069:28 amPRNHolding(s) in Company
24th Apr 20067:00 amPRNHolding(s) in Company
7th Apr 200611:25 amPRNHolding(s) in Company
24th Mar 20067:00 amPRNNetherlands Reserves Upgrade
14th Mar 20067:00 amPRN€40 Million Project Finance Facility
13th Mar 20067:00 amPRNAvington-3 Update
1st Mar 20063:29 pmPRNHolding(s) in Company
16th Feb 200611:14 amPRNAward of Italian Licences
10th Feb 200610:30 amRNSAvington Update
10th Feb 200610:30 amPRNCommencement of Drilling
30th Jan 200612:08 pmRNSNPEL Completion
30th Jan 20067:00 amPRNRe Spanish Agreements
20th Jan 200612:50 pmPRNLicence Update
29th Dec 20057:00 amPRNFurther Re. Agreements with NAM
9th Dec 200510:30 amPRNChange of Adviser
29th Nov 20053:38 pmPRNExtension of Warrants
11th Nov 20051:22 pmPRNSenior Appointment
10th Nov 20054:33 pmPRNAdditional Listing & Director Shareholding
3rd Nov 20051:13 pmPRNUpdate Re. Share Reorganisation
2nd Nov 20057:00 amPRNLicence Application Update
31st Oct 20057:01 amPRNGuyane Operations
7th Oct 20056:00 amPRNDrilling Report
6th Oct 200510:00 amPRNDisposal
5th Oct 20059:16 amPRNWeekly Drilling Report
29th Sep 200511:29 amPRNInterim Results
28th Sep 20059:44 amPRNWeekly Drilling Report
23rd Sep 20056:00 amPRNRe Agreement
21st Sep 200510:52 amPRNWeekly Drilling Report

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.