Charles Jillings, CEO of Utilico, energized by strong economic momentum across Latin America. Watch the video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksBezant Res Regulatory News (BZT)

Share Price Information for Bezant Res (BZT)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 0.021
Bid: 0.018
Ask: 0.024
Change: 0.00 (0.00%)
Spread: 0.006 (33.333%)
Open: 0.021
High: 0.021
Low: 0.021
Prev. Close: 0.021
BZT Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

New Mining Study Commissioned, Mankayan Project

28 Nov 2018 09:00

RNS Number : 7447I
Bezant Resources PLC
28 November 2018
 

28 November 2018

Bezant Resources Plc

("Bezant" or the "Company")

New Mining Study Commissioned, Mankayan Project, Philippines

Bezant (AIM: BZT), the copper-gold exploration and development company, is pleased to announce that it has commissioned a new mining study to be conducted by Mining Plus Pty Limited ("Mining Plus") in order to examine mining options in relation to distinct high grade areas within the Mankayan copper-gold project, located on the Island of Luzon in the Philippines (the "Mankayan Project").

 

New Mining Study

Mining Plus, a mining technical services provider, has been appointed as an independent consultancy group to undertake a mining study on the Mankayan Project (the "Mining Study") based on their strong international reputation and prior experience with the project. The Board notes that Mining Plus' involvement in an historic study, alongside TWP Australia (Pty) Ltd ("TWP"), was limited in scope by the then specified mining method, production rate and other parameters.

 

Following analysis of higher grade areas and engineering concepts by the Company, the new study will look to examine the viability of new, scalable mining options for the Mankayan Project. One of the objectives of the study is to determine economically viable alternative mining processes, within the Lift 1 area of the historic Scoping Study, to traditional block caving. Block caving typically requires high levels of initial capital expenditure before first production commences.

 

The new Mining Study will comprise a high-level desktop review, which will not require additional drilling, and is expected to be completed during Q1 2019.

 

The Mining Study will consider the economics of various mining options, which may include:

· High-grade focussed block caving

· Alternative production rates

· Staged production rate ramp-ups

 

The existing block cave model, based on the historic studies completed in 2011 and 2014, includes various scenarios built around a two lift sequence including, at a run rate of 20 million tonnes per annum ("Mtpa"), a US$739m net present value ("NPV") with a 21 per cent. internal rate of return ("IRR"), production costs of US$17.31/t, mining capex of US$217m and infrastructure capex of US$796m. Following analysis of certain high-grade areas, including 'open' sections in the JORC (2004) resource, the single lift scenario offers the potential to move from a block cave system to a different mine plan with significantly reduced capital expenditure. It is anticipated than any new alternate mining scenario resulting from the new study would sit alongside the full 20 Mtpa block cave model, thereby allowing the Company distinct options to progress its Mankayan Project.

 

As the new Mining Study will include geological block model analysis, it will assist the Company in determining further target areas where higher grades of copper and gold may exist within the current JORC (2004) resource area defined by Snowden Mining Industry Pty Limited in 2009. The Board notes that this previously reported resource estimate excludes the results of hole BRC-60, a 1,491m diamond drill hole completed by Gold Fields Netherlands Services BV ("Gold Fields"), which were announced on 12 February 2014, which confirmed that the Mankayan deposit is open at depth and increased the previously known depth extent of the mineralisation on the eastern part of the deposit by over 200m.

 

Commenting today Laurence Read, CEO of Bezant, said:

"

"As CEO, I am pleased that we shall be progressing the Mankayan copper gold project following the results of extensive in-house geological and engineering work over the course of the last year. 

 

"Our understanding of Mankayan has grown significantly and the potential for exploiting high grade resource areas needs to be independently examined. While the current, 20 Mtpa economic scenario for Mankayan is highly robust and comparable to a series of successful, currently operating, third party projects we believe that there may well be a viable alternate mining system that can be implemented within the Lift 1 area of the existing model.

 

"Mankayan is a significant potential source of long-term copper gold-supply and the results of the new Mining Study may allow Bezant to pursue new avenues for the project if production scenarios, with reduced upfront capital expenditure, can be determined.

 

"Mining Plus is a major, internationally recognised mining services provider who have successfully worked with a host of mining companies to deliver projects into first production and I look forward to working with them."

 

 

 

For further information, please contact:

 

Bezant Resources Plc

Laurence Read

Chief Executive Officer

Colin Bird

Executive Chairman

 

Tel: +44 (0)20 3289 9923

 

 

Strand Hanson Limited (Nomad)

James Harris / Matthew Chandler / James Dance

 

Tel: +44 (0)20 7409 3494

 

Novum Securities Limited (Broker)

Jon Belliss

 

Tel: +44 (0)20 7399 9400

 

or visit http://www.bezantresources.com

 

 

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulation (EU) No. 596/2014.

 

Notes to Editors:

Mining Plus

Mining Plus (www.mining-plus.com) in an international mining services provider specialising in geology, mining engineering, and geotechnical engineering, covering a broad range of mineral commodities and project types, enhanced by strategic alliances in other core disciplines. Mining Plus has advised on over 1,850 projects for 630 customers in 40 countries over a range of different commodities.

 

The Mankayan Project, Philippines

The Mankayan deposit is principally hosted by a 900m long by 400m wide north-south striking intrusive stock complex composed largely of quartz diorite porphyry. The igneous rocks have intruded a thick sequence of andesitic volcanics and a basement of biotitequartz schists and mafic flows. The size, grade and mineralogy of the Guinaoang deposit are typical of porphyry copper deposits.

 

From October 2011 to January 2014, the Mankayan Project was held under option by Gold Fields for a total exercise price of US$70m (of which US$9.5m was received by the Company by way of initial non-refundable option payments). The option ultimately lapsed, as Gold Fields began new operations in Australia, and all exploration data, including the results of the high-grade BR 60 drill hole completed by Gold Fields during the option period, was transferred to Bezant.

 

Historic Studies

In 2011, TWP was commissioned by Bezant to undertake a Conceptual Study on the Mankayan Project comprising an undeveloped underground mine, for which a conceptual mining, extraction and processing method was to be determined. This study was conducted within +35% to -30% limits of accuracy. In 2014, GHD Group Pty. Limited ("GHD") and Mining Plus were commissioned to conduct a desktop review of TWP's report and update the capital and operating expenditure assumptions.

 

· Project's estimated return (US$3.00/lb, Cu and US$1,250/oz Au):

- post-tax NPV of approximately US$739 million at an 8% discount rate

- post-tax IRR of 21%

- post-tax net cashflow of approximately US$3.7 billion

· Total capital investment cost of approximately US$1 billion over the duration of the project at 20 Mt per annum and over a 28-year mine life

· US$17.31 costs per ore tonne, including all royalties, taxes, capital costs, equipment ownership, operating and processing costs and administrative and technical services costs

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDZMMZMRRMGRZG
Date   Source Headline
30th Mar 20129:35 amRNSInterim Results
29th Mar 20124:35 pmRNSPrice Monitoring Extension
27th Mar 20127:00 amRNSUpdate re Mkurumu Project, Tanzania
20th Mar 20124:40 pmRNSSecond Price Monitoring Extn
20th Mar 20124:35 pmRNSPrice Monitoring Extension
13th Mar 20124:40 pmRNSSecond Price Monitoring Extn
13th Mar 20124:35 pmRNSPrice Monitoring Extension
9th Mar 20124:40 pmRNSSecond Price Monitoring Extn
9th Mar 20124:35 pmRNSPrice Monitoring Extension
6th Mar 20124:40 pmRNSSecond Price Monitoring Extn
6th Mar 20124:35 pmRNSPrice Monitoring Extension
1st Mar 20124:40 pmRNSSecond Price Monitoring Extn
1st Mar 20124:35 pmRNSPrice Monitoring Extension
23rd Feb 20124:41 pmRNSSecond Price Monitoring Extn
23rd Feb 20124:35 pmRNSPrice Monitoring Extension
30th Jan 20127:00 amRNSAppointment of CEO
16th Jan 20123:40 pmRNSDirector's Dealings
11th Jan 20123:00 pmRNSHolding(s) in Company
9th Jan 201212:00 pmRNSHolding(s) in Company
4th Jan 20127:00 amRNSUpdate re Eureka Project - Argentina
28th Dec 20113:30 pmRNSHolding(s) in Company
23rd Dec 201111:30 amRNSHolding(s) in Company
21st Dec 20114:40 pmRNSSecond Price Monitoring Extn
21st Dec 20114:35 pmRNSPrice Monitoring Extension
14th Dec 201112:00 pmRNSResult of AGM
14th Dec 20117:00 amRNSHoldings in Company
1st Dec 20114:35 pmRNSPrice Monitoring Extension
30th Nov 20114:40 pmRNSSecond Price Monitoring Extn
30th Nov 20114:35 pmRNSPrice Monitoring Extension
21st Nov 20117:00 amRNSFinal Results
16th Nov 20113:00 pmRNSHolding(s) in Company
3rd Nov 20114:40 pmRNSSecond Price Monitoring Extn
3rd Nov 20114:35 pmRNSPrice Monitoring Extension
1st Nov 20111:00 pmRNSHolding(s) in Company
28th Oct 20114:40 pmRNSSecond Price Monitoring Extn
28th Oct 20114:35 pmRNSPrice Monitoring Extension
26th Oct 20114:40 pmRNSSecond Price Monitoring Extn
26th Oct 20114:35 pmRNSPrice Monitoring Extension
26th Oct 201111:00 amRNSResult of General Meeting
26th Oct 20117:00 amRNSGeneral Meeting Statement
20th Oct 20114:40 pmRNSSecond Price Monitoring Extn
20th Oct 20114:35 pmRNSPrice Monitoring Extension
5th Oct 20117:00 amRNSGrant of Option re Mankayan Project
15th Sep 20114:35 pmRNSPrice Monitoring Extension
25th Aug 20114:40 pmRNSSecond Price Monitoring Extn
25th Aug 20114:35 pmRNSPrice Monitoring Extension
16th Aug 20114:40 pmRNSSecond Price Monitoring Extn
16th Aug 20114:35 pmRNSPrice Monitoring Extension
15th Aug 20117:00 amRNSUpdate re Eureka Project - Argentina
28th Jun 20114:36 pmRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.