Operational Update

20 Oct 2011 07:00

RNS Number : 5114Q
Beowulf Mining PLC
20 October 2011
 



20 October 2011

Beowulf Mining Plc

("Beowulf" or the "Company")

Operational Update

Maiden JORC resource estimate on Kallak deposit expected by end of October

and additional two phase drilling programme planned

New exploration licence granted over 2,219 hectares adjoining the

presently known limits of the Kallak deposit

Letter of intent signed for a planned 3,000m drill programme at Ballek in 2012

 

Highlights:

·; Maiden JORC resource estimate for the Kallak deposit is expected to be received by the end of October 2011.

·; Additional two phase drilling programme planned for Kallak: Phase One comprising approximately 7,000m intended to commence in late 2011; and Phase Two comprising approximately 50,000m intended to commence in Q2 2012, together representing a large infill drilling programme of up to approximately 57,000m.

·; Per-Ola Larsson appointed as Operational Manager of the Company's Swedish subsidiary, Beowulf Mining AB, which will supervise all of the group's future drilling programmes. 

·; New exploration licence granted over 2,219 hectares adjoining the presently known limits of the Kallak deposit.

·; Letter of intent signed with Dala Prospektering AB to undertake approximately 3,000m of drilling at the Company's joint-venture Ballek copper-gold project, preliminarily scheduled for late 2012.

Clive Sinclair-Poulton, Executive Chairman of Beowulf, commented:

"I am delighted to announce that, subject to securing the requisite financing, we currently plan to embark on an extensive drilling programme at our Kallak deposits. We remain convinced that Kallak North and South are one large ore body and look forward to confirming this via the drill bit."

"It is our intention to further define and prove up the Kallak iron ore project as quickly and efficiently as possible and to this end we plan to conduct a two phased drilling campaign. The appointment of Per-Ola as Operational Manager will greatly assist us in achieving our goal. With such additional drilling planned on our most promising licence areas and an expansion of our areas held under licence, the value of our asset base continues to increase."

 

Beowulf (AIM: BEM; Aktietorget: BEO), the mineral exploration company which owns several exploration projects in Sweden, is pleased to announce an update in respect of its wholly owned Kallak iron ore project and its Ballek copper-gold joint venture project.

Kallak iron ore project

The Company is pleased to announce that the maiden independent JORCresource estimatein respect of its Kallak iron ore deposit isclose to being finalised and is currently anticipated to be completed by the end of October. 

In order to further define the size of the deposit, Beowulf has recently signed a letter of intent with Ludvika BorrTeknik AB, a Swedish drilling company, for the completion of the next stages of its Kallak drilling programme. Ludvika BorrTeknik AB has been directly involved with all previous drilling of the Company's deposits and are technically well equipped and experienced to complete the next drilling phases at a competitive cost. The initial phase ("Phase One") will consist of approximately 7,000m of drilling to define the limits of the northern extension of the Kallak deposit and any possible connection of the northern zone with the southern zone, both in breadth and depth. Subject to sufficient financing being procured, the drilling programme for Phase One is scheduled to commence in late 2011.

The planned second phase of the programme ("Phase Two") will consist of large infill drilling, whereby a denser spacing between individual drill sections and drill-holes will be utilised. The Phase Two drilling programme of up to an estimated 50,000m will cover the entire extension and width of the Kallak deposit. The results of the Phase One and Phase Two drilling programme will then be utilised to move the impending anticipated JORC Inferred status of the deposit towards JORC Measured status as quickly as possible. The Phase Two programme is currently expected to commence in Q2 2012.

Further to the abovementioned planned drilling programme, the Company has signed a letter of intent with the chemical laboratory, ALS Scandinavia AB, to complete all sample preparation and analysis required. ALS Scandinavia AB has been involved in all sample preparation and analysis of Beowulf's earlier completed drilling programmes on the deposit in 2010 and 2011.

Fieldwork in respect of the Environmental Impact Study ("EIS") for the Kallak project has now been completed, including baseline environmental studies and the commissioning of an archeology review. The results of the EIS will be included in the Company's formal application to the Mines Inspector to transfer its existing exploration permit for the Kallak project area into an exploitation (mining) licence. Representatives from the Company are regularly participating in local public information meetings with the principal municipal authorities of Jokkmokk and locally affected community organisations such as Sami village boards.

Licences

Beowulf has submitted a request to the Mines Inspector that all iron ore licences currently held by the Company or its wholly-owned English subsidiary, Iron of Sweden Limited, should be transferred to Beowulf's wholly-owned Swedish subsidiary, Beowulf Mining AB which it is intended will undertake all of the group's future iron ore drilling programmes. Such a transfer will, inter alia, facilitate future applications for mining licences or exploitation concessions where appropriate. In addition, a new wholly-owned Swedish subsidiary, Beowulf Developments AB, is currently being established to hold the Company's other portfolio assets.

Accordingly, Per-Ola Larsson, the son and an experienced colleague of Dr Jan-Ola Larsson, has been appointed as Operational Manager of Beowulf Mining AB in order to coordinate and supervise all future drilling programmes. Mr Larsson has worked for the Company since 2005 and has participated in all of Beowulf's exploration programmes in northern Sweden, having direct responsibility for all field operations and drilling phases completed on the Kallak deposit. Accordingly, Mr Larsson has played a significant role in the Company's discovery and development of the Kallak deposit to date and will continue to do so.

In addition, the Company is pleased to announce that the Mines Inspector has officially granted the Company a new exploration licence, Kallak nr 2, which covers 2,219 hectares of potentially promising land adjacent to the Company's current licence areas of Kallak nr 1 and Parkijaure nr 3, both of which host the presently known limits of the Kallak deposit.

Beowulf has also registered two large licence areas in a direct extension to both the north and south of the existing Kallak deposit area, with the proposed northern licence area covering 11,250 hectares and the southern area covering 1,680 hectares. These newly registered areas, together with Beowulf's currently granted licences, will form a large and potentially new mining province covering approximately 163.5km2, which will preliminarily be defined as the "Jokkmokk Mining District".

As a consequence of the Company's drilling activities on the Kallak deposit and completed regional exploration surveys, the Company has obtained an improved geological and structural understanding of the region surrounding the Kallak deposit. Accordingly, the Company anticipates that these new licence areas being claimed by it may potentially host further deposits of iron, as well as deposits of copper and gold of IOCG type.

Ballek copper-gold joint venture project

The Company also announces that it has signed a letter of intent with Dala Prospektering AB to carry out additional drilling, subject to the requisite funding being available, at its Ballek copper-gold joint venture project in the municipality of Arjeplog in northern Sweden. A total of approximately 3,000m of drilling is planned to test deep lying sourced IOCG targets of Olympic Dam type, as previously defined by deep sensing geophysical surveys carried out by the Swedish company GeoVista AB. This programme is preliminarily scheduled to commence in late 2012.

 

Enquiries:

 

Beowulf Mining Plc

Clive Sinclair-Poulton, Chairman

Tel: +353 (0)85 739 2674

Strand Hanson Limited

Matthew Chandler / Simon Raggett

Tel: +44 (0)207 409 3494

Alexander David Securities Limited

David Scott

Tel: +44 (0)207 448 9820

Lothbury Financial Services Limited

Gary Middleton / Michael Padley

Tel: +44 (0)207 868 2010

or visit http://www.beowulfmining.net

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCBIBDGBSBBGBC
Date   Source Headline
31st Mar 20257:00 amRNS-RCEO Interview
27th Mar 20257:00 amRNS-RUpdated Corporate Presentation
21st Mar 20257:00 amRNSPlacing and Notice of General Meeting
10th Mar 20257:00 amRNSGAMP PFS Demonstrates Robust Project Economics
28th Feb 20256:14 pmRNSUnaudited Results for year ended 31 December 2024
16th Dec 20247:00 amRNSPortfolio update
2nd Dec 20247:00 amRNSChange of Auditor
29th Nov 20247:00 amRNSUnaudited Financial Results
26th Nov 20247:00 amRNSBusiness Finland Commits Additional Grant Funding
31st Oct 20247:00 amRNSCompletion of Business Finland Project
30th Sep 20247:00 amRNSInitiation of the Consultation Process for Kallak
5th Sep 20247:00 amRNSTest-work confirms high grade product at Kallak
30th Aug 20247:00 amRNSUnaudited Results for Period Ended 30 June 2024
28th Aug 20247:00 amRNSGraphite Anode Materials Plant update
22nd Jul 20247:00 amRNSChief Executive Share Purchase
16th Jul 20247:00 amRNSGállok/ Kallak Iron Ore Project Update
28th Jun 20243:45 pmRNSChief Executive Share Purchase
25th Jun 20249:48 amRNSUpdate on the Kallak Iron Ore Project
14th Jun 202410:40 amRNSResult of Annual General Meeting
10th Jun 20247:00 amRNSGraphite Anode Materials Plant update
3rd Jun 20247:00 amRNSGállok/ Kallak Iron Ore Project Update
29th May 20247:00 amRNSUnaudited Results for Period Ended 31 March 2024
20th May 20247:00 amRNSPosting of Annual Report and Notice of AGM
20th May 20247:00 amRNSFinancial Results for the year ended 31 Dec 2023
30th Apr 20247:00 amRNSTotal Voting Rights
25th Apr 202411:45 amRNSSP Angel Research Note
23rd Apr 20247:00 amRNSAlternative Resource Capital Research Note
18th Apr 20247:00 amRNSGrant of Options
11th Apr 20247:00 amRNSLast day of trading in Paid Subscribed SDRs
10th Apr 20247:00 amRNSIssue of SDRs to underwriters
9th Apr 20247:00 amRNSCompletion of Vardar Minerals Ltd Consolidation
3rd Apr 20247:00 amRNSBeowulf announces outcome of Capital Raise
26th Mar 20247:00 amRNSProspective Exploration Targets at Parkijaur nr 7
20th Mar 202410:05 amRNSCapital Raise Update
20th Mar 20249:43 amRNSCapital Raise Update
15th Mar 20247:00 amRNSUpdate on Consolidation of Vardar Minerals Limited
14th Mar 202410:30 amRNSPrimaryBid Offer
14th Mar 20247:06 amRNSSubscription period in Rights Issue of SDRs begins
13th Mar 20244:37 pmRNSPublication of Prospectus
12th Mar 20244:50 pmRNSPostponement of Subscription period
8th Mar 20242:10 pmRNSBörsveckan Presentation and Interview
7th Mar 20247:00 amRNSProject Director appointed for Kallak
5th Mar 20241:40 pmRNSResult of General Meeting
4th Mar 20247:00 amRNSBeowulf announces final terms for capital raise
4th Mar 20247:00 amRNSVardar Consolidation of Ownership and Update
29th Feb 20247:00 amRNSParkijaur nr 8 Exploration Permit Awarded
29th Feb 20247:00 amRNSUnaudited Preliminary Financial Results
19th Feb 20247:00 amRNSExtension of Site Reservation in GigaVaasa Area
16th Feb 20247:00 amRNSProposed fundraise and Notice of General Meeting
5th Feb 20247:00 amRNSProject Director appointed for Kallak

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.