Third Quarter 2018 Operations Update

10 Oct 2018 07:00

RNS Number : 4793D
Atalaya Mining PLC
10 October 2018
 

10 October 2018

Atalaya Mining Plc.

("Atalaya" or the "Company")

Third Quarter 2018 Operations Update

Increase in Full Year Guidance following record production

 

Atalaya Mining Plc. (AIM:ATYM, TSX:AYM) is pleased to announce its operations update for the third quarter of 2018.

 

PROYECTO RIOTINTO

 

Third quarter

Second quarter

Year-to-date

Updated full year guidance

2018

2017

2018

2018

Ore mined

(M tonnes)

2.8

2.4

2.6

7.9

9.7

Waste mined

(M tonnes)

3.2

5.2

4.8

13.4

16.5

Ore milled

(M tonnes)

2.5

2.2

2.5

7.2

9.6

Cu grade

(%)

0.50

0.58

0.48

0.49

0.48

Cu recovery

(%)

88.40

85.95

87.31

88.06

87 - 88

Cu production

(tonnes)

11,055

10,679

10,446

30,942

39,000 - 41,000

 

Copper production at Proyecto Riotinto for Q3 2018 has exceeded expectations, reaching a record 11,055 tonnes. This is the highest quarterly copper production since the project was re-started. The previous highest quarterly copper production was 10,679 tonnes, reported in Q3 2017. In addition, this is the second consecutive quarter where copper production has exceeded 10,000 tonnes.

 

In terms of ore milled, 2.5 million tonnes were processed in the quarter, reporting a consistent quarterly throughput. Copper head grade was slightly above plan. The increase in copper production during the quarter is mainly attributable to slightly higher than budgeted head grade, ore milled and better metallurgical recoveries, which averaged 88.40% during the quarter.

 

The Company is pleased to increase its previous 2018 production guidance from 37,000 - 40,000 tonnes to 39,000 - 41,000 tonnes of copper.

 

Mining operations are progressing to plan and at similar levels to previous quarters. On a combined basis, ore, waste and marginal ore amounted to 2.2 million m3 in Q3 2018 versus 2.6 million m3 in Q2 2018. Additional mining equipment is available on site in anticipation of the increase in production in 2019.

 

As part of the Company's continuous improvements programme, an additional secondary cone crusher, installed during the previous quarter, is now fully operational. Crushing capacity is no longer a bottleneck in the production process. A detailed analysis of the current screening section is now under way. Construction of the dome to cover the coarse ore stockpile has been put on hold due to re-engineering activities.

 

During the first week of August a wildfire broke out in close proximity to the north of Proyecto Riotinto which affected 1,600 ha of pine trees and eucalyptus. Although there was some damage to water pipelines at Proyecto Riotinto, production was minimally affected.

 

On-site concentrate inventories at the end of the quarter were approximately 2,725 tonnes. All concentrate in stock at the beginning of the quarter and produced during the quarter was delivered to the port at Huelva.

Copper prices decreased during the quarter compared with the previous quarter, with an average realised price per pound of copper payable, including the QPs closed in the period, of $2.89/lb compared with $3.12/lb in Q2 2018. The average copper spot price during the quarter was $2.77/lb. The realised price during the quarter excluding QPs was approximately $2.75/lb.

 

Cash operating costs for Q3 2018 are expected to be slightly lower than the 2018 cost guidance ranges previously provided. Further details on costs will be provided with the Q3 Financial Statements to be reported in November 2018.

 

Exploration is under way at the Atalaya pit where massive sulphides and stockwork mineralisation are targeted. The first 1,500 m of a 19,000 m drilling campaign of have already been drilled with positive preliminary results received. Drilling around the high grade underground workings in Filon Sur is also ongoing.

 

EXPANSION TO 15Mtpa AT PROYECTO RIOTINTO

 

The 15Mtpa expansion project is progressing according to schedule with engineering essentially complete and site construction activities picking up. Overall progress completion at the end of the reporting quarter was 65%. Procurement has progressed to 64% completed. Earthworks are almost completed with only minor final activities pending. Civil engineering works are progressing with main activities now concentrated on completion of the new SAG area and the crusher and coarse stockpile buildings. Structural steel works are well advanced in the flotation area. Piping is also close to completion in the concentrate handling area with electrical installation commencing. Installation of mechanical equipment is progressing in the concentrate handling area. The milling area is the critical path to completion. The expansion project is scheduled for mechanical completion at the end of Q2 2019.

 

PROYECTO TOURO

 

At the end of the reporting quarter, additional studies and detailed reports addressing certain project improvements and recommendations from the public hearing process were formally submitted to the authorities. This is the last step to complete the public hearing process initiated in August 2017.

 

An environmental monitoring programme similar to the programme carried out in Riotinto is fully implemented at Touro.

 

Alberto Lavandeira, CEO commented:

"We are delighted to report copper production at Proyecto Riotinto for Q3 2018, reaching a record 11,055 tonnes. This is the highest quarterly copper production since the project was re-started. Positively our production guidance for the year has also increased. The delivery of another consistent record quarter is testimony to the quality and commitment of the Company's teams and provides a good indication that the growth plans through the Riotinto expansion and Touro are solid and on track."

 

About Atalaya Mining Plc

Atalaya is an AIM and TSX-listed mining and development group. It produces copper concentrates and silver by-product at its wholly owned Proyecto Riotinto site in southwest Spain, which is also undergoing a brownfield expansion. In addition, the Group has a phased, earn-in agreement for up to 80% ownership of Proyecto Touro, a brownfield copper project in the northwest of Spain which is currently in the permitting stage. For further information, visit www.atalayamining.com

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) no 596/2014.

Contacts:

Newgate Communications

Elisabeth Cowell / Adam Lloyd / Tom Carnegie

+44 20 3757 6882

4C Communications

Carina Corbett

+44 20 3170 7973

Canaccord Genuity (NOMAD and Joint Broker)

Henry Fitzgerald-O'Connor / Martin Davison / James Asensio

+44 20 7523 8000

BMO Capital Markets (Joint Broker)

Jeffrey Couch / Tom Rider / Michael Rechsteiner

+44 20 7236 1010

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDQKLFBVBFLFBB
Date   Source Headline
13th Jan 20227:00 amRNSQ4 2021 Operations Update and 2022 Guidance
6th Jan 20227:00 amRNSAtalaya to Start Construction of an E-LIX Plant
21st Dec 20217:00 amRNSAcquisition and Additional Investigation Permits
17th Dec 202112:02 pmRNSIssue of Equity
22nd Nov 20217:00 amRNSDirector share sale and Director/PDMR Shareholding
19th Nov 20212:20 pmRNSHolding(s) in Company
18th Nov 20217:00 amRNSQ3 2021 Financial Results
16th Nov 20217:00 amRNSExchange Rate of Inaugural Dividend
4th Nov 20217:00 amRNSNotice of Q3 2021 Results & Investor Presentation
27th Oct 20217:00 amRNSApproval of inaugural dividend
13th Oct 20217:00 amRNSQ3 2021 Operations Update and Increase in Guidance
6th Oct 20217:00 amRNSProyecto Masa Valverde Exploration Update
20th Aug 20217:00 amRNSHolding(s) in Company
18th Aug 20212:45 pmRNSHolding(s) in Company
13th Aug 20214:01 pmRNSDirector share sale and Director/PDMR Shareholding
13th Aug 20214:00 pmRNSHolding(s) in Company
11th Aug 20217:00 amRNSQ2 and H1 2021 Interim Financial Statements
4th Aug 202110:30 amRNSHolding(s) in Company
3rd Aug 20217:00 amRNSNotice of Results and Investor Presentation
22nd Jul 202112:10 pmRNSHolding(s) in Company
13th Jul 20217:00 amRNSSecond Quarter 2021 Operations Update
5th Jul 20214:30 pmRNSDirector/PDMR Shareholding
1st Jul 20213:30 pmRNSDirector/PDMR Dealing
29th Jun 20217:00 amRNSDirector share sale and Director/PDMR Shareholding
25th Jun 202110:00 amRNSGranting of Share Options & Director/PDMR
25th Jun 20217:00 amRNSHolding(s) in Company
24th Jun 202112:35 pmRNSResult of AGM
24th Jun 20219:45 amRNSUpdate on Cerro Colorado Reserves (correction)
24th Jun 20217:00 amRNSUpdate on Cerro Colorado Reserves
24th Jun 20217:00 amRNS2021 Annual General Meeting Statement
3rd Jun 20214:35 pmRNSHolding(s) in Company
28th May 20217:00 amRNSNotice of AGM
25th May 20217:00 amRNSUpdate on Proyecto Riotinto East & Masa Valverde
19th May 20217:30 amRNSDirector/PDMR Shareholding
18th May 20217:47 amRNSDirector/PDMR Shareholding
18th May 20217:00 amRNSIssue of Equity
13th May 20217:00 amRNS1st Quarter Financial Results
14th Apr 20217:00 amRNSFirst Quarter 2021 Operations Update
12th Apr 20217:00 amRNSDirectorate Change
25th Mar 20217:00 amRNSDirectorate Change
25th Mar 20217:00 amRNSResults for the year ended 31 December 2020
16th Mar 20217:00 amRNSDirector share sale and Director/PDMR Shareholding
15th Mar 20211:31 pmRNSPayment of the Deferred Consideration to Astor
12th Feb 20217:00 amRNSIssue of Equity
10th Feb 20217:00 amRNSAppointment of Director
14th Jan 20217:00 amRNSQ4 2020 Operations Update and 2021 Guidance
17th Dec 20207:00 amRNSIssue of Equity
15th Dec 20205:10 pmRNSDirectorate Change
15th Dec 20207:00 amRNSHolding(s) in Company
26th Nov 20207:00 amRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.