Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAtalaya Mining Regulatory News (ATYM)

Share Price Information for Atalaya Mining (ATYM)

Share Price is delayed by 15 minutes
Get Live Data
892.00    3.00 (0.34%)
Bid:
888.00
Ask:
891.50
Spread: 3.50 (0.394%)
Market Cap: £1.37b
ATYM Live PriceLast checked at - London Stock Exchange

Intraday Atalaya Mining Share Chart

Second Quarter 2021 Operations Update

13 Jul 2021 07:00

RNS Number : 9907E
Atalaya Mining PLC
13 July 2021
 

13 July 2021

Atalaya Mining Plc.

("Atalaya" or the "Company")

Second Quarter 2021 Operations Update

 

Atalaya Mining Plc (AIM:ATYM, TSX:AYM) is pleased to announce its operations update for the second quarter of 2021 ("Q2 2021" or the "Period").

Proyecto Riotinto Operating Highlights

Q2

Q1

Full year

2021

2020

2021

2021 Guidance

Ore mined

(M tonnes)

3.3

3.2

3.3

15.1

Waste mined

(M tonnes)

8.0

5.7

7.4

25.9

Ore milled

(M tonnes)

4.0

3.6

4.0

15.0 - 15.5

Cu grade

(%)

0.42

0.44

0.41

0.42

Cu recovery

(%)

84.83

85.89

84.90

82 - 84

Cu production

(tonnes)

14,353

13,635

13,979

52,000 - 54,000

 

· Copper production in Q2 2021 was 14,353 tonnes, 2.7 % higher than Q1 2021 and 5.3 % higher than Q2 2020.

· The plant processed 4.03 million tonnes of ore during Q2 2021 equivalent to a throughput rate of approximately 16 Mtpa. Low grade stockpiles added extra tonnage.

· The increase in copper production, when compared with the Company's guidance, is mainly attributable to higher throughput and, to a lesser extent, to better recoveries than planned.

· Despite ongoing COVID-19 restrictions, mining operations have continued normally with higher production levels compared with previous quarters.

· On-site copper concentrate inventories at the end of Q2 2021 were approximately 15,103 tonnes. All concentrate in stock at the beginning of the Period was delivered to the port at Huelva.

· Copper prices increased during the Period compared with the previous quarter. Average spot prices increased from US$3.85/lb in Q1 2021 to US$4.40/lb in Q2 2021. The average realised price per pound of copper payable was $ 4.27 /lb compared with $ 3.62 /lb in the previous quarter. The realised price during Q2 2021 excluding QPs was approximately $ 4.40 /lb.

· Cash operating costs for the Period are expected to be below full year 2021 cost guidance owing mainly to the Euro/U.S. dollar exchange rate of 1.2058 compared with 1.22 budgeted by the Company in its 2021 guidance, together with higher copper production and better recoveries. Further details on costs will be provided with the Q2 Financial Statements due to be reported in August.

Proyecto Riotinto Optimisation

· During Q2 2021 some cost reduction initiatives were implemented such as the commissioning of a tailings thickener and changes to the lime circuit, both of which resulted in lower lime and energy consumption as well as a reduction in CO2 emissions.

· Permitting of a 50 Mw solar plant for self-consumption advanced significantly and final construction permits are expected imminently.

· New initiative focused on increased recoveries using different grinding media in the regrind mill.

 

Reserves and Resources Updates at Proyecto Riotinto

· Following an independent reserve estimate which confirmed the status of a long life at the Cerro Colorado open pit, studies have advanced around the addition of further resources at Proyecto Riotinto.

· A sizeable resource has been identified at San Dionisio deposit that is potentially mineable by open pit. Further polymetallic mineralization could be exploited using underground mining methods at the San Antonio and San Dionisio deposits.

· Work has started on the preparation of an NI 43-101 compliant technical report which will be followed by PEA or PFS studies.

Outlook for 2021

· The Company maintains its 2021 guidance but now expects to be towards the high end of production guidance and the lower end of costs guidance.

Growth Projects

Proyecto Touro

· The Company is finalising a new project to be presented to the Xunta de Galicia during Q3 2021. The new project for Touro includes a new design to address and resolve all the concerns previously raised by stakeholders during the Environmental Impact Evaluation Assessment.

· The Company continues to be confident that its approach to Proyecto Touro is in line with international best practice and includes fully plastic lined tailings with zero discharge which will satisfy the most stringent environmental conditions that may be imposed by the authorities prior to development of the project.

Proyecto Masa Valverde

· Exploration at Masa Valverde has started with ground geophysics and two rigs currently drilling around the new Majadales and the historic Masa Valverde deposits.

· NI 43-101 compliant resource estimates have been started for these two properties.

Proyecto Riotinto Este

· The Los Herreros investigation permit was granted in May and the Company now has access to two of the three investigation permits at Riotinto Este, Cerro Negro and Los Herreros. The third investigation permit, Peñas Blancas, is expected to be granted in the coming months.

· A proposal and quotes for an electromagnetic airborne geophysics survey covering Cerro Negro and Peñas Blancas investigation permits at Riotinto Este have been requested from three geophysical operators and the Company will provide a further update on activity for this area in due course.

 

 

E-LIX Update

· A feasibility study continues for an industrial plant using the third party-patented E-LIX System followed by conventional SX-EW to produce cathodes on site. Results of the feasibility study are expected in Q3 2021.

· The E-LIX pilot plant is fully operational and continues gathering real data to be incorporated in the copper and zinc concentrates leaching section of the feasibility studies.

· The work at the pilot plant continues to support the viability of the E-LIX system and further details will be provided in due course.

Astor Update

· As previously announced by the Company, the hearing of the summary Judgment application took place on 14th and 15th June 2021. The application for the summary Judgment was based on evidence given in a witness statement by Astor's Chief Executive, Ashwath Mehra.

· The Court dismissed Astor's application and the question as to whether any residual interest is payable to Astor therefore remains to be resolved at trial. Astor is required to pay Atalaya's costs of the application (the fourth time Astor has been ordered to pay costs in this long-running case).

· Trial will take place in February 2022 and Atalaya continues to be confident in its case, reinforced by this judgment in which the Judge concluded by saying, "it is obvious from what I have said in this judgment that I expect Astor's case to fail at trial and they will no doubt consider carefully whether they wish to pursue this case to trial".

 

Alberto Lavandeira, CEO commented:

"Our mining operations continue to perform strongly with higher production levels compared with previous quarters. Adding to this continued robust performance, our team continues to focus on delivering new efficiencies and growth projects, which includes cost reduction initiatives at Proyecto Riotinto and additional exploration across prospective landholdings to create shareholder value.

"The Company maintains its 2021 guidance but now expects to be towards the high end of production guidance and the lower end of costs guidance."

 

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) no 596/2014.

Contacts:

SEC Newgate UK

Elisabeth Cowell / Adam Lloyd / Tom Carnegie

+ 44 20 3757 6880

4C Communications

Carina Corbett

+44 20 3170 7973

Canaccord Genuity

(NOMAD and Joint Broker)

Henry Fitzgerald-O'Connor / James Asensio

+44 20 7523 8000

BMO Capital Markets

(Joint Broker)

Tom Rider / Andrew Cameron

+44 20 7236 1010

Peel Hunt LLP

(Joint Broker)

Ross Allister / David McKeown

+44 20 7418 8900

 

About Atalaya Mining Plc

Atalaya is an AIM and TSX-listed mining and development group which produces copper concentrates and silver by-product at its wholly owned Proyecto Riotinto site in southwest Spain. Atalaya's current operations include the Cerro Colorado open pit mine and a modern 15 Mtpa processing plant, which has the potential to become a centralised processing hub for ore sourced from its wholly owned regional projects around Riotinto that include Proyecto Masa Valverde and Proyecto Riotinto East. In addition, the Group has a phased, earn-in agreement for up to 80% ownership of Proyecto Touro, a brownfield copper project in the northwest of Spain. For further information, visit www.atalayamining.com

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDBRGDRLBBDGBD
Date   Source Headline
26th May 20267:00 amRNSQ1 2026 Financial Results
21st May 20267:00 amRNSNotice of AGM
13th May 20267:00 amRNSNotice of Results
28th Apr 20267:01 amRNSGrant of Conditional Share Awards
28th Apr 20267:00 amRNSPublication of 2025 Annual Reporting Documents
16th Apr 20265:04 pmRNSTR-1
14th Apr 20267:00 amRNSQ1 2026 Operations Update
10th Apr 202611:46 amRNSHolding(s) in Company
2nd Apr 20267:00 amRNSInvestment in Lara Exploration Ltd.
19th Mar 20267:00 amRNS2025 Annual Results
5th Mar 20267:00 amRNSNotice of 2025 Annual Results
9th Feb 20267:00 amRNSTR1 Notification of Major Holdings
4th Feb 20267:00 amRNSResults of placing in Atalaya Mining Copper, S.A.
3rd Feb 20264:45 pmRNSProposed placing - in Atalaya Mining Copper, S.A.
28th Jan 20267:00 amRNSSuccessful Fundraise
27th Jan 20264:39 pmRNSRetail Offer by RetailBook
27th Jan 20264:38 pmRNSProposed Fundraise to Accelerate Copper Project
14th Jan 20267:00 amRNSQ4 Operations Update and 2026 Production Guidance
9th Jan 202612:21 pmRNSHolding(s) in Company
30th Dec 20257:00 amRNSDirectorate Change
30th Dec 20257:00 amRNSDirectorate Change
19th Dec 20257:00 amRNSStatement Regarding Shareholder Consultation
19th Dec 20257:00 amRNSStatement Regarding Shareholder Consultation
10th Dec 20257:00 amRNSHolding(s) in Company
13th Nov 20257:00 amRNSQ3 and YTD 2025 Financial Results
30th Oct 20257:00 amRNSNotice of Q3 and YTD 2025 Financial Results
21st Oct 20257:00 amRNSQ3 2025 Operations Update
3rd Oct 202510:33 amRNSHolding(s) in Company
1st Oct 20259:35 amRNSHolding(s) in Company
30th Sep 20257:01 amRNSDirector/PDMR Shareholding
30th Sep 20257:00 amRNSHolding(s) in Company
18th Sep 20257:00 amRNSPDMR Share Dealings
17th Sep 20257:00 amRNSNotice for Holders of Physical Share Certificates
10th Sep 20257:00 amRNSResult of Secondary Placing
9th Sep 20254:43 pmRNSProposed placing in Atalaya Mining Copper, S.A.
12th Aug 20257:00 amRNSQ2 and H1 2025 Financial Results
23rd Jul 20257:00 amRNSNotice of Q2 and H1 2025 Financial Results
15th Jul 20257:00 amRNSQ2 2025 Operations Update
10th Jul 20257:01 amRNSMasa Valverde Drilling Update
10th Jul 20257:00 amRNSDirector/PDMR Shareholding
24th Jun 202511:59 amRNSBoard Committee Updates
24th Jun 202511:29 amRNSAGM 2025 – Voting Results
20th Jun 20257:00 amRNSAppointment of Director
4th Jun 20253:48 pmRNSDirector Declaration
2nd Jun 20257:00 amRNSFinal Dividend Timetable & Updated AGM Resolution
29th May 20257:00 amRNSQ1 2025 Financial Results
21st May 20257:00 amRNSNotice of Q1 2025 Financial Results
15th May 20257:00 amRNSSan Dionisio Granted Environmental Authorisation
14th May 20257:00 amRNSNotice of Annual General Meeting
2nd May 20257:00 amRNSFTSE 250 Index Inclusion

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.