Second Quarter 2021 Operations Update

13 Jul 2021 07:00

RNS Number : 9907E
Atalaya Mining PLC
13 July 2021
 

13 July 2021

Atalaya Mining Plc.

("Atalaya" or the "Company")

Second Quarter 2021 Operations Update

 

Atalaya Mining Plc (AIM:ATYM, TSX:AYM) is pleased to announce its operations update for the second quarter of 2021 ("Q2 2021" or the "Period").

Proyecto Riotinto Operating Highlights

Q2

Q1

Full year

2021

2020

2021

2021 Guidance

Ore mined

(M tonnes)

3.3

3.2

3.3

15.1

Waste mined

(M tonnes)

8.0

5.7

7.4

25.9

Ore milled

(M tonnes)

4.0

3.6

4.0

15.0 - 15.5

Cu grade

(%)

0.42

0.44

0.41

0.42

Cu recovery

(%)

84.83

85.89

84.90

82 - 84

Cu production

(tonnes)

14,353

13,635

13,979

52,000 - 54,000

 

· Copper production in Q2 2021 was 14,353 tonnes, 2.7 % higher than Q1 2021 and 5.3 % higher than Q2 2020.

· The plant processed 4.03 million tonnes of ore during Q2 2021 equivalent to a throughput rate of approximately 16 Mtpa. Low grade stockpiles added extra tonnage.

· The increase in copper production, when compared with the Company's guidance, is mainly attributable to higher throughput and, to a lesser extent, to better recoveries than planned.

· Despite ongoing COVID-19 restrictions, mining operations have continued normally with higher production levels compared with previous quarters.

· On-site copper concentrate inventories at the end of Q2 2021 were approximately 15,103 tonnes. All concentrate in stock at the beginning of the Period was delivered to the port at Huelva.

· Copper prices increased during the Period compared with the previous quarter. Average spot prices increased from US$3.85/lb in Q1 2021 to US$4.40/lb in Q2 2021. The average realised price per pound of copper payable was $ 4.27 /lb compared with $ 3.62 /lb in the previous quarter. The realised price during Q2 2021 excluding QPs was approximately $ 4.40 /lb.

· Cash operating costs for the Period are expected to be below full year 2021 cost guidance owing mainly to the Euro/U.S. dollar exchange rate of 1.2058 compared with 1.22 budgeted by the Company in its 2021 guidance, together with higher copper production and better recoveries. Further details on costs will be provided with the Q2 Financial Statements due to be reported in August.

Proyecto Riotinto Optimisation

· During Q2 2021 some cost reduction initiatives were implemented such as the commissioning of a tailings thickener and changes to the lime circuit, both of which resulted in lower lime and energy consumption as well as a reduction in CO2 emissions.

· Permitting of a 50 Mw solar plant for self-consumption advanced significantly and final construction permits are expected imminently.

· New initiative focused on increased recoveries using different grinding media in the regrind mill.

 

Reserves and Resources Updates at Proyecto Riotinto

· Following an independent reserve estimate which confirmed the status of a long life at the Cerro Colorado open pit, studies have advanced around the addition of further resources at Proyecto Riotinto.

· A sizeable resource has been identified at San Dionisio deposit that is potentially mineable by open pit. Further polymetallic mineralization could be exploited using underground mining methods at the San Antonio and San Dionisio deposits.

· Work has started on the preparation of an NI 43-101 compliant technical report which will be followed by PEA or PFS studies.

Outlook for 2021

· The Company maintains its 2021 guidance but now expects to be towards the high end of production guidance and the lower end of costs guidance.

Growth Projects

Proyecto Touro

· The Company is finalising a new project to be presented to the Xunta de Galicia during Q3 2021. The new project for Touro includes a new design to address and resolve all the concerns previously raised by stakeholders during the Environmental Impact Evaluation Assessment.

· The Company continues to be confident that its approach to Proyecto Touro is in line with international best practice and includes fully plastic lined tailings with zero discharge which will satisfy the most stringent environmental conditions that may be imposed by the authorities prior to development of the project.

Proyecto Masa Valverde

· Exploration at Masa Valverde has started with ground geophysics and two rigs currently drilling around the new Majadales and the historic Masa Valverde deposits.

· NI 43-101 compliant resource estimates have been started for these two properties.

Proyecto Riotinto Este

· The Los Herreros investigation permit was granted in May and the Company now has access to two of the three investigation permits at Riotinto Este, Cerro Negro and Los Herreros. The third investigation permit, Peñas Blancas, is expected to be granted in the coming months.

· A proposal and quotes for an electromagnetic airborne geophysics survey covering Cerro Negro and Peñas Blancas investigation permits at Riotinto Este have been requested from three geophysical operators and the Company will provide a further update on activity for this area in due course.

 

 

E-LIX Update

· A feasibility study continues for an industrial plant using the third party-patented E-LIX System followed by conventional SX-EW to produce cathodes on site. Results of the feasibility study are expected in Q3 2021.

· The E-LIX pilot plant is fully operational and continues gathering real data to be incorporated in the copper and zinc concentrates leaching section of the feasibility studies.

· The work at the pilot plant continues to support the viability of the E-LIX system and further details will be provided in due course.

Astor Update

· As previously announced by the Company, the hearing of the summary Judgment application took place on 14th and 15th June 2021. The application for the summary Judgment was based on evidence given in a witness statement by Astor's Chief Executive, Ashwath Mehra.

· The Court dismissed Astor's application and the question as to whether any residual interest is payable to Astor therefore remains to be resolved at trial. Astor is required to pay Atalaya's costs of the application (the fourth time Astor has been ordered to pay costs in this long-running case).

· Trial will take place in February 2022 and Atalaya continues to be confident in its case, reinforced by this judgment in which the Judge concluded by saying, "it is obvious from what I have said in this judgment that I expect Astor's case to fail at trial and they will no doubt consider carefully whether they wish to pursue this case to trial".

 

Alberto Lavandeira, CEO commented:

"Our mining operations continue to perform strongly with higher production levels compared with previous quarters. Adding to this continued robust performance, our team continues to focus on delivering new efficiencies and growth projects, which includes cost reduction initiatives at Proyecto Riotinto and additional exploration across prospective landholdings to create shareholder value.

"The Company maintains its 2021 guidance but now expects to be towards the high end of production guidance and the lower end of costs guidance."

 

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) no 596/2014.

Contacts:

SEC Newgate UK

Elisabeth Cowell / Adam Lloyd / Tom Carnegie

+ 44 20 3757 6880

4C Communications

Carina Corbett

+44 20 3170 7973

Canaccord Genuity

(NOMAD and Joint Broker)

Henry Fitzgerald-O'Connor / James Asensio

+44 20 7523 8000

BMO Capital Markets

(Joint Broker)

Tom Rider / Andrew Cameron

+44 20 7236 1010

Peel Hunt LLP

(Joint Broker)

Ross Allister / David McKeown

+44 20 7418 8900

 

About Atalaya Mining Plc

Atalaya is an AIM and TSX-listed mining and development group which produces copper concentrates and silver by-product at its wholly owned Proyecto Riotinto site in southwest Spain. Atalaya's current operations include the Cerro Colorado open pit mine and a modern 15 Mtpa processing plant, which has the potential to become a centralised processing hub for ore sourced from its wholly owned regional projects around Riotinto that include Proyecto Masa Valverde and Proyecto Riotinto East. In addition, the Group has a phased, earn-in agreement for up to 80% ownership of Proyecto Touro, a brownfield copper project in the northwest of Spain. For further information, visit www.atalayamining.com

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDBRGDRLBBDGBD
Date   Source Headline
11th Nov 20227:00 amRNSHolding(s) in Company
9th Nov 20222:40 pmRNSPDMR Share Dealing
9th Nov 20227:00 amRNSQ3 and YTD 2022 Financial Results
1st Nov 20227:00 amRNSEstablishment of Sustainability Committee
25th Oct 20227:00 amRNSNotice of Q3 2022 Results
17th Oct 20227:00 amRNSQ3 2022 Operations Upate
17th Oct 20227:00 amRNSQ3 2022 Operations Update
14th Oct 202212:43 pmRNSHolding(s) in Company
5th Oct 20227:00 amRNSFiling of Proyecto Riotinto Technical Report
29th Sep 20227:00 amRNSHolding(s) in Company
13th Sep 20227:00 amRNSChange in Dividend Payment Date
6th Sep 20227:00 amRNSInterim Dividend Foreign Exchange Rates andPayment
25th Aug 202210:45 amRNSDirector/PDMR Shareholding
23rd Aug 202211:54 amRNSHolding(s) in Company
10th Aug 20227:00 amRNSQ2 and H1 2022 Financial Results
18th Jul 20227:00 amRNSNotice of Q2 2022 and Interim Results
14th Jul 202211:06 amRNSSecond Price Monitoring Extn
14th Jul 202211:00 amRNSPrice Monitoring Extension
14th Jul 20227:00 amRNSQ2 2022 Operations Update
5th Jul 20227:00 amRNSPositive Drilling Results from Campanario Trend
24th Jun 20227:00 amRNSGrant of Share Options and PDMR Shareholding
23rd Jun 202212:15 pmRNS2022.06.23 - ATYM RNS - Options Executed
22nd Jun 202212:55 pmRNSResults of the 2022 Annual General Meeting
22nd Jun 20227:00 amRNS2022 Annual General Meeting Statement
26th May 20227:00 amRNSNotice of Annual General Meeting
20th May 20227:20 amRNSPDMR Share Purchase and Shareholding
19th May 20227:00 amRNSQ1 2022 Financial Results
18th May 20224:11 pmRNSAppointment of Director
18th May 20227:00 amRNSFiling of Proyecto Masa Valverde Technical Report
11th May 20227:00 amRNSNotice of Unaudited Q1 2022 Results
3rd May 20225:15 pmRNSHolding(s) in Company
27th Apr 20227:00 amRNSPublication of Site Visit Presentation
25th Apr 20227:00 amRNSPublication of Inaugural Sustainability Report
13th Apr 20227:00 amRNSNew Resource Estimates: San Dionisio & San Antonio
13th Apr 20227:00 amRNSFirst Quarter 2022 Operations Update
7th Apr 20227:00 amRNSShareholder Update
6th Apr 20228:07 amRNSHolding(s) in Company
5th Apr 20222:00 pmRNSHolding(s) in Company
5th Apr 20227:00 amRNSIncrease in Mineral Resources at Masa Valverde
1st Apr 20229:05 amRNSSecond Price Monitoring Extn
1st Apr 20229:00 amRNSPrice Monitoring Extension
31st Mar 20224:48 pmRNSProposed placing in Atalaya Mining Plc
24th Mar 20222:16 pmRNSDirectorate Change
24th Mar 20227:00 amRNSAudited Full Year Results 2021
21st Mar 202211:50 amRNSConclusion of Astor Management AG litigation
22nd Feb 20227:00 amRNSDirector/PDMR Shareholding
3rd Feb 20227:00 amRNSBest copper intercept to date at Masa Valverde
27th Jan 20227:00 amRNSGranting of share options and PDMR Notification
26th Jan 20227:00 amRNSIssue of Equity
25th Jan 20227:00 amRNSSummary re. Approach to Sustainability

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.