Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAtalaya Mining Regulatory News (ATYM)

Share Price Information for Atalaya Mining (ATYM)

Share Price is delayed by 15 minutes
Get Live Data
889.00    0.00 (0.00%)
Bid:
0.00
Ask:
0.00
Spread: 1.50 (0.169%)
Market Cap: £1.37b
ATYM Live PriceLast checked at - London Stock Exchange

Intraday Atalaya Mining Share Chart

Operations Update

25 Jul 2016 07:00

RNS Number : 0587F
Atalaya Mining PLC
25 July 2016
 

 

Atalaya Mining plc ("Atalaya" or the "Company")

(AIM: ATYM, TSX: AYM)

Second Quarter 2016 Operational Update

Expansion Project Completed Ahead of Schedule and Under Budget

 

Atalaya is pleased to report the successful completion of the construction of its Expansion Project, with production ramping up towards 9.5Mtpa. The Company is also providing an operations update for Q2 2016.

Q2 2016 Highlights

· The Expansion Project was declared mechanically complete during the first week of May 2016, ahead of schedule and under budget.

· Copper production increased by 10% in Q2 2016 to 4,442 tonnes, compared with 4,048 tonnes in Q1 2016. The increase in production was significant considering the plant was temporarily shut down due to the administrative tailings discharge suspension and interruptions required to commission the Expansion.

· 1.3m tonnes of ore were processed compared with 1.1m tonnes during Q1 2016, representing a 15% increase.

· Copper grade in final concentrate remained consistent at 21.54% while recoveries decreased to 79.80% due to the commissioning of the new flotation circuit. Recoveries have now reverted to normal and averaged over 84% in July.

· Updated Reserves and Resources statement released following the end of Q2 2016, indicating a 12% increase in contained reserves and extended life of mine to 16.5 years.

Expansion Project

During the first week of May 2016, the Expansion Project was declared mechanically complete, ahead of schedule and under budget. Commissioning of the new equipment and subsequent handover to the operations team took place during the latter part of the quarter. Production levels increased to an annualized rate of 6.8Mtpa in June, in line with the ramp-up schedule. This trend has continued and the annualised rate achieved during July is equivalent to 7.7 Mtpa.

Phase 1 of the plant ramp-up was performing well at the start of the quarter before operations were temporarily suspended by the Junta de Andalucía (see announcement dated 22 April 2016). During the suspension period, which was lifted on 4 May 2016, the site team integrated the new Expansion equipment into the existing Phase 1 section, which then allowed commissioning and ramp-up to move continuously through May.

Mining and Processing

Copper production increased by 10% during Q2 2016 to a total of 4,442 tonnes compared with 4,048 tonnes during Q1 2016. The increase was adversely impacted by the temporary operational suspension due to the tailings discharge issue as well as the interruptions required to connect the Expansion of the plant to the Phase 1 Project.

Copper grade in the final concentrate was consistent with the previous quarter, reporting 21.54% in Q2 2016 versus 21.33% for Q1 2016. Recoveries were lower at 79.80% during Q2 2016, compared with 82.93% during Q1 2016. This was mainly attributable to the commissioning of the new flotation circuit. Recoveries are now back to normal and averaging over 84% during July.

A total of 1,308,641 tonnes of ore was processed during Q2 2016, compared with 1,133,948 tonnes during Q1 2016, representing a 15% increase. 

Ore extraction during Q2 2016 totalled 1,254,323 tonnes compared with 1,188,953 tonnes during Q1 2016. Marginal ore extracted was 177,495 tonnes compared with 144,459 tonnes during Q1 2016. A total of 1,343,400 cubic metres of waste was removed during Q2 2016 compared with 935,452 cubic metres during Q1 2016.

The Company anticipates continued ramp-up to nameplate capacity throughout the rest of the year.

Exploration and Geology

Following the end of Q2 2016, a Reserves and Resources statement was released on 14 July 2016. Total open-pit mineral reserves have increased from 123Mt at 0.49% Cu to 153 million tonnes averaging 0.45% Cu using variable, declining cut-off grades, representing a 12% increase in contained metal.

Total open-pit Measured and Indicated Mineral Resources were estimated at 193 million tonnes averaging 0.43% Cu, compared with the previous estimate of 203 million tonnes at 0.46% Cu. Inferred Mineral Resources increased to 23 million tonnes averaging 0.48% Cu, from 2 million tonnes at 0.50% Cu.

An exploration drilling campaign has been initiated during the quarter to evaluate historical mineral resources around both the Corta Atalaya and Filon Sur pits.

Financial

Information on sales and operating costs will be provided in the Q2 2016 Financial Statements due out in early September 2016.

As previously announced, the Company continues to evaluate a number of funding options to address its short term working capital needs, to support the Company through the ramp up phase.

Corporate

Following the end of Q2 2016, Cesar Sanchez was appointed Group Chief Financial Officer (see announcement 7 July 2016). In addition, the Company appointed BMO Capital Markets Limited as joint corporate broker.

Astor update

Following the announcements on 2 November 2015 and 26 May 2016, the Company continues to work closely with its legal advisors in preparing for trial at the High Court of Justice in London. The date for the trial has been set for 30 January 2017.

The Company remains confident of a positive outcome of the upcoming trial and will update shareholders following the trial, or if there are any material developments in the meantime.

Alberto Lavandeira, CEO, commented:

"The progress that has been made by our team in moving the plant closer to nameplate capacity ahead of schedule and under budget is impressive. When we factor in the improved knowledge of the orebody gained from our recent Reserves and Resources update which has extended the life of mine, increased mineable reserves and will lead to greater efficiencies, it confirms our belief that Proyecto Riotinto has a viable future for many years to come".

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) No 596/2014.

 

Contacts:

Atalaya Mining plc

Roger Davey / Alberto Lavandeira

+34 959 59 28 50

Canaccord Genuity (NOMAD and Joint Broker)

Henry Fitzgerald-O'Connor / Martin Davison

+44 20 7523 8000

BMO Capital Markets (Joint Broker)

Jeffrey Couch/Neil Haycock/Tom Rider

+44 20 7236 1010

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDKZLFLQDFZBBB
Date   Source Headline
26th May 20267:00 amRNSQ1 2026 Financial Results
21st May 20267:00 amRNSNotice of AGM
13th May 20267:00 amRNSNotice of Results
28th Apr 20267:01 amRNSGrant of Conditional Share Awards
28th Apr 20267:00 amRNSPublication of 2025 Annual Reporting Documents
16th Apr 20265:04 pmRNSTR-1
14th Apr 20267:00 amRNSQ1 2026 Operations Update
10th Apr 202611:46 amRNSHolding(s) in Company
2nd Apr 20267:00 amRNSInvestment in Lara Exploration Ltd.
19th Mar 20267:00 amRNS2025 Annual Results
5th Mar 20267:00 amRNSNotice of 2025 Annual Results
9th Feb 20267:00 amRNSTR1 Notification of Major Holdings
4th Feb 20267:00 amRNSResults of placing in Atalaya Mining Copper, S.A.
3rd Feb 20264:45 pmRNSProposed placing - in Atalaya Mining Copper, S.A.
28th Jan 20267:00 amRNSSuccessful Fundraise
27th Jan 20264:39 pmRNSRetail Offer by RetailBook
27th Jan 20264:38 pmRNSProposed Fundraise to Accelerate Copper Project
14th Jan 20267:00 amRNSQ4 Operations Update and 2026 Production Guidance
9th Jan 202612:21 pmRNSHolding(s) in Company
30th Dec 20257:00 amRNSDirectorate Change
30th Dec 20257:00 amRNSDirectorate Change
19th Dec 20257:00 amRNSStatement Regarding Shareholder Consultation
19th Dec 20257:00 amRNSStatement Regarding Shareholder Consultation
10th Dec 20257:00 amRNSHolding(s) in Company
13th Nov 20257:00 amRNSQ3 and YTD 2025 Financial Results
30th Oct 20257:00 amRNSNotice of Q3 and YTD 2025 Financial Results
21st Oct 20257:00 amRNSQ3 2025 Operations Update
3rd Oct 202510:33 amRNSHolding(s) in Company
1st Oct 20259:35 amRNSHolding(s) in Company
30th Sep 20257:01 amRNSDirector/PDMR Shareholding
30th Sep 20257:00 amRNSHolding(s) in Company
18th Sep 20257:00 amRNSPDMR Share Dealings
17th Sep 20257:00 amRNSNotice for Holders of Physical Share Certificates
10th Sep 20257:00 amRNSResult of Secondary Placing
9th Sep 20254:43 pmRNSProposed placing in Atalaya Mining Copper, S.A.
12th Aug 20257:00 amRNSQ2 and H1 2025 Financial Results
23rd Jul 20257:00 amRNSNotice of Q2 and H1 2025 Financial Results
15th Jul 20257:00 amRNSQ2 2025 Operations Update
10th Jul 20257:01 amRNSMasa Valverde Drilling Update
10th Jul 20257:00 amRNSDirector/PDMR Shareholding
24th Jun 202511:59 amRNSBoard Committee Updates
24th Jun 202511:29 amRNSAGM 2025 – Voting Results
20th Jun 20257:00 amRNSAppointment of Director
4th Jun 20253:48 pmRNSDirector Declaration
2nd Jun 20257:00 amRNSFinal Dividend Timetable & Updated AGM Resolution
29th May 20257:00 amRNSQ1 2025 Financial Results
21st May 20257:00 amRNSNotice of Q1 2025 Financial Results
15th May 20257:00 amRNSSan Dionisio Granted Environmental Authorisation
14th May 20257:00 amRNSNotice of Annual General Meeting
2nd May 20257:00 amRNSFTSE 250 Index Inclusion

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.