Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAtalaya Mining Regulatory News (ATYM)

Share Price Information for Atalaya Mining (ATYM)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 418.50
Bid: 417.00
Ask: 420.50
Change: 1.50 (0.36%)
Spread: 3.50 (0.839%)
Open: 417.50
High: 422.50
Low: 416.50
Prev. Close: 417.00
ATYM Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Operations Update

25 Jul 2016 07:00

RNS Number : 0587F
Atalaya Mining PLC
25 July 2016
 

 

Atalaya Mining plc ("Atalaya" or the "Company")

(AIM: ATYM, TSX: AYM)

Second Quarter 2016 Operational Update

Expansion Project Completed Ahead of Schedule and Under Budget

 

Atalaya is pleased to report the successful completion of the construction of its Expansion Project, with production ramping up towards 9.5Mtpa. The Company is also providing an operations update for Q2 2016.

Q2 2016 Highlights

· The Expansion Project was declared mechanically complete during the first week of May 2016, ahead of schedule and under budget.

· Copper production increased by 10% in Q2 2016 to 4,442 tonnes, compared with 4,048 tonnes in Q1 2016. The increase in production was significant considering the plant was temporarily shut down due to the administrative tailings discharge suspension and interruptions required to commission the Expansion.

· 1.3m tonnes of ore were processed compared with 1.1m tonnes during Q1 2016, representing a 15% increase.

· Copper grade in final concentrate remained consistent at 21.54% while recoveries decreased to 79.80% due to the commissioning of the new flotation circuit. Recoveries have now reverted to normal and averaged over 84% in July.

· Updated Reserves and Resources statement released following the end of Q2 2016, indicating a 12% increase in contained reserves and extended life of mine to 16.5 years.

Expansion Project

During the first week of May 2016, the Expansion Project was declared mechanically complete, ahead of schedule and under budget. Commissioning of the new equipment and subsequent handover to the operations team took place during the latter part of the quarter. Production levels increased to an annualized rate of 6.8Mtpa in June, in line with the ramp-up schedule. This trend has continued and the annualised rate achieved during July is equivalent to 7.7 Mtpa.

Phase 1 of the plant ramp-up was performing well at the start of the quarter before operations were temporarily suspended by the Junta de Andalucía (see announcement dated 22 April 2016). During the suspension period, which was lifted on 4 May 2016, the site team integrated the new Expansion equipment into the existing Phase 1 section, which then allowed commissioning and ramp-up to move continuously through May.

Mining and Processing

Copper production increased by 10% during Q2 2016 to a total of 4,442 tonnes compared with 4,048 tonnes during Q1 2016. The increase was adversely impacted by the temporary operational suspension due to the tailings discharge issue as well as the interruptions required to connect the Expansion of the plant to the Phase 1 Project.

Copper grade in the final concentrate was consistent with the previous quarter, reporting 21.54% in Q2 2016 versus 21.33% for Q1 2016. Recoveries were lower at 79.80% during Q2 2016, compared with 82.93% during Q1 2016. This was mainly attributable to the commissioning of the new flotation circuit. Recoveries are now back to normal and averaging over 84% during July.

A total of 1,308,641 tonnes of ore was processed during Q2 2016, compared with 1,133,948 tonnes during Q1 2016, representing a 15% increase. 

Ore extraction during Q2 2016 totalled 1,254,323 tonnes compared with 1,188,953 tonnes during Q1 2016. Marginal ore extracted was 177,495 tonnes compared with 144,459 tonnes during Q1 2016. A total of 1,343,400 cubic metres of waste was removed during Q2 2016 compared with 935,452 cubic metres during Q1 2016.

The Company anticipates continued ramp-up to nameplate capacity throughout the rest of the year.

Exploration and Geology

Following the end of Q2 2016, a Reserves and Resources statement was released on 14 July 2016. Total open-pit mineral reserves have increased from 123Mt at 0.49% Cu to 153 million tonnes averaging 0.45% Cu using variable, declining cut-off grades, representing a 12% increase in contained metal.

Total open-pit Measured and Indicated Mineral Resources were estimated at 193 million tonnes averaging 0.43% Cu, compared with the previous estimate of 203 million tonnes at 0.46% Cu. Inferred Mineral Resources increased to 23 million tonnes averaging 0.48% Cu, from 2 million tonnes at 0.50% Cu.

An exploration drilling campaign has been initiated during the quarter to evaluate historical mineral resources around both the Corta Atalaya and Filon Sur pits.

Financial

Information on sales and operating costs will be provided in the Q2 2016 Financial Statements due out in early September 2016.

As previously announced, the Company continues to evaluate a number of funding options to address its short term working capital needs, to support the Company through the ramp up phase.

Corporate

Following the end of Q2 2016, Cesar Sanchez was appointed Group Chief Financial Officer (see announcement 7 July 2016). In addition, the Company appointed BMO Capital Markets Limited as joint corporate broker.

Astor update

Following the announcements on 2 November 2015 and 26 May 2016, the Company continues to work closely with its legal advisors in preparing for trial at the High Court of Justice in London. The date for the trial has been set for 30 January 2017.

The Company remains confident of a positive outcome of the upcoming trial and will update shareholders following the trial, or if there are any material developments in the meantime.

Alberto Lavandeira, CEO, commented:

"The progress that has been made by our team in moving the plant closer to nameplate capacity ahead of schedule and under budget is impressive. When we factor in the improved knowledge of the orebody gained from our recent Reserves and Resources update which has extended the life of mine, increased mineable reserves and will lead to greater efficiencies, it confirms our belief that Proyecto Riotinto has a viable future for many years to come".

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) No 596/2014.

 

Contacts:

Atalaya Mining plc

Roger Davey / Alberto Lavandeira

+34 959 59 28 50

Canaccord Genuity (NOMAD and Joint Broker)

Henry Fitzgerald-O'Connor / Martin Davison

+44 20 7523 8000

BMO Capital Markets (Joint Broker)

Jeffrey Couch/Neil Haycock/Tom Rider

+44 20 7236 1010

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDKZLFLQDFZBBB
Date   Source Headline
11th Apr 20247:00 amRNSQ1 2024 Operations Update
19th Mar 20247:00 amRNS2023 Annual Results
8th Mar 20247:00 amRNSNotice of 2023 Annual Results
9th Feb 20247:00 amRNSIssue of Equity
18th Jan 20247:00 amRNSQ4 Operations Update and 2024 Production Guidance
21st Dec 20237:01 amRNSUpdate on Move to Main Market
21st Dec 20237:00 amRNSHolding(s) in Company
21st Dec 20237:00 amRNSHolding(s) in Company
20th Dec 20237:00 amRNSHolding(s) in Company
14th Dec 20231:49 pmRNSExtension of Port Handling Agreement
12th Dec 202311:28 amRNSResults of the 2023 Extraordinary General Meeting
12th Dec 20237:00 amRNS2023 Extraordinary General Meeting Statement
1st Dec 20237:00 amRNSHistorical Related Party Transactions
20th Nov 20237:00 amRNSHolding(s) in Company
16th Nov 20237:00 amRNSQ3 and YTD 2023 Financial Results
14th Nov 20237:00 amRNSProposed Re-domiciliation and Notice of EGM
13th Nov 20237:00 amRNSIntention to Move from AIM to Main Market
2nd Nov 20237:00 amRNSNotice of Q3 and YTD 2023 Financial Results
12th Oct 20237:00 amRNSQ3 2023 Operations Update
10th Oct 20233:11 pmRNSDirector/PDMR Shareholding
12th Sep 20237:00 amRNSInterim Dividend Foreign Exchange Rates
10th Aug 20237:00 amRNSQ2 and H1 2023 Financial Results
27th Jul 20237:00 amRNSNotice of Q2 and H1 2023 Financial Results
20th Jul 20237:00 amRNSFinal Dividend Foreign Exchange Rates & Payment
20th Jul 20237:00 amRNSCorrection to Q2 Provisional Revenue Adjustments
12th Jul 20237:00 amRNSQ2 2023 Operations Update
10th Jul 20237:00 amRNSPDMR Shareholding
29th Jun 20237:00 amRNS2022 Final Dividend Timetable
28th Jun 202311:25 amRNSResults of the 2023 Annual General Meeting
28th Jun 20237:00 amRNS2023 Annual General Meeting Statement
26th Jun 20237:00 amRNSReport on Payments to Governments
26th Jun 20237:00 amRNSApproval to Cease to be Reporting in Canada
1st Jun 20237:00 amRNSNotice of AGM
30th May 20237:00 amRNSApplication to Cease to be a Reporting Issuer
23rd May 20237:00 amRNSGrant of Share Options and PDMR Notification
16th May 20237:00 amRNSPublication of 2022 Sustainability Report
15th May 20237:00 amRNSQ1 2023 Financial Results
2nd May 20237:00 amRNSNotice of Q1 2023 Results
17th Apr 20237:00 amRNSQ1 2023 Operations Update
28th Mar 20237:00 amRNSEnvironmental Authorisation Granted to PMV
24th Mar 20237:00 amRNSFiling of New Riotinto PEA Technical Report
23rd Mar 20234:35 pmRNSPrice Monitoring Extension
22nd Mar 20237:00 amRNS2022 Annual Results
15th Mar 20237:00 amRNSNotice of 2022 Annual Results
13th Mar 20237:00 amRNSUpdate on Voluntary Delisting From The TSX
23rd Feb 20237:00 amRNSResults of New PEA for Riotinto
20th Feb 20237:00 amRNSVoluntary Delisting from the TSX
17th Jan 20237:00 amRNSQ4 Operations Update and 2023 Production Guidance
12th Jan 20237:00 amRNSHolding(s) in Company
24th Nov 20227:00 amRNSUpdate on Exploration Activities

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.